Device and method for performing DC ice melting on overhead ground wire of power transmission line
An overhead ground wire, DC ice-melting technology, applied in the direction of overhead installation, cable installation, electrical components, etc., can solve the problems of high cost of ground wire insulation and segmental transformation, long time of ice-melting operation, etc., to reduce line maintenance Effects of cost, increased selection flexibility, and reduced short-circuit time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0022] Such as figure 1 As shown in the figure, a device for DC deicing the overhead ground wire of transmission lines, including 5 segmented towers, overhead ground wires, AC three-phase power supply, DC deicing device, first wire, second wire, segmented ground line, grounding knife switch KG, automatic wiring device KN; the five segmented towers are segmented tower 1, segmented tower 2 ... segmented tower 5, and the first wire, the second wire and The power grid is isolated and insulated from the ground, the short-connection point of the first wire is on the even-numbered segment tower, the short-connection point of the second wire is on the odd-numbered segment tower, and the overhead ground wire is insulated from the ground and divided The segment is grounded through a plurality of grounding knife gates KG, each of the segmented towers is short-circuited with the first conductor or the second conductor and the overhead ground wire through an automatic wiring device KN, and...
Embodiment 2
[0024] Such as figure 2 As shown, the difference from Embodiment 1 is that for a special section with a shorter distance between the segmented towers (generally less than 10 km), the two sides of the segmented overhead ground wire are connected in series and connected in parallel between the first conductor and the second conductor.
Embodiment 3
[0026] A method for direct current melting of overhead ground wires of power transmission lines, comprising the following steps:
[0027] S1) Operate and confirm that the first conductor, the second conductor and the overhead ground wire are isolated from the power grid, and open all the grounding knife switches KG to insulate the entire overhead ground wire from the ground;
[0028] S2) Close the automatic wiring device KN that needs to melt the ice segment to short-circuit the first wire, the second wire and the overhead ground wire;
[0029] S3) Close the ice-melting device and connect it to the knife switch K, start the DC ice-melting device to output the minimum ice-melting current, and gradually increase the DC current within the range of the minimum ice-melting current and the maximum ice-melting current according to the site conditions until the ice cover melts and falls off, Stop the output of the DC ice-melting device, and disconnect the switch K to isolate the first...