Monitoring method gives uncertainty regarding the reliability and technological risk associated with the development of um new equipament
The DRUM + RM methodology addresses the limitations of current reliability assessment methods by integrating Bayesian modeling and expert elicitation to monitor and manage uncertainty and risk, ensuring new equipment meets reliability and risk targets, thus reducing uncertainties and ensuring a reliable system.
Patent Information
- Application Number
- BR102025009221
- Authority / Receiving Office
- BR · BR
- Patent Type
- Applications
- Publication Date
- 2026-11-17
AI Technical Summary
Current methods for assessing reliability and technological risk in the development of new equipment are inadequate, as they rely on unrepresentative data, lack systemic views, and fail to integrate cost, time, and reliability dimensions, leading to potential cost overruns, schedule delays, and performance erosion.
The DRUM + RM methodology, which integrates Bayesian reliability modeling, expert elicitation, and multi-criteria decision-making, to monitor uncertainty and risk through multilevel reliability models, stressor analysis, and accelerated testing, ensuring reliability targets are met.
Enables proactive risk management and efficient decision-making by quantitatively assessing and updating reliability and risk throughout the development process, ensuring the new technology meets predefined criteria, reducing uncertainty and ensuring a reliable and safe system.
Smart Images

Figure 00000000_0000_ABST
Description
1 / 24 METHOD FOR MONITORING UNCERTAINTY REGARDING RELIABILITY AND TECHNOLOGICAL RISK ASSOCIATED WITH THE DEVELOPMENT OF A NEW EQUIPMENT FIELD OF THE INVENTION
[001] The present invention falls within the field of petroleum engineering. More specifically, the present invention relates to well engineering, particularly to the development of well completion equipment. FUNDAMENTALS OF THE INVENTION
[002] The development of new technologies is a complex process, often executed in non-sequential stages, with many iterations, returns to previous tests or ideas, rework, and possibilities of failure. In short, the creation of a new technology is an activity characterized by and based on risk. However, although aware of and dealing with this fact daily, decision-makers and all stakeholders involved in the development of new technologies do not have a tool capable of quantitatively assessing the risk involved in innovation. This risk involves considering several dimensions or criteria such as cost, time, integration, and the reliability of the new technology. Regarding the reliability dimension, in the development of new technologies, there is a reliability target and a target uncertainty to be met.Often, the reliability of equipment under development is assessed by suppliers based on data that may be unrepresentative, such as generic data and data from equipment developed for other applications. Therefore, to ensure that the technology under development actually meets reliability requirements, it is necessary to monitor its relative uncertainty by quantifying and updating it using scarce data from different sources, taking into account cost, time, and laboratory infrastructure constraints for conducting tests. Petition 870250037343, dated 08 / 05 / 2025, page 45 / 81 2 / 24 reliability.
[003] Currently, the standard method for verifying whether technology is being satisfactorily developed is to perform functional tests required by standards at each stage of development. Essentially, this procedure boils down to a single verification of the functioning of the new technology or its subsystems and components. Characterizing reliability in quantitative terms using only functional tests is quite limited, which compromises the risk assessment at each stage of development. At the end of the innovation process, some manufacturers, seeking a quantitative measure of reliability, apply Reliability Demonstration Tests (RDTs) to verify whether the equipment meets a given reliability requirement and / or reliability growth tests for components or subsystems associated with a specific failure mechanism before the final stages of equipment development itself.Reliability-based testing (RDTs) does not allow for the estimation of reliability and confidence level; it only allows for determining whether a minimum reliability limit is exceeded or not for a given confidence level. Like reliability growth tests, they can be specific to components and subsystems and, per se, lack the systemic view necessary to estimate the reliability of the equipment as a whole. Furthermore, data from previous versions of similar equipment are frequently used as if they were entirely relevant to analyze the reliability of the equipment under development, even when the operating contexts and / or operating modes of both are quite distinct, which constitutes a conceptual error. Finally, the approaches currently used to obtain reliability, even in a simplified form, are not integrated with the other dimensions of risk within the same methodological framework, impacting their evaluation. Petition 870250037343, dated 08 / 05 / 2025, p. 46 / 81 3 / 24 throughout the development process as a contribution to decision-making. STATE OF THE ART
[004] The document “Bayesian prior distribution based on generic data and experts’ opinion - A case study in the O&G industry” (Maior et al, Journal of Petroleum Science and Engineering, Volume 210, 2022, 109891, ISSN 0920-4105, https: / / doi.org / 10.1016 / j.petrol.2021.109891) reveals an approach to estimating reliability that does not require direct elicitation of parameters to define informative prior distributions for the reliability function using fault tree analysis, expert opinions, and / or generic data at the system level of the equipment under development. Specifically, the method of moments (MM) and maximum entropy (ME) are adopted to propagate down the uncertainty from the system level through the failure modes to the basic events of the fault tree, weighted by expert knowledge of the failure behavior.Therefore, having all the previous distributions of the basic events, the information can be propagated upwards based on Monte Carlo simulation to update the reliability distribution of the system.
