A technology of concrete and bored piles, which is applied in construction and foundation structure engineering, etc. It can solve problems such as troublesome construction, insufficient strength of a single pile, and affecting the overall safety and stability of the foundation and foundation, and achieves the effect of simple operation and low cost of use
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0021] Example: such as Figure 1-7 As shown, a method for pouring concrete conduits of bored piles according to the present invention. First, a leak test is performed on a conduit 1 composed of a plurality of steel pipes; after the test is completed, a storage hopper 4 is installed at one end of the conduit 1; Place it in the pile hole 6; after placing the conduit 1, install the sealing plate 5 on the bottom of the storage hopper 4; pour concrete into the storage hopper 4 after the sealing plate 5 is installed; then pull out the sealing plate 5 , into the concrete and the pile hole 6; repeat the above steps of pouring into the concrete. Repeat intervals are less than 30 minutes.
[0022] The conduit 1 is composed of several steel pipes, and a sealing ring 3 is arranged between the steel pipes and fixed by a flange 2 . Fixed steel plates 7 are arranged on both sides of the hole of the pile hole 6 . The distance between the bottom of the conduit 1 and the poured concrete top...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 