Rapid Construction Method of Asphalt Concrete Core Wall in High Altitude Area

A technology of asphalt concrete and construction method, which is applied in the direction of wall dams, foundation structure engineering, construction, etc., can solve the problem of thin, daily minimum temperature even less than -20 ℃, year-round wind force greater than 4, occasional light rain and snow, physical The mechanical properties will be affected by plateau environmental factors, and the thickness of the asphalt concrete layer should not be greater than 25cm, so as to achieve the effects of high paving efficiency, shortening the rolling time, and reducing the speed of heat loss

Active Publication Date: 2019-08-23
SINOHYDRO FOUND ENG
View PDF2 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] 3. The thickness of the asphalt concrete layer paved in a single layer shall not be greater than 25cm;
[0009] According to the above specification, above 3,000 meters above sea level, the daily minimum temperature is less than 0°C, the wind force is greater than level 4, and the daily precipitation is greater than 5mm. At this time, the construction of the asphalt concrete core wall dam will not be possible.
[0010] However, due to the development of water conservancy and hydropower projects, it is often necessary to work in high-altitude areas. These areas are high-cold and hypoxic, and the air is thin. The amount is sometimes greater than 10mm), in these areas, the physical and mechanical properties of asphalt materials and asphalt concrete will be affected by plateau environmental factors. Quality and safety, construction methods to improve construction efficiency

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Rapid Construction Method of Asphalt Concrete Core Wall in High Altitude Area
  • Rapid Construction Method of Asphalt Concrete Core Wall in High Altitude Area
  • Rapid Construction Method of Asphalt Concrete Core Wall in High Altitude Area

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0049] Such as figure 1 Shown, be the flow chart of the fast construction method of bituminous concrete core wall in the high altitude area of ​​the present invention, as can be seen from the figure, the method of the present invention comprises:

[0050] Preparation of asphalt concrete with local sand and gravel at high altitudes as aggregate;

[0051] Preparation of transition material with local sand and gravel as raw material;

[0052] Pave the prepared asphalt concrete and transition material on the asphalt concrete base at one time, so as to form an asphalt concrete layer and a pair of transition material layers on both sides of the asphalt concrete layer on the base;

[0053] Roll the asphalt concrete layer and the transition material layer with a roller compactor exceeding the existing rolling weight standard, so that the average porosity of the asphalt concrete after final rolling is less than 2%;

[0054] Repeat the above steps, adopt the method of one-time simulta...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
thicknessaaaaaaaaaa
particle diameteraaaaaaaaaa
particle diameteraaaaaaaaaa
Login to View More

Abstract

The invention discloses a high-attitude-area bituminous concrete core wall rapid construction method. The high-attitude-area bituminous concrete core wall rapid construction method comprises the steps that bituminous concrete and transitional materials are simultaneously laid on a bituminous concrete base at a time, so that a bituminous concrete layer and a pair of transitional material layers located on the two sides of the bituminous concrete layer are formed on the base; three rolling machines exceeding the existing normative standards are adopted to be distributed in a delta shape to roll the bituminous concrete layer and the pair of transitional material layers; and the steps are repeated, the methods of one-time simultaneous laying and over-rolling-weight-standard rolling are adopted, and a bituminous concrete core wall which is not provided with bonding faces between every two adjacent layers and a pair of transitional material straps located on the two sides of the bituminous concrete core wall are formed. According to the high-attitude-area bituminous concrete core wall rapid construction method, the bituminous concrete and the transitional materials are simultaneously laid at a time, the laying efficiency is high, the three rolling machines are adopted for simultaneous rolling after laying, the rolling efficiency is high, the heat dissipation speed of the laid bituminous concrete is decreased, the bituminous concrete can be directly laid on the laid bituminous concrete, the construction work procedure is reduced, and the construction efficiency is improved.

Description

technical field [0001] The invention relates to the field of water conservancy and hydropower engineering, in particular to a rapid construction method for asphalt concrete core walls in high-altitude areas. Background technique [0002] With the rapid development of domestic water conservancy and hydropower engineering construction, the treatment scope, depth, and stratum structure are becoming more complicated and diversified. In the prior art, when constructing asphalt concrete core wall dams, it is often necessary to follow the water conservancy and hydropower construction specifications, as stipulated in the specifications: [0003] 1. Construction can only be carried out when the minimum temperature is greater than 0°C, the wind force is less than level 4, and the daily precipitation is less than 5mm; [0004] 2. In the process of laying asphalt concrete, the surface temperature of the lower layer of asphalt concrete layer laid first must be above 70 °C before the upp...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02B7/08E02D15/02C04B26/26
Inventor 陈龙李浩路孙亮刘典忠刘建发韩伟肖恩尚石峰娄旭峰王海艳周培祥陆卫东