Underground structure and construction method thereof
A technology of underground structures and construction methods, applied in underwater structures, infrastructure engineering, artificial islands, etc., to achieve the effects of improving safety, improving manufacturing, and improving anti-leakage capabilities
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0029] as Figure 1 As shown, the present embodiment provides an underground structure, comprising an outer arch 1 and an inner arch 6, the inner arch 6 is elliptical, the inner arch 6 is provided in the middle of the outer arch 1, the top of the inner arch 6 long axis is connected to the top of the outer arch 1, the bottom of the inner arch 6 long axis is connected to the arch 7, the axis of the outer arch 1 is a quadratic function of the opening downward, the axis of the inner arch 6 is elliptical, by setting the inner arch 6 in the middle of the outer arch 1, the single force structure is transformed into a double force structure, which can not only effectively share the load and improve structural stability, It can also improve the safety of deep buried long-span structures.
[0030] In a specific embodiment of the present disclosure, the center line of the inner arch 6 coincides with the center line of the outer arch 1, by setting the double arch structure of the outer arch 1 ...
Embodiment 2
[0038] The present embodiment provides a method of underground structure construction, comprising: through geological exploration, the outline of the outer arch 1 is divided into at least a small section, by adjusting the parameters of the small module tunnel boring machine, at least one small module tunnel boring machine is excavated at the same time, forming a complete outline of the outer arch 1; Under the protection of the outer arch 1, the construction machinery is used to excavate the interior of the outer arch 1, and the truss unit is erected layer by layer from top to bottom; the middle plate 5 is erected under the truss unit, and then the inner arch 6 is constructed, the inner arch 6 is fixed to connect the middle plate 5, and then continues to construct the inner arch 6, the bottom plate 4 is erected between the bottom of the outer arch 1 and the middle plate 5, the inner arch 6 is fixed to connect the bottom plate 4, after the construction of the remaining inner arch 6,...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com