Photovoltaic systems and network linking methods; performance enhancers for photovoltaic systems.
Patent Information
- Application Number
- TH2501008284
- Authority / Receiving Office
- TH · TH
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2023-06-07
- Filing Date
- 2023-06-28
- Publication Date
- 2026-11-02
Smart Images

Figure 2501008284_DRAWING_01 
Figure 2501008284_DRAWING_02 
Figure 2501008284_DRAWING_03
Abstract
Claims
DEPCT69 1. Networking method for enhancers for photovoltaic systems, where the photovoltaic system comprises an inverter and photovoltaic lines connected to boost circuits at the preceding phase of the inverter's DC bus, and the networking method for enhancers comprises inverter-controlled enhancer startup, inverter-operated IV scan operations on boost circuits one by one, identification of boost circuits connected to the enhancer based on the enhancer's output characteristics during each IV scan operation by each enhancer, and the inverter's acquisition of the identified output characteristics from the enhancer to achieve consistency between the boost circuits and the enhancer.
2. Networking method for enhancers for photovoltaic systems according to claim 1, where the output characteristics comprise at least one of the output voltage interference characteristics and the output current interference characteristics. 3.The network linking method for enhancers in photovoltaic systems under Claim 1, where the identification of boost circuits connected to the enhancer based on the enhancer's output characteristics during each IV scan operation by each enhancer, includes: receiving the topology specification and boost channel number command for each boost circuit in each IV scan operation by the enhancer from the inverter; identifying the boost channel number of the boost circuits connected to the enhancer based on the enhancer's output characteristics by the enhancer; and storing the boost channel numbers identified by the enhancer for each enhancer.
4. The network linking method for enhancers in photovoltaic systems under Claim 3, where, prior to performing IV scan operations on each boost circuit individually by the inverter, the network linking method further includes: controlling each enhancer to clear the boost channel numbers stored by the enhancer by the inverter. 5.The network linking method for enhancers for photovoltaic systems under Claim 1, where prior to performing IV scan operations per boost cycle by the inverter, the network linking method for enhancers is further incorporated with controlling the inverter to operate in a grid-connected condition.
6. The network linking method for enhancers for photovoltaic systems under Claim 5, where during performing IV scan operations per boost cycle by the inverter, the network linking method for enhancers is further incorporated with setting at least one of the output voltage limit and output current limit values for each enhancer to meet the IV scan conditions by the inverter. 7.The method for networking enhancers for photovoltaic systems under Claim 1, where enhancer control for activation by the inverter includes sending trigger commands to the enhancers to put them into inverter-operated mode, and performing a soft start on the enhancers to increase the output voltage of each enhancer. 8.The method for networking the enhancers for photovoltaic systems under claim 7, where the enhancer is initiated by the inverter during control, includes the following additional components: setting at least one output voltage limit and output current limit for each enhancer by the inverter; obtaining the voltage at the input terminal of each boost circuit once the output voltage of each enhancer is stabilized at a preset value for each of the two preset values by the inverter; and determining whether each photovoltaic component in the photovoltaic line connected to the boost circuit is supplied with an enhancer by the inverter based on the variation of the voltage at the input terminal of each boost circuit. 9.The network linking method for photovoltaic systems under one of the claims 1 through 8, where, after achieving compatibility between the boost circuit and the enhancer, the network linking method incorporates the operation of pulse blocking operations per boost circuit one by one by the inverter, and the change of the output voltage of one of the enhancers connected to the boost circuit at least once by the inverter, and the identification of the photovoltaic line corresponding to each enhancer according to the electrical condition of the enhancer during the operation of pulse blocking operations per boost circuit.
10. The network linking method for photovoltaic systems under claim 9, where the change of the output voltage incorporates an active bypass, where the electrical condition is the output current. 11.The networking method for enhancers for photovoltaic systems under one of the claims 1 through 8, where prior to the control of the enhancer, the operation is initiated by the inverter, includes the additional operation of establishing a numbered communication link configuration for each enhancer by the inverter. 12.The network linking method for photovoltaic systems under any of the claims 1 through 8, where prior to the control of the enhancer initiation by the inverter, includes the acquisition of the enhancer serial number by the inverter; identification of whether the manually entered topological position has been obtained by the inverter, where the inverter-controlled enhancer initiation process is performed when the topological position is not obtained; and identification of whether the serial number matches the topological position when the topological position has been obtained by the inverter, where the inverter-controlled enhancer initiation process is performed when the serial number does not match the topological position. 13.The method for networking the enhancer for photovoltaic systems under one of the claims 1 through 8, where prior to the control of the enhancer being initiated by the inverter, the method for networking the enhancer includes the acquisition of the enhancer serial number by the inverter; identification of whether there are any previously unstored serial numbers among the serial numbers by the inverter; identification of whether the number of previously unstored serial numbers is less than a predetermined number or whether the inverter operates in a grid-connected state when there are previously unstored serial numbers by the inverter, where the process of controlling the enhancer to be initiated by the inverter is performed when the number of previously unstored serial numbers is less than a predetermined number or the inverter operates in a grid-connected state. 14.A photovoltaic system comprising an inverter and at least one photovoltaic line characterized as follows: at least one photovoltaic line is provided with at least one enhancer at its two terminals; the output terminals of at least one enhancer are connected in series; and the input terminals of at least one enhancer are connected to at least one photovoltaic component; the preceding phase of the inverter's DC bus is configured to connect at least one boost circuit; and the input terminals of at least one boost circuit are configured to connect to at least one photovoltaic line; and the inverter comprises a controller acting as a master buoy to communicate with at least one enhancer; and the controller is configured to implement one of the enhancer networking methods for the photovoltaic system as described in Recollections 1 through 13 and 15.A photovoltaic system under claim 14, where at least one boost circuit is independent of the inverter, or at least one boost circuit is integrated with the inverter, and the output terminals of the boost circuit are connected to the DC side of the inverter circuit in the inverter via a DC bus.