Construction method of full-section grouting shield in water-rich rock formation under sensitive buildings
A construction method and building technology, which is applied to earth drilling, underground chambers, shaft equipment, etc., can solve problems such as difficult to meet expected quality requirements and progress goals, shield tunneling cannot be normally excavated, and high water content in soil bins, etc., to achieve Control surface subsidence, reduce groundwater loss, and ensure safety
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0027] The present invention will be further described below in combination with specific embodiments and accompanying drawings.
[0028] An intercity rail project in Nanhai District, Foshan City, Guangdong Province. A shield tunnel in the project has a buried depth of 47.5 meters and a water head height of 35 to 39 meters. The tunnel body is made of Tertiary gravel-bearing sandstone with well-developed rock mass joints and fissures , the face of the tunnel has relatively large fissure water, and the bedrock fissure water in the tunnel body has certain connectivity with the pore water of the Quaternary overburden. The surface of this section of the tunnel is a textile city, and some buildings are sensitive to groundwater loss, and some settlement and cracking have occurred before the shield tunnel passed through. In view of the above situation, the construction method of the full-section grouting shield under the water-rich rock layer under the sensitive building according to ...