A technology of transmission tower and design method, which is applied in the direction of infrastructure engineering, construction, etc., can solve the difficulty of safe and stable operation of transmission lines, the destruction of iron towers, the calculation of the internal force of the foundation thickness of the composite protective plate, and the cross-section design. No specific and feasible methods are proposed And other issues
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0019] The implementation of the patent of the present invention will be further described below in conjunction with the accompanying drawings, specifically divided into the following steps:
[0020] 1. Determine the thickness H, m of the composite protective plate foundation according to 1 / 45 to 1 / 25 of the base opening of the transmission tower. When the root opening is greater than or equal to 30m, the foundation thickness shall be 1 / 45 of the root opening and not greater than 800mm; when the root opening is less than or equal to 10m, the foundation thickness shall be 1 / 25 of the root opening and not less than 200mm; Linear interpolation calculates the thickness of the foundation.
[0021] 2. By formula: Calculate the average net reaction force σ of the foundation of the transmission tower composite protection plate under the action of the upper independent foundation and the self-weight of the tower structure 0 , MPa; where G DJ is the total weight of the upper indepen...