An urban construction engineering pipeline installation structure and construction method thereof
A technology for construction engineering and pipeline installation, applied in separation methods, chemical instruments and methods, pipes/pipe joints/pipe fittings, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0040] Such asfigure 1 As shown, a pipeline installation structure for urban construction projects includes a main pipe 1 and a branch pipe 4. A butt joint 2 is extended at the connection between the main pipe 1 and the branch pipe 4. 4 is provided with a connecting pipe 3, the connecting pipe 3 includes a pair of half-pipe 31, the half-pipe 31 is arranged symmetrically along the plane where the axis of the connecting pipe 3 is located, on the outside of the butt pipe 2 and the branch pipe 4 and at the opposite ends of the radial direction. A wedge-shaped block 5 is extended, and a caulking 32 is provided on the inner side of the half pipe 31 and at both ends in the axial direction, and a dovetail groove 33 is formed by milling from the caulking 32 on the inner side of the half pipe 31 around its axis;
[0041] Align the butt joint pipe 2 with the branch pipe 4, and then buckle a pair of half pipes 31 relative to each other, and align the socket 32 on the half pipe 31 with th...
Embodiment 2
[0046] Such as figure 1 As shown, a pipeline installation structure for urban construction projects includes a main pipe 1 and a branch pipe 4. A butt joint 2 is extended at the connection between the main pipe 1 and the branch pipe 4. 4 is provided with a connecting pipe 3, the connecting pipe 3 includes a pair of half-pipe 31, the half-pipe 31 is arranged symmetrically along the plane where the axis of the connecting pipe 3 is located, on the outside of the butt pipe 2 and the branch pipe 4 and at the opposite ends of the radial direction. A wedge-shaped block 5 is extended, and a caulking 32 is provided on the inner side of the half pipe 31 and at both ends in the axial direction, and a dovetail groove 33 is formed by milling from the caulking 32 on the inner side of the half pipe 31 around its axis;
[0047] Align the butt joint pipe 2 with the branch pipe 4, and then buckle a pair of half pipes 31 relative to each other, and align the socket 32 on the half pipe 31 with ...
Embodiment 3
[0055] A construction method for pipeline installation in urban construction engineering, comprising the following steps:
[0056] S1. Prepare the main pipe 1, the branch pipe 4 and the connecting pipe 3 as mentioned in the above-mentioned embodiment 1 or embodiment 2;
[0057] S2, the connecting rod 8 is hingedly installed before the half pipe 31, and the filter screen 9 is hingedly installed between the connecting rods 8;
[0058] S3. Align the butt joint 2 with the branch pipe 4, then align the wedge block 5 with the socket 32 of the half pipe 31, relatively move the half pipe 31, and then rotate the half pipe 31 around its axis.