[005] The document “Using experts' opinion for Bayesian prior reliability distribution of on-demand equipment: A case study of a novel sliding sleeve valve for open-hole wells” (Macedo et al, Reliability Engineering & System Safety, Volume 238, 2023, 109430, ISSN 0951-8320, https: / / doi.org / 10.1016 / j.ress.2023.109430) reveals a methodology for constructing an informative prior reliability distribution for different failure mechanisms of new equipment operating on demand. The methodology is flexible enough to consider failure events caused by degradation over time and / or past demands. Furthermore, it involves an elicitation process to extract expert opinions. Petition 870250037343, dated 08 / 05 / 2025, page 47 / 81 4 / 24 regarding the probability of failure at the system level. Uncertainty regarding differing expert opinions is considered by modeling each expert's opinion with a probability distribution and then aggregating them through multiplicative error and Population Variability Analysis. Thus, the proposed methodology considers how probability estimates vary among experts and defines an informative Bayesian prior distribution using only expert knowledge.
[006] Document CN111008438A, entitled “Umbilical cable multi-stage system reliability analysis method and device,” discloses a method and device for multi-stage umbilical cable system reliability analysis. The method comprises the steps S1 - constructing a multi-stage umbilical cable fault tree model: performing statistical analysis of the failure causes of an umbilical cable and constructing the umbilical cable fault tree model at different stages; S2 converting the multi-stage umbilical cable fault tree model to a multi-stage Bayesian network model; S3 - solving the multi-stage Bayesian network model to obtain a time variation curve of the multi-stage reliability of the target umbilical cable; and S4 - determining the reliability of each stage of the umbilical cable according to the time variation curve of reliability.According to the method, a full lifecycle reliability analysis is performed on the target umbilical cable, so that a safety assessment at the on-site operation stage can be carried out and suggestions for improvement can be provided for weak links.
[007] The document “Technology readjustment and risk assessments: a new approach” (John C. Mankins, Acta Astronautica, Volume 65, Issues 9-10, 2009, Pages 1208-1215, ISSN 0094-5765, https: / / doi.org / 10.1016 / j.actaastro.2009.03.059) reveals that Systems that depend on the application of new technologies Petition 870250037343, dated 08 / 05 / 2025, p. 48 / 81 5 / 24 inevitably faces three major challenges during development: performance, schedule, and budget. Technology research and development (R&D) programs are typically championed on the grounds that these investments will substantially reduce uncertainty across all three dimensions of project management. However, if initial R&D is poorly implemented, subsequent systems developments that plan to employ the resulting advanced technologies will suffer from cost overruns, schedule delays, and a steady erosion of initial performance objectives. It is often essential for senior management to determine which of these two paths is more likely and respond accordingly. The challenge for systems and technology managers is to conduct clear and well-documented assessments of technology readiness and risks, and to do so at key points in the program lifecycle.Several approaches have been used to assess technology maturity and risk in order to better anticipate future system development risks. Technology Readiness Levels (TRLs), developed by NASA, are a discipline-independent programmatic figure of merit (FOM) that allows for more effective assessment and communication of the maturity of new technologies. Another widely used management tool is the “risk matrix,” which relies on a graphical representation of uncertainty and consequences. However, for the most part, these various methodologies have not had any explicit interrelation. This document examines the past uses of current methods to improve R&D outcomes and will highlight some of the limitations that may arise. In this context, a new concept for integrating the TRL methodology and the “risk matrix” concept will be described.The document concludes with observations on prospective future directions for the important new concept of "technology readiness and risk assessments." Petition 870250037343, dated 08 / 05 / 2025, page 49 / 81 6 / 24 integrated. SUMMARY OF THE INVENTION
