A Temporary Prestressed Anchor Segmented Prefabricated Cover Beam and Temporary Prestress Applying Method
A segmented prefabricated and prestressed technology, applied in bridges, bridge construction, bridge parts, etc., to save construction time, simplify processes, and reduce labor and financial costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0032] see Figure 1 to Figure 3 , in one embodiment, a segmented prefabricated cap beam, comprising: a middle section 1, a first cantilever section 2, a second cantilever section 3, a first shear key 7, a second shear key, a first prestressed Rib 4, the second prestressed tendon 5. Wherein, the first end of the first shear key 7 is arranged in the first end of the first cantilever section 2 . The first end of the second shear key is arranged in the first end of the second cantilever section 3 . The first end of the middle section 1 is provided with a first shear slot matching the second end of the first shear key 7, the first end of the first cantilever section 2 is connected with the first end of the middle section 1, and the first The shear key 7 cooperates with the first shear groove. The second end of the middle section 1 is provided with a second shear slot matching the second end of the second shear key, the first end of the second cantilever section 3 is connected t...
Embodiment 2
[0037] see Figure 6 , a temporary prestressing method for temporarily prestressed anchoring segmented prefabricated cover beams, which is used for the segmented prefabricated cover beams in the first embodiment above, and the specific steps are as follows:
[0038] S1: The hoisting middle section 1 is docked with the outer pier 6.
[0039] S2: apply epoxy splicing glue to joints of the first shear bond and the second shear bond;
[0040] S3: hoisting the first cantilever section 2 and the second cantilever section 3 to dock with the middle section 1 respectively.
[0041] S4: Install the first prestressed tendon 4 and the second prestressed tendon 5 in the first pipeline and the second pipeline respectively, adopt single-end tension anchorage, provide 0.3MPa temporary prestress, and perform grouting to seal the prestressed channel.
[0042] A more detailed expression of the construction steps in a specific implementation is as follows:
[0043]Step 1: Prefabricate the firs...
Embodiment 3
[0049] On the basis of Embodiment 1 and Embodiment 2, this embodiment is further explained through practical application examples.
[0050] Taking the cover beam with a total length of 25m as an example, the construction and installation steps are as follows:
[0051] Step 1: The first cantilever section 2, the second cantilever section 3 and the middle section 1 are poured in sections using short lines, the pouring concrete is C50, and the prestressed pipe is embedded at the upper end of the section. The prestressed pipe uses ZSM self-locking pipe. The first PVC pipes are reserved on both sides of the formwork of the cantilever section 2 and the second cantilever section 3, which is convenient for grouting the embedded pipes after tensioning. Pre-reinforcement in the shear channel before precast pouring.
[0052] Step 2: The lifting device first lifts the middle section 1, and paints a layer of epoxy resin on the splicing surface of the bridge pier and the middle section 1 t...