Method for dismantling pier and bearing platform at lower part of river-crossing bridge
A technology for bridge piers and bridges, which is applied in the field of bridge demolition and construction to achieve the effects of ensuring safety, facilitating cutting and construction, and facilitating hoisting
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0034] Taking a river-crossing bridge as an example, the lower piers and caps of the bridge set at the tidal flats are removed, as shown in figure 1 As shown, it includes pier 1, pier 1 lower cap 2 and the pile foundation connected to the lower part of pier 2, wherein the top of pier 1 is connected with No. 0 block 4; as image 3 As shown, pier 1 is a thin-walled hollow pier with a thickness of 4.2m and a width of 10.42m. The cross-section of pier 1 is a double-hole structure; Figure 5 and Figure 6 As shown, the size of the cap 2 at the lower part of the pier 1 is 11.36m in length x 5.5m in width x 2m in thickness. There are 8 pile foundations distributed at intervals under the cap 2. The pile foundations are arranged in two rows at the front and back, with four piles in each row.
[0035] combine Figure 1 to Figure 9 , to further illustrate a method for dismantling the lower piers and caps of bridges across the river, the specific steps are as follows,
[0036] Step 1. ...