Unlock instant, AI-driven research and patent intelligence for your innovation.

High-viscosity thick filling soil layer pore-forming method

A high-viscosity, hole-forming technology, applied in drilling equipment and methods, earth-moving drilling, drilling equipment, etc., can solve problems such as high cost, inability to pull out steel pipes, and difficulty in lowering casing, ensuring quality and avoiding difficulties in lowering. or blocking effect

Inactive Publication Date: 2018-09-28
上海元易勘测设计有限公司
View PDF7 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The full-casing drilling process has disadvantages such as difficulty in lowering the casing and high cost. After the hole is completed, the submerged steel pipe often cannot be pulled out.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • High-viscosity thick filling soil layer pore-forming method
  • High-viscosity thick filling soil layer pore-forming method
  • High-viscosity thick filling soil layer pore-forming method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0021] According to the attached Figure 1 ~ Figure 4 , give a preferred embodiment of the present invention, and give a detailed description, so that the functions and characteristics of the present invention can be better understood.

[0022] Please refer to 1~ Figure 4 , in this embodiment, the high-viscosity thick fill soil layer 2 has a thickness of 10.0m, the lower soil layer 3 is a clay layer with a thickness of 20.0m, and the lower part is bedrock. The burial depth of the downfall tube well 5 is 25.0m, and the hole diameter is 250mm. At the same time, a 160mm PVC pipe is used as the downfall tube well 5 .

[0023] A method for forming holes in high-viscosity thick fill strata according to an embodiment of the present invention, comprising steps:

[0024] S1: Select the drill bit of a rotary drilling rig 1 according to the diameter of the downcomer well 5, the diameter of the drill bit is greater than the diameter of the downcomer well 5; in the present embodiment, t...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a high-viscosity thick filling soil layer pore-forming method. The high-viscosity thick filling soil layer pore-forming method comprises the steps that S1, a drill bit of a rotary drilling rig is selected according to the diameter of a precipitation tube well, and the diameter of the drill bit is larger than that of the precipitation tube well; S2, parameters of first cementmortar are determined according to the requirements of the high-viscosity thick filling rotary pore-forming operation; S3, the selected drill bit is installed on the rotary drilling rig and drilled to the bottom of a high-viscosity thick filling soil layer by using a pore-forming method of a mud protection wall, and drilling is stopped; S4, parameters of second cement mortar are obtained by reconfiguring the cement mortar parameters, so that the performance of the cement mortar is compatible with a lower portion soil layer of the high-viscosity thick filling soil layer; and S5, a conventionaldig is used for continuing drilling to the specified depth and cleaning the hole in the formed hole of the rotary drilling rig, and the pore-forming of the precipitation tube well is completed. The high-viscosity thick filling soil layer pore-forming method can effectively form holes in high-viscosity thick fill soil layer, and has the advantage of avoiding difficulty of lowering or blockage of precipitation pipe well downhole caused by hole collapsing.

Description

technical field [0001] The invention relates to the field of hole formation in downwater tube wells in construction engineering, in particular to a method for forming holes in high-viscosity thick filling soil strata. Background technique [0002] The downfall tube well is widely used in the excavation process of foundation pit dewatering. It is suitable for silty clay, silty silty clay, clay silt, sandy silt and silt and other soil layers. It has a wide range of applications. Downfall tube wells are generally drilled with ordinary drill bits with a diameter of 250 mm. In high-viscosity thick fill strata, holes may collapse or even voids, and the success rate of hole formation is relatively low. The full-casing drilling process has disadvantages such as difficulty in lowering the casing and high cost. After the hole is completed, the problem that the sunken steel pipe cannot be pulled out often occurs. Contents of the invention [0003] In view of the deficiencies in the ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E21B7/00E02D19/10
CPCE21B7/00E02D19/10
Inventor 张昌伟郑亮亮耿敏王敦显奚磊朱成兵惠冠军于守跃潘海洋郭嫚
Owner 上海元易勘测设计有限公司