A steel sleeve and sleeve grouting technology, which is applied to the processing of walls and building materials, structural elements, etc., can solve the problems of warehouse partition wall deformation, poor wall connection reliability, and inability to grout, etc., to achieve convenient construction, The effect of improving construction efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0024] like figure 1 Shown: a prefabricated wall reinforcement sleeve grouting process, which includes the following steps:
[0025] Step 1: The prefabricated wall is hoisted in place;
[0026] Step 2: Fine adjustment of the wall and installation of diagonal braces:
[0027] In order to ensure the accuracy of the installation position of the prefabricated wall and the location of the steel bars, the project department formulated the "seven-line control method" to control the installation location of the prefabricated wall and the location of the steel bars, that is, through the solid line of the wall and the horizontal position control line , Longitudinal position control line, elevation control line, slab seam center line, steel bar positioning line, and 1m elevation line on prefabricated wall panels are comprehensively controlled to ensure the accuracy of wall installation positions;
[0028] location line name effect Wall Solid Line Mark the installatio...