Buried pipeline construction method for sewage treatment plant
A technology for sewage treatment plant and pipeline construction, which is applied to pipeline supports, pipeline laying and maintenance, pipes/pipe joints/pipe fittings, etc. Diversity of functions, avoiding leakage of sewage, and ensuring the effect of accuracy
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0028] In order to make the technical means realized by the present invention, creative features, goals and effects easy to understand, the following combination Figure 1 to Figure 5 , to further elaborate the present invention.
[0029] A sewage treatment plant buried pipeline construction method, which uses a sewage treatment plant buried pipeline construction equipment, the sewage treatment plant buried pipeline construction equipment includes a base 1, a lifting unit 2 and a docking device 3, using The specific methods for the construction of buried pipelines by the above-mentioned sewage treatment plant buried pipeline construction equipment are as follows:
[0030] Step 1. Preparatory work: debug the construction equipment of the buried pipeline in the sewage treatment plant of the present invention, and move the equipment of the present invention into the foundation pit where the pipeline needs to be installed;
[0031] Step 2. Adjusting the position of the pipeline: ...