The method of carbon dioxide phase change coal seam cracker to treat the floor drum of coal mine roadway
A technology of carbon dioxide and coal mine roadway, applied in drilling equipment and methods, mining equipment, earthwork drilling and other directions, can solve the problems of flying out and poor effect, and achieve the effects of high efficiency, avoiding hidden dangers of flying out and convenient operation.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
no. 1 example
[0017] see figure 1 , figure 2 , image 3 , Figure 4 , a carbon dioxide phase-change coal seam cracker treatment method for coal mine roadway floor drum, characterized in that: determine the maximum length of the minimum resistance line 31: W max =[pgdt / (r.u)] 1 / 2 , where: W max is the maximum length of the minimum resistance line 31, m; p is the burst pressure, MPa; g is the acceleration of gravity, 9.8m / s 2 ;d is the diameter of the borehole, m; t is the blasting action time, s; r is the specific gravity of the rock, t / m 3 ; u is the minimum moving speed that must be passed to the rock, m / s, and the angle α=arctan (W max / S), degrees; where: S is the length of the blasting point from the orifice, m; according to the result of the above formula, a single hole is drilled on the floor drum 2 of the roadway when drilling a single hole; After the first drill hole is drilled at the rightmost end, the depth of the drill hole ensures that the blast hole position 30 of the c...
no. 2 example
[0019] see figure 1 , figure 2 , image 3 , Figure 4 , a carbon dioxide phase-change coal seam cracker treatment method for coal mine roadway floor drum, characterized in that: determine the maximum length of the minimum resistance line 31: W max =[pgdt / (r.u)] 1 / 2 , where: W max is the maximum length of the minimum resistance line 31, m; p is the burst pressure, MPa; g is the acceleration of gravity, 9.8m / s 2 ;d is the diameter of the borehole, m; t is the blasting action time, s; r is the specific gravity of the rock, t / m 3 ; u is the minimum moving speed that must be passed to the rock, m / s, and the angle α=arctan (W max / S), degrees; where: S is the length of the blasting point from the orifice, m; according to the result of the above formula, a single hole is drilled on the floor drum 2 of the roadway when drilling a single hole; After the first drill hole is drilled at the rightmost end, the depth of the drill hole ensures that the blast hole position 30 of the c...
no. 3 example
[0022] see figure 1 , figure 2 , image 3 , Figure 4 , a carbon dioxide phase-change coal seam cracker treatment method for coal mine roadway floor drum, characterized in that: determine the maximum length of the minimum resistance line 31: W max =[pgdt / (r.u)] 1 / 2 , where: W max is the maximum length of the minimum resistance line 31, m; p is the burst pressure, MPa; g is the acceleration of gravity, 9.8m / s 2 ;d is the diameter of the borehole, m; t is the blasting action time, s; r is the specific gravity of the rock, t / m 3 ; u is the minimum moving speed that must be passed to the rock, m / s, and the angle α=arctan (W max / S), degrees; where: S is the length of the blasting point from the orifice, m; according to the result of the above formula, a single hole is drilled on the floor drum 2 of the roadway when drilling a single hole; After the first drill hole is drilled at the rightmost end, the depth of the drill hole ensures that the blast hole position 30 of the c...