Steel bar prefabricating jig frame for large rectangular-section pier body and using method of steel bar prefabricating jig frame
A technology of steel bars and rectangular sections for pier bodies, which is applied in the erection/assembly of bridges, structural elements, building components, etc., can solve the problems of long construction time, high difficulty of prefabrication, and heavy steel bars for ordinary tire frames, and achieves optimized construction efficiency, The effect of reducing construction risks and saving labor
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0023] In order to overcome the existing problems of large self-weight of steel bars in the pier body, high difficulty in prefabrication, long construction time of ordinary tire frames, waste of labor and efficient construction without using the pier body, the present invention provides such as Figure 1-3 Shown is a prefabricated steel frame for a large rectangular cross-section pier body and its use method. The invention improves the prefabrication rate of steel bar segments during pier body construction, saves construction time, optimizes construction efficiency, and reduces safety risks.
[0024] A prefabricated steel bar frame for a large cross-section pier body, including a bottom plate 9, a hydraulic system 1, a bottom hydraulic pushing system 2, a movable pole positioning frame 3, an end main reinforcement positioning frame 6 and a horizontal fixing rod 7. The main rib positioning frames 6 are arranged at both ends of the bottom plate 9, the hydraulic system 1 is set un...
Embodiment 2
[0029] Based on Embodiment 1, in this embodiment, preferably, the bottom plate 9 is in the shape of a rectangular frame.
[0030] Preferably, the bottom hydraulic pushing system 2 is a jack or a hydraulic cylinder.
[0031] Preferably, the upper end of the bottom hydraulic pushing system 2 is provided with a steel backing plate.
[0032] In the present invention, the setting of the steel backing plate ensures that the hydraulic jacking system 2 at the bottom exerts uniform force when jacking up the fabricated steel skeleton, and does not damage the fabricated steel skeleton. The steel skeleton made by the certificate is completely jacked up.
[0033] Preferably, the top positioning device 5 and the bottom positioning device 4 are both positioning scales.
[0034] In the present invention, if figure 2 As shown, the positioning dimension provided by the positioning scale enables the movable pole positioning frame 3 to intuitively and clearly move the distance required during...