Method for opening cave in self-balancing type supporting and load bearing wall body
A self-balancing, wall-based technology, applied in the direction of walls, building maintenance, building components, etc., can solve the problems of large self-weight load, high cost, and long construction period of the wall, and achieve the effect of good effect and low cost
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0030] Embodiment 1: as Figure 1~3 As shown, this embodiment includes the following steps:
[0031] 1) On the wall 11 where the hole 7 needs to be opened, a number of process holes 1 are set at intervals along the same height in the horizontal direction, and monitoring points are arranged;
[0032] 2) Place the prefabricated I-shaped steel support 5 in each of the above-mentioned process holes 1 for supporting the upper ring beam, floor and wall 6, and place the steel support 5 behind each process hole 1, Use a steel wedge to tighten the upper and lower sides of the steel support and the process hole, and then fill the gap between the steel support and the inner wall of the process hole with high-strength non-shrinkage grouting material or epoxy mortar.
[0033] 3) After the grouting material of the process holes opened at intervals for the first time reaches the design strength, other process holes are opened at intervals, and the prefabricated I-shaped steel support 5 is p...
Embodiment 2
[0041] Example 2, such as Figure 4 , 5 shown. This embodiment is basically the same as Embodiment 1, except that the steel support is a square-shaped steel support 9, and the axial direction of the square-shaped steel support is parallel to the horizontal direction of the wall. Pass the steel plates forming the zigzag steel structure support beam 3 through the zigzag steel support 9 along the direction of the horizontal groove, weld the steel plates forming the zigzag steel structure support girder 3 into a whole, and then connect each zigzag steel support 9 with the zigzag The zigzagging steel structure support beam 3 is welded as one to form an integral steel support beam 2, and then the zigzag steel structure support beam 3 is poured compactly with fine stone concrete or high-strength non-shrinkage grouting material. The width of zigzag steel bearing 9 is wider than the thickness of body of wall 1cm.
Embodiment 3
[0042] Embodiment 3 is basically the same as Embodiment 1, except that the steel support adopts a square steel support 9, and the axial direction of the square steel support is parallel to the horizontal direction of the wall. Pass the steel plates forming the I-shaped steel structure support beam 8 through the mouth-shaped steel support 9 along the direction of the horizontal groove, weld the steel plates forming the I-shaped steel structure support beam 8 into a whole, and then connect each mouth-shaped steel support 9 with the I-shaped steel support Zigzag steel structure support beam 8 is welded as a whole, becomes integral type steel support beam 2. The width of zigzag steel bearing 9 is wider than the thickness of body of wall 2cm.