Device and method for assembling and disassembling truss coupling-beam type gantry crane in tunnel
A technology of connecting beams and inner trusses, applied in hoisting devices, hoisting equipment braking devices, cranes, etc., can solve problems such as inability to install gantry cranes, dismantling TBM roadheaders, and inability to install gantry cranes in tunnels. The effect of installation efficiency, solving construction problems and ensuring safety
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0046] see Figure 1-4, the truss in the tunnel is connected with the installation and disassembly device of the beam type portal crane, which includes the artificial tunnel excavation section 2, the upstream tunnel expansion section 3 is excavated after the artificial tunnel excavation section 2, and the tunnel expansion section is excavated after the upstream tunnel expansion section 3 Elevation section 5, tunnel expansion and excavation After the elevation section 5, a downstream tunnel expansion section 6 is excavated. After the downstream tunnel expansion section 6, a roadheader excavates a tunnel 7. The bottom of the artificial tunnel excavation section 2, the upstream tunnel expansion section 3, the tunnel expansion and heightening section 5 and the downstream tunnel expansion section 6 is laid with a portal crane track 1, and the portal crane track 1 is supported by double main girders. Type door machine 4. Further, the double main girder type door crane 4 includes a ...
Embodiment 2
[0052] The method for installing the door crane by using any one of the truss connection beam type door crane installation and disassembly devices in the tunnel described above includes the following steps:
[0053] Step1: Lay two portal crane tracks 1 at the bottom of the artificial tunnel excavation section 2, the upstream tunnel expansion section 3, the tunnel expansion section 5 and the downstream tunnel expansion section 6;
[0054] Step2: install the wheel box 8 on the track 1 of the door machine, and use a truck crane to hoist the bottom beams 9 of the two door machines onto the wheel boxes 8 on the track 1 of the two door machines;
[0055] Step3: After the two gantry bottom beams 9 are leveled, temporarily fix the gantry bottom beam 9 to the ground with rods 10, and then hoist the assembled contact beam 13 across the top of the two gantry bottom beams 9 , and use the rod 10 to temporarily fix the two, and then make the two form an integral structure;
[0056] Step4: ...