Intelligent early warning tower crane installation construction method
A construction method and early warning tower technology, which is applied in the directions of safety devices, transportation and packaging, and load hanging components, can solve the problems of not proposing monitoring and early warning indicators, and failing to monitor the tower arm in all directions, so as to improve reliability and improve The effect of carrying capacity and improving accuracy
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0066] Such as figure 1 As shown, the installation and construction method of the intelligent early warning tower crane includes the following steps:
[0067] S000. Construction preparation: survey and determine the plane position of the tower cranes in the middle and adjacent tower cranes, prepare materials and equipment required for construction, and calibrate the accuracy of testing instruments;
[0068] S100, construction of support pile 1 at the bottom of the column:
[0069] S110, such as figure 2 and image 3 As shown, a number of reinforced concrete cast-in-place piles are laid out in the shape of a "ten" in the central part of the tower crane to form an array of column bottom support piles, and a built-in anchor plate is pre-embedded on the top of the four column bottom support piles 1 outside the column bottom support pile array 2 and connecting plate dynamometer 3;
[0070] Among them, such as Figure 7 and Figure 8 As shown, the connection plate dynamometer...
Embodiment 2
[0104] In order to make it easier for those skilled in the art to understand embodiment 1, the explanation of each technical term in embodiment 1 is given below:
[0105] Construct five reinforced concrete cast-in-place piles at the tower crane in the middle to form the support pile 1 at the bottom of the column, with a diameter of 1m, a length of 5m, and a concrete strength grade of C30;
[0106] The built-in anchor plate 2 and the connecting plate 16 at the bottom of the column are both rolled from a steel plate with a thickness of 20 mm, and both have a diameter of 30 cm;
[0107] The connecting plate dynamometer 3 adopts a steel bar meter, which is matched with a steel bar with a diameter of 25mm;
[0108] The depth of the connecting beam laying groove 4 is 1m and the width is 0.5m;
[0109] At the top of the supporting pile 1 at the bottom of the column, a pile top support plate 5 and a pile top sleeve 6 are arranged, and the pile top support plate 5 and the pile top sle...