[008] The present invention discloses a method for monitoring uncertainty about reliability and technological risk based on the DRUM + RM approach developed by the inventors, comprising: a) supporting the allocation process for defining the minimum required reliability level and the maximum tolerated uncertainty; b) performing concept selection, comprising choosing one or more concepts based on a multi-criteria methodology; c) modeling equipment reliability, comprising: c1) determining failure mechanisms and their logical relationships; c2) creating models that describe the reliability of the failure mechanisms; and c3) developing MRM; d) estimating a priori reliability distribution, comprising: d1) eliciting expert opinions; d2) collecting and processing partially relevant data; d3) obtaining a distribution over the MRM parameters; and d4) obtaining the reliability distribution over mission time; e) planning reliability tests;f) Bayesian reliability update, comprising: f1) collecting data from tests performed at the current Gate; f2) updating the distribution of MRM parameters for the current TRL; and f3) updating the mission time reliability distribution for the current Gate; g) assessing the technological risk at the current Gate, comprising: g1) verifying the residual uncertainty about the reliability target; g2) verifying the updated cost and duration estimates of the project; g3) determining if the technological risk is tolerable for the current Gate; g3.1) if not, deciding on the type of action to be taken: g3.1.1) if design change, suggest and implement the design change and return to step (c); g3.1.2) if conducting new tests, return to step (e); g3.1.3) if abandoning the project, determine that the technology is inadequate and terminate the project; g3.2) if positive; Petition 870250037343, dated 08 / 05 / 2025, pages 50 / 81 7 / 24 check if the current Gate is the final Gate; g3.2.1) if yes, determine that the equipment is suitable; g3.2.2) if no, proceed to the next Gate and return to step (f).
[009] The assessment of equipment reliability and uncertainty is based on expert opinions, Bayesian methodology, FMECA, FTA, and PPoF, where FMECA includes a new component called a stressor, which represents the physical variable responsible for the failure mechanism identified in the FMECA. This stressor is crucial in defining the PPoF model, depending on the nature of the stressor and the frequency with which it acts on the component—whether instantaneously during certain operational demands or continuously throughout production, causing a cumulative degradation process. This makes the invention's method suitable for very long mission times, on the order of decades. Thus, in the context of the invention, the innovative activity involves defining the stressor component associated with the failure mechanism component, which will be used to choose the best PPoF law that models that specific equipment failure scenario under analysis. BRIEF DESCRIPTION OF THE DRAWINGS
[010] The present invention will now be described with reference to typical embodiments thereof and also with reference to the accompanying drawings, in which: Fig. 1 illustrates a compact configuration of the DRUM + RM approach with its steps according to the present invention; Fig. 2 illustrates the adapted FMECA approach used in the DRUM + RM Methodology according to the present invention; Fig. 3 illustrates an example of a fault tree according to the present invention; Fig. 4 is a detailed illustrative flowchart of the steps of the method according to the present invention; Fig. 5A illustrates the first part of an exemplary elicitation form according to the present invention; Petition 870250037343, dated 08 / 05 / 2025, pp. 51 / 81 8 / 24 Figure 5A illustrates the second part of the exemplary elicitation form according to the present invention; Figure 5C illustrates the third part of the exemplary elicitation form according to the present invention. DETAILED DESCRIPTION OF THE INVENTION
[011] Specific embodiments of this disclosure are described below. In an effort to provide a concise description of these embodiments, all features of an actual implementation may not be described in the descriptive report. It should be appreciated that in the development of any actual implementation, as in any engineering or design project, numerous specific implementation decisions must be made to achieve the specific objectives of the developers, such as compliance with system and business-related constraints, which may vary from one implementation to another. Furthermore, it should be appreciated that such a development effort may be complex and time-consuming, but would nevertheless be a routine design and manufacturing undertaking for those of ordinary skill having the benefit of this disclosure.
