A technology for connecting structures and wind turbine blades, which is applied in the preparation of test samples, household components, sustainable manufacturing/processing, etc., can solve the problems of frequent testing, restricting the development prospects of large wind turbines, and the high cost of making mold models. Facilitate reliability verification, reduce production material cost and time cost
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0068] Such as Figure 1 to Figure 3 The sample used for testing the connection structure of wind turbine blades shown, the sample includes a first scaled test piece 1 and a second scaled test piece 2;
[0069] The first scaled test piece 1 and the second scaled test piece 2 are oppositely provided with matching first profile and second profile, and the first profile and the second profile are provided with a vertical connection portion a and a bend The connecting part b is folded, the clamping block 3 is placed on the vertical connecting part a, and the first scale parallel to the vertical connecting part a is provided on the side away from the vertical connecting part a of the first scaled test piece 1 and the second scaled test piece 2. The spacer 4 and the second spacer 5 , the first spacer 4 and the second spacer 5 clamp the first scaled test piece 1 and the second scaled test piece 2 through the fastener 6 .
[0070] In the preferred embodiment of the present invention,...
Embodiment 2
[0076] Such as Figure 4 to Figure 8 As shown, the present invention also provides a manufacturing process of a sample used for testing the connecting structure of wind power blades, which is used to make a sample used for testing the connecting structure of wind power blades. The manufacturing process includes the following steps:
[0077] Step 1: Based on the shape structure of the first scaled test piece 1 and the second scaled test piece 2, the lay-up and perfusion system arrangement are carried out on the prefabricated mold; the prefabricated mold is used to constrain the molding of the first profile and the second profile, Therefore, the assembly accuracy of the first profile and the second profile is ensured.
[0078] Step 2: After the lay-up and perfusion system layout are completed, the first scale-down test piece 1 and the second scale-down test piece 2 are covered with double-layer vacuum, and the pressure is kept under vacuum, and the pressure loss is less than 1KP...
Embodiment 3
[0117] Such as Figure 9 The shown vertical connection part a and the bent connection part b adopt a circular arc transition, and the bent connection part b adopts a connection form without glue. The implementation process of non-adhesive bonding: directly use the torque wrench bolts to lock the parts at a torque of 87 Nm.