An installation method and steel structure technology, applied in the direction of building types, buildings, towers, etc., can solve the problems of installation component volume, installation height and installation environment restrictions, and achieve the goals of saving measures, ensuring project quality, and speeding up construction progress Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0037] The present invention will be further explained in detail below in conjunction with the accompanying drawings and specific embodiments, but it should be understood that the protection scope of the present invention is not limited by the specific embodiments.
[0038] The jacking equipment and construction method of tubular high-rise steel structure, the specific steps are:
[0039] (1) Component deepening and optimization
[0040] Detailed design steps: establish the overall model of the structure → assemble and segment on site (transportation segment) → process and manufacture segments → decompose into components and nodes → combine processes, materials, welds, structural design instructions, etc. → detailed design drawings.
[0041] (2) Selection of hoisting machinery
[0042] The steel structure should be all within the coverage of the tower crane 16, the hoisting height should not be too large, the weight of the segmented components should be within a certain range...