[012] The present invention proposes a new methodology for monitoring uncertainty about reliability and the inherent technological risk associated with the development of new equipment, which is at TRL 2 and in the process of reaching TRL 3. The developed methodology is called DRUM + RM, and is divided into two parts: (i) DRUM (Development Supported by Reliability Uncertainty Monitoring) and its stages (data collection, reliability modeling and reliability prediction) and (ii) RM (risk monitoring) and its stage (concept selection).
[013] In DRUM, the data collection phase includes support for reliability testing, expert elicitation, and the handling of partially relevant data. The reliability prediction phase uses Bayesian methodology for forecasting. Petition 870250037343, dated 08 / 05 / 2025, pages 52 / 81 9 / 24 of equipment reliability and the reliability modeling stage is dedicated to creating models that describe the reliability of the equipment. In RM, the concept selection stage incorporates a multi-criteria method to select different concepts (i.e., designs) from a set of available concepts, which should move forward in the development process. The criteria used are duration, cost, integration, and reliability, and they are evaluated for each of the concepts. The concept selection stage is applied at least twice during the development of the new technology: Before Gate 0 and between Gates 1 and 2.
[014] Based on the initial allocation of system reliability, requirements are established for the reliability of the equipment under development during the specified mission time and for the uncertainty associated with it. These requirements are understood as targets to be achieved by the new technology at the end of the development process and, therefore, are used as input to DRUM. Initially, the multilevel reliability model (MRM) that describes the equipment reliability is developed in the reliability modeling stage. Then, in the reliability prediction stage, the MRM parameters are determined; at the beginning of development, a prior probability distribution of the equipment's reliability during the mission time is obtained based on information provided by the data collection stage (expert opinion and / or partially relevant data), from which the initial uncertainty associated with it is obtained.As new evidence from the tests is acquired and consolidated in the data collection phase, the reliability prediction phase uses Bayesian methodology and generates a new estimate of the equipment's reliability distribution over mission time, allowing uncertainty to be monitored over time. Uncertainty acts as a control variable. Petition 870250037343, dated 08 / 05 / 2025, pages 53 / 81 10 / 24 so that the system achieves the established goal. Specifically, from the application of the RM concept selection stage at the beginning of the development process (before Gate 0), the initial target uncertainty regarding mission-time reliability is obtained by aggregating the uncertainties of the multiple concepts (e.g., 4 or 5) selected via a multi-criteria method to proceed. Furthermore, DRUM provides the distribution of mission-time reliability that is used in quantifying the reliability criterion necessary for monitoring technological risk by the RM side. The desired output is a system that meets the predefined uncertainty and risk targets. If the new technology meets the reliability requirements, as well as the other criteria that comprise technological risk (duration, cost, integration), the development process will proceed.Technological risk is understood as the uncertainty associated with the development of a specific technology. DRUM and RM play a crucial role in delivering new technology, ensuring that it meets the determined reliability, uncertainty, and risk requirements, resulting in a reliable and safe system for its intended use.
[015] For simplicity, the method of the present invention will be described below based on an exemplary application where the new equipment under development is a downhole drilling rig. However, it will be evident to those skilled in the art that the present invention is not limited to this type of equipment. Adaptations and adjustments to specific applications are possible without departing from the scope of the present invention.
[016] The DRUM + RM methodology is structured in stages: data collection, reliability modeling, and reliability prediction in DRUM, and concept selection in RM. As briefly illustrated in Fig. 1 (and in detail in Fig. 4), the methodology involves the sequential steps described below. a) - Step 1: Defining Reliability Requirements Petition 870250037343, dated 08 / 05 / 2025, pages 54 / 81 11 / 24
[017] The reliability target for the pre-specified mission time and the associated uncertainty target for the equipment under development should be derived from a reliability allocation procedure that takes the well system into account. For equipment already developed within the well system, the reliability functions are well defined. However, it should be considered that these reliability functions were obtained from historical data in different applications, which can be characterized as partially relevant data for the well system in question. Therefore, the method for handling partially relevant data should be adopted to weight these reliability values before executing the allocation process. Thus, the reliability and uncertainty targets for the technologies to be developed can then be adequately determined by the allocation process, in order to meet a global target for the well system.
