Construction method for guide wall of clean water tank
A construction method and clean water pool technology, applied in the field of water purification plants, can solve problems such as unsuitable diversion walls, and achieve the effect of reducing human errors
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0049] (1) laying plain concrete cushion 1, described plain concrete cushion 1 is a back-shaped structure, wherein the elevation of the cushion of the mouth-shaped position of the inner ring is higher than the elevation of the cushion of the mouth-shaped position of the outer ring;
[0050] (2) A base plate deformation joint 10 is set in the transverse middle part of the cushion layer 1. The construction method of the base plate deformation joint 10 is as follows: install the lower end low-foaming polystyrene in sequence from bottom to top at the set base plate deformation joint 10 position. An ethylene caulking board, a rubber waterstop and an upper low-foaming polyethylene caulking board, the top level of the upper low-foaming polyethylene caulking board is higher than the top level of the reinforced concrete bottom plate 2 to be poured.
[0051] (3) Reserve a base plate reserved belt at the longitudinal middle part of the cushion layer 1 on both sides of the base plate defor...