Vertical pre-stressed anchor cable balance weight retaining wall and construction method thereof
A prestressed anchor cable and vertical prestressed technology, which is applied in the direction of excavation, artificial island, sheet pile wall, etc., can solve the problems of complex construction technology, many construction procedures, and high project cost, so as to reduce the construction period and improve construction efficiency , The effect of reducing the project cost
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0039] like figure 1 As shown, the present embodiment 1 provides a vertical prestressed anchor cable 3 counterweight retaining wall, including a retaining wall body 1 and a prestressed anchor cable sleeve 12;
[0040] The foundation of the retaining wall body 1 is located in the gentle slope section of the cover layer 8;
[0041] The retaining wall body 1 is pre-embedded with a plurality of prestressed anchor cable sleeves 12, and the prestressed anchor cable sleeves 12 vertically penetrate the retaining wall from the counterweight platform 2 of the retaining wall body 1 The body 1, and extends into the bedrock 10;
[0042] A prestressed anchor cable 3 for anchoring is penetrated into the prestressed anchor cable casing 12 .
[0043] In the prior art, there are many construction procedures for the retaining wall, the construction process is complex, the construction period is long, and the construction cost is relatively high. , using this structure, the vertical prestresse...
Embodiment 2
[0049] like figure 2 As shown, Embodiment 2 is further optimized on the basis of Embodiment 1, and provides a construction method for a vertical prestressed anchor cable 3 counterweight retaining wall, comprising the following steps:
[0050] Step 1: Determine the allowable bearing capacity of the foundation in the high fill and gentle slope section, and calculate the tension value of the prestressed anchor cable 3 and the horizontal spacing of the prestressed anchor cable 3 according to the allowable bearing capacity of the foundation;
[0051] Step 2: excavate the foundation to the design elevation, then construct the retaining wall body 1, and vertically embed the prestressed anchor cable casing 12 in the reserved position;
[0052] Step 3: Then use clay 11 to ram the front and rear sides of the retaining wall body 1 to the surface 7;
[0053] Step 4: When the strength of the retaining wall body 1 meets the design requirements, construct the prestressed anchor cable 3 at ...