A construction method of pile-pier integrated structure

A construction method and technology for piles and piers, applied in the field of pile foundations and bridge piers, can solve the problems of lack of uplift resistance and buckling resistance, lack of applicable standards or methods, and achieve good uplift resistance and buckling resistance, and the control of positioning accuracy is easy. , The effect of convenient position adjustment

Active Publication Date: 2019-02-22
THE 5TH ENG CO LTD OF CHINA RAILWAY 25TH BUREAU GRP +1
View PDF4 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Existing pile foundations and bridge piers are mainly used for vertically supported buildings such as bridges, and the loads they bear are also vertically directed to the ground, so there are very high requirements for the compressive capacity of pile foundations and bridge piers, but for some For buildings with lateral load or bending moment, the existing pile foundations and bridge piers lack sufficient resistance to pullout and flexural resistance, resulting in the need for a large number of reinforcements when applied to these buildings, and the lack of applicable standards or methods that can be promoted

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A construction method of pile-pier integrated structure
  • A construction method of pile-pier integrated structure
  • A construction method of pile-pier integrated structure

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0021] A pile-pier integrated structure includes a bored pile foundation 1 and a bridge pier 2, the top of the bored pile foundation is higher than the ground, and the scoop pile boundary line of the bored pile foundation is lower than the ground by a certain distance, and the reinforcement cage of the foundation pile extends from the bottom To the top; the bottom of the pier is buried in the foundation pile, and placed on the scoop pile boundary line, the side wall surface of the part of the bottom of the pier located under the ground is covered with horizontally protruding studs 4, which are fixed outside the studs to surround the pier The bottom has reinforcement cage 3, and the top of reinforcement cage is higher than ground. Such as figure 1 , 2 As shown, the horizontal line M in the figure is the ground line, and the horizontal line N is the scoop pile boundary line. The reinforcement cage is set between these two horizontal lines. It is not only installed in the bored ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method for a pile and pier integrated structure. The method includes the steps that an underground pile foundation is constructed at first, and then pile and pier connecting construction is performed; afterwards, an underground tool and a ground tool are installed in sequence, and hoisting and accurate adjusting of the pier position are conducted after installation is completed; and finally concrete is poured to the pile and pier connecting position. The underground tool is arranged between a pile ladling boundary line and a pier bottom, position adjustment of a pier is greatly facilitated after the pier is changed to be in a floor pier mode from a suspended pier form, and thus pier positioning precision can be controlled more easily. Moreover, by the adoption of a limiting space formed by longitudinal and transverse limiting baffles arranged at the top of the underground tool, when the pier is inserted into the limiting space, the pier can be preliminarily positioned naturally, and therefore the pier can be accurately positioned only through fine adjustment of the pier position on this basis, and the process of pier positioning is simplified.

Description

technical field [0001] The invention relates to a pile foundation and a bridge pier, in particular to a construction method for an integrated structure of a pile foundation and a bridge pier. Background technique [0002] The pile foundation is composed of foundation piles buried in the ground and caps connected to the pile tops, and bridge piers are piers built above the caps for support. Existing pile foundations and bridge piers are mainly used for vertically supported buildings such as bridges, and the loads they bear are also vertically directed to the ground, so there are very high requirements for the compressive capacity of pile foundations and bridge piers, but for some For buildings with lateral load or bending moment, the existing pile foundations and bridge piers lack sufficient resistance to pullout and flexure, resulting in the need for a large number of reinforcements when applied to these buildings, and there is a lack of applicable standards or methods that ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D27/12E01D19/02
CPCE01D19/02E02D27/12E02D2250/0023
Inventor 孙青霞葛国庆王有旗张旭海鲍汝苍刘国山范佰通窦鸿
Owner THE 5TH ENG CO LTD OF CHINA RAILWAY 25TH BUREAU GRP