Blasting dehumidification system for multiple blast furnaces and control method of blasting dehumidification system
A control method and blast furnace blasting technology, applied in humidity control, blast furnace, blast furnace details, etc., can solve the problems of unbalanced use of refrigeration equipment capacity and inability to flexibly adjust the operation mode of refrigeration equipment, so as to improve the overall utilization rate and avoid system Overall failure, flexible adjustment effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
example 1
[0056] Example 1: The operation mode of the dehumidification system above working condition point 3 (1#, 2# fans are running, 3# fans are in standby)
[0057] 1#~4# refrigeration units are running, the total cooling load is 12 million kcal / h, and the cooling capacity required by the dehumidification device is 10 million to 13 million kcal / h
[0058] Cold water pipe valve LS 3#~14# valve is fully open, LS 1#~2# valve is fully closed
[0059] Steam pipeline valve ZQ 1#~4# valve fully open
[0060] Circulating water pipeline valve XH 11#, 12#, 21#, 22#, 31#, 32#, 41#, 42# valve fully open
[0061] Refrigeration unit inlet and outlet cold water valve SB11#, 12#, 13#, 21#, 22#, 23#, 31#, 32#, 33#, 41#, 42#,
[0062] 43# valve fully open
example 2
[0063] Example 2: Operation mode of refrigeration equipment under working condition point 4 (1# and 2# fans are running, 3# fans are in standby)
[0064] It can operate 1#~3# refrigeration unit, 4# refrigeration unit is standby, the total cooling load is 9 million kcal / h, and the cooling capacity required by the dehumidification device is 8.5 million kcal / h
[0065] Cold water pipe valve LS 3#~14# valve is fully open, LS 1#~2# valve is fully closed
[0066] Steam pipeline valve ZQ 1#~3# valve is fully open, ZQ 4# valve is fully closed
[0067] Circulating water pipeline valves XH 11#, 12#, 21#, 22#, 31#, 32# valves are fully open, XH41#, 42# valves are fully closed
[0068] SB11#, 12#, 13#, 21#, 22#, 23#, 31#, 32#, 33# valves of the inlet and outlet cold water valves of the refrigeration unit are fully open, and SB41#, 42#, 43# valves are fully closed
example 3
[0069] Example 3: Example of adjusting the operation mode of refrigeration equipment under working condition point 4: (1# and 2# fans are operated, 3# fans are standby, Turn to 1#, 3# fan operation, 2# fan standby)
[0070] It can operate 1#~3# refrigeration unit, 4# refrigeration unit is standby, the total cooling load is 9 million kcal / h, and the cooling capacity required by the dehumidification device is 8.5 million kcal / h
[0071] Cold water pipeline valves LS 1#~6#, 9#~14# valves are fully open, LS 7#~8# valves are fully closed
[0072] Steam pipeline valve ZQ 1#~3# valve is fully open, ZQ 4# valve is fully closed
[0073] Circulating water pipeline valves XH 11#, 12#, 21#, 22#, 31#, 32# valves are fully open, XH41#, 42# valves are fully closed Refrigeration unit inlet and outlet cold water valves SB11#, 12#, 13#, 21 #, 22#, 23#, 31#, 32#, 33# valves are fully open, SB41#, 42#, 43# valves are fully closed
[0074] From the above example, it can be seen that as the a...