A double-track tunnel and tunnel technology, which is applied in mine/tunnel ventilation, tunnel, earthwork drilling and mining, etc., can solve the problems of long tunnel construction period and difficult construction of smoke exhaust system, so as to reduce the construction scale and difficulty, The effect of reducing construction risk and reducing construction difficulty
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0044] Such as Figure 3 ~ Figure 5 As shown, the smoke exhaust rescue system for a double-lane tunnel of the present invention includes a left-line tunnel 11 and a right-line tunnel 12 parallel to each other for vehicle passage, and is used to discharge smoke in the left-line tunnel 11 and the right-line tunnel 12. The smoke exhaust horizontal hole and the fan 4, the smoke exhaust horizontal hole includes: a connecting section 21, which is horizontally arranged between the left-line tunnel 11 and the right-line tunnel 12, and communicates with the left-line tunnel 11 and the right-line tunnel 12, with It is used to exhaust the smoke in the left-line tunnel 12; the smoke exhaust section 24 is arranged at the same level as the connecting section 21, one end communicates with the right-line tunnel 12, and the other end is arranged with a smoke exhaust port that communicates with the outside world for exhausting the left-line tunnel 11 and the flue gas in the right-hand tunnel 12...
Embodiment 2
[0049] Such as Figure 3 ~ Figure 5 As shown, a construction method of a double-line tunnel smoke exhaust rescue system of the present invention is used for the double-line tunnel smoke exhaust rescue system of construction embodiment one, comprising the following steps:
[0050] S1, according to the layout direction of the left-line tunnel 11, construct the smoke exhaust section 24 of the smoke exhaust horizontal tunnel from the direction perpendicular to the left-line tunnel 11, and carry out primary support and secondary lining to the smoke exhaust section 24;
[0051] S2, continue to excavate the smoke exhaust horizontal tunnel, the gradual change section 22 and the expansion section 23 of the construction smoke exhaust horizontal tunnel, and carry out initial support and secondary lining to the gradual change section 22 and the expansion section 23;
[0052] S3, continue to excavate the smoke exhaust horizontal tunnel, the connection section 21 of the construction smoke e...