A construction method and corrugated pipe technology, which is applied in the construction field of piece-assembled steel corrugated pipe forming culverts, can solve problems such as unfavorable subgrade culvert construction, concrete structures that are difficult to meet quality and construction period requirements, and achieve simplified construction procedures and shortened construction periods. , to ensure the rapid formation of the effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0025] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
[0026] like figure 1 , 2 , 3, 4, 5, and 6, the construction method of the piece-assembled steel bellows forming culvert of the present invention can shorten the construction period of the subgrade culvert and road construction, ensure the rapid formation of the subgrade culvert under complex geological conditions, and realize Mass effect of complete structure of subgrade culvert. The present invention comprises the steps:
[0027] (1) Excavate the location of the culvert according to the requirements of the process design to form the foundation pit of the culvert; when the base soil is bad soil layer such as silt, it should be replaced and filled; over-excavation should be avoided, if over-excavation, the loose part should be removed ;The soil foundation pit dug to the elevation shall not be exposed, disturbed or soaked for a long time, and ...