Construction method of continuous laying of sand and gravel dam in high altitude area

A sand-gravel dam and construction method technology, applied in the field of water conservancy and hydropower engineering, can solve the problem that physical and mechanical properties will be affected by plateau environmental factors, the thickness of the asphalt concrete layer should not be greater than 25cm, thin, and the daily minimum temperature is even less than -20 ℃, The annual wind power is greater than level 4, and there are occasional problems such as light rain and snow, so as to achieve the effect of high paving efficiency, reducing heat loss rate and reducing construction process.

Active Publication Date: 2019-06-25
SINOHYDRO FOUND ENG
View PDF3 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] 3. The thickness of the asphalt concrete layer paved in a single layer shall not be greater than 25cm;
[0010] However, due to the development of water conservancy and hydropower projects, it is often necessary to work in high-altitude areas. These areas are high-cold and hypoxic, and the air is thin. The amount is sometimes greater than 10mm), in these areas, the physical and mechanical properties of asphalt materials and asphalt concrete will be affected by plateau environmental factors. Quality and safety, construction methods to improve construction efficiency

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of continuous laying of sand and gravel dam in high altitude area
  • Construction method of continuous laying of sand and gravel dam in high altitude area
  • Construction method of continuous laying of sand and gravel dam in high altitude area

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0047] Such as figure 1 Shown, be the flow chart of the construction method of the continuous laying of sand and gravel dam in high altitude area of ​​the present invention, as can be seen from the figure, method of the present invention comprises:

[0048] The dam shell material used to form the sand and gravel dam with a water content between 4.1% and 4.4% is obtained by taking sand and gravel materials and draining water from the stockyard in the reservoir area at high altitude;

[0049] A pair of lower dam shell material layers are formed by laying the dam shell material on the dam site on both sides of the base of the asphalt concrete core wall to be paved;

[0050] Carry out rolling treatment to a pair of lower dam shell material layers by a rolling machine, so as to compact the dam shell material of the lower dam shell material layer;

[0051] Based on the compacted pair of lower dam shell material layers, the dam shell material is laid layer by layer from bottom to top,...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
thicknessaaaaaaaaaa
heightaaaaaaaaaa
thicknessaaaaaaaaaa
Login to View More

Abstract

The invention discloses a construction method for continuous laying of a gravel dam in a high attitude area. The construction method comprises the following steps: allowing a pair of lower dam shell material layers to be formed; compacting the lower dam shell material layers; and taking the lower dam shell material layers as the foundation, laying dam shell materials layer by layer from bottom to top, and performing rolling compaction layer by layer to form a pair of gravel dams with the dam temperature being in field distribution, wherein the step of laying the dam shell materials layer by layer comprises the following sub-steps: performing loosening treatment on the frozen surfaces of the lower dam shell material layers under the condition that the daily average solar radiation amount of the daytime is 4.53*10[11]-6.43*10[11] MJ; and laying the dam shell materials on the loosened surfaces of the lower dam shell material layers, so that each of the previously laid lower dam shell material layers is covered with a newly laid upper dam shell material layer, and the temperature of the lower dam shell material layers is improved. According to the construction method for continuous laying of the gravel dam in the high attitude area, the specific sunshine condition in the high attitude area is utilized, the dam shell materials are directly laid on the surfaces of the laid lower dam shell material layers, so that the conduction function of heat energy in the previously laid lower dam shell material layers is utilized, the previously laid lower dam shell material layers and the newly laid upper dam shell material layers are densely combined, the construction is carried out smoothly, and the construction efficiency is increased.

Description

technical field [0001] The invention relates to the field of water conservancy and hydropower engineering, in particular to a construction method for continuously laying sand and gravel dams in high-altitude areas. Background technique [0002] With the rapid development of domestic water conservancy and hydropower engineering construction, the treatment scope, depth, and stratum structure are becoming more complicated and diversified. In the prior art, when constructing asphalt concrete core wall dams, it is often necessary to follow the water conservancy and hydropower construction specifications, as stipulated in the specifications: [0003] 1. Construction can only be carried out when the minimum temperature is greater than 0°C, the wind force is less than level 4, and the daily precipitation is less than 5mm; [0004] 2. In the process of laying asphalt concrete, the surface temperature of the lower layer of asphalt concrete layer laid first must be above 70 °C before ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02B7/08E02D17/18
CPCE02B7/08E02D17/18
Inventor 王海艳万志杰娄旭峰陈龙刘典忠刘建发韩伟肖恩尚石峰孙亮周培祥陆卫东
Owner SINOHYDRO FOUND ENG