Closure construction method for continuous rigid frame beam of lower dragging extra-large bridge
A technology for super-large bridges and rigid-frame girders, which is applied in the construction field of continuous rigid-frame girders for Xiatuo super-large bridges. It can solve the problems of unbalanced beams, large height differences, and low construction efficiency of the main bridge, so as to improve construction efficiency and speed up construction. Speed, the effect of ensuring the balance of the beam body
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0033] A kind of continuous rigid frame girder closing construction method of the lower drag super large bridge of the present embodiment, such as Figure 1-Figure 3 shown, including the following steps:
[0034] Step A, pre-construct the continuous slab girder of the approach bridge and the cover beam of the junction pier on both sides of the main bridge before the construction of the main bridge, and reserve tensioning operation holes on the cover beam of the junction pier and the continuous slab girder of the approach bridge;
[0035] Step B. Concrete pouring of No. 0# beam section is carried out on the top of the main pier and hanging baskets are installed on both sides of the No. 0# beam section concrete;
[0036] Step C, the hanging baskets on both sides are moved forward synchronously and symmetrically, and the subsequent cantilever beam sections are poured symmetrically until the middle span and side span;
[0037] Step D, performing mid-span closure in mid-span pouri...
Embodiment 2
[0046] This embodiment is further optimized on the basis of embodiment 1, such as figure 1 As shown, the step D includes the following sub-steps:
[0047] Step D1, after the mid-span closing section is poured, a 180t jacking force is applied to both ends of the mid-span closing section to ensure that the relative displacement of the mid-span is less than or equal to 8cm;
[0048] Step D2, installing a stiff frame on the mid-span closing section and forming a mold to bind the steel bars, and then closing and locking the stiff frame;
[0049] Step D3, pressurizing and counterweighting the closing section of the mid-span and pouring and pouring the closing section of the connecting mid-span, and then performing reinforced concrete curing;
[0050] Step D4, after the concrete is derived until the concrete strength reaches the standard, the longitudinal prestressed steel tendons in the span are stretched in batches and anchored and grouted.
[0051] According to embodiment 1, con...
Embodiment 3
[0062] This embodiment is further optimized on the basis of above-mentioned embodiment 1 or 2, such as figure 1 As shown, the step E includes the following sub-steps:
[0063] Step E1, pouring the cantilevered section of the side span in the unbalanced side span, and then stretching the longitudinal prestressed steel cables in the span in batches and anchoring and grouting;
[0064] Step E2, synchronously installing the rear anchor cables of the hinged piers at the side spans on both sides;
[0065] Step E3, pre-embed section steel on the junction pier, set up brackets on the pre-embedded section steel, and pour side span cast-in-place sections on the brackets;
[0066] Step E4, remove the ballast and counterweight of the mid-span and pour the side-span closing section to close the side-span, complete the erection of the hollow slab of the approach bridge and balance the weight of the junction pier.
[0067] After the mid-span closing construction is completed, the side-span...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 