[018] The uncertainty target must be met at the end of the development process, and the uncertainties observed throughout this process can be compared to it, characterizing the reliability uncertainty monitoring process incorporated by DRUM. This reliability uncertainty is then combined with the other criteria that make up the risk during development, allowing for more strategic, risk-based decision-making, which is the objective of RM. b) - Step 2: Concept Selection
[019] The methodology developed for concept selection quantitatively integrates reliability using the Additive Ratio Assessment (ARAS) method. The approach incorporates reliability estimation through prior distributions obtained by expert elicitation. The reliability criterion is then translated into a relative scoring scale (1 = much worse, 2 = worse, 3 = reference, 4 = better, 5 = much better), where the simple average of the reliabilities Petition 870250037343, dated 08 / 05 / 2025, pages 55 / 81 The expected reliability of the alternatives (12 / 24) serves as a reference. In this way, concepts with reliability higher than the average value receive higher scores, while those with lower reliabilities are penalized proportionally. This approach ensures that reliability is considered quantitatively and objectively in the decision-making process, reducing subjectivity and allowing the integration of this criterion with other essential factors.
[020] The evaluation criteria – cost, duration, integration, and reliability – have weights defined by experts according to their relevance to the project, using an importance scale of 1 to 5. In this way, more critical criteria exert greater influence on the final decision. After assigning scores and weights, the weighted values are combined in the ARAS structure, resulting in a weighted sum that determines the final ranking of the alternatives. This strategy allows for a structured evaluation, ensuring greater transparency, traceability, and alignment with the project objectives. c) - Step 3: Reliability Modeling of the Technology Under Development
[021] The first step necessary to obtain a reliability estimate for a technology under development consists of its modeling and analysis, from a topological and causal point of view. It is necessary to define a model capable of representing the characteristics of complex systems, in order to subsequently aggregate the data that will be collected. For this, the DRUM + RM methodology establishes a Multilevel Reliability Model (MRM). The MRM begins with sub-step c1): determining the failure mechanisms and their logical relationships, in which a Failure Mode, Effects and Criticality Analysis (FMECA) is performed. Although FMECA is an already developed tool, Petition 870250037343, dated 08 / 05 / 2025, pages 56 / 81 13 / 24 DRUM + RM proposes its own FMECA specifically developed to facilitate the application of MRM. A model of this FMECA is presented in Fig. 2. The main difference is the inclusion of the column corresponding to the stressor, which allows specialists to assess which physical variable is responsible for the failure. This information is useful for planning the tests to be performed. Another fundamental point is the establishment of the Risk Priority Number (RPN), which consists of multiplying the occurrence, detection, and severity scores. The RPN is the main filter for analyzing which failure modes will be included in the analysis and which will be considered irrelevant. Next, the FMECA information is transformed into a Fault Tree Analysis (FTA). This means that the data entered in the FMECA spreadsheet will be processed and their logical relationships will be obtained, indicating, for each component, a logical failure path.Thus, the top-event failure is decomposed into several basic failure events. The system is divided topologically (system, subsystem, component) and into its failure paths (basic events, intermediate events, top-event). A typical example of FTA is shown in Fig. 3.
[022] After defining the FTAs, the DRUM + RM methodology moves to step c2): creating models that describe the reliability of the failure mechanisms, which establishes how the reliability estimate of each failure mode will be handled. For this, an approach called Probabilistic Physics of Failure (PPoF) is used to determine the reliability models for each basic event. The novelty of the PPoF approach, in this case, is its coupling with a failure analysis approach for the top event, through propagation through logic gates. The first point to define the models of the basic events is to consider the type of system operation: on-demand or on-demand. Petition 870250037343, dated 08 / 05 / 2025, pages 57 / 81 14 / 24 continuous operation. Stressors acting on demand are applied instantaneously to a component, only during a procedure, such as installation, actuations (e.g., opening or closing valves), interventions, etc. These types of failure mechanisms are associated with a probability of failure on demand (PFD), p, meaning that when the demand occurs, the failure mode will occur with a probability p. For example, during the installation of an expandable packer, a pressurization procedure is performed by applying pressure to the metal expandable jacket. The expandable jacket may burst during this procedure with probability p. For failure mechanisms whose stressors continuously affect the item, or at high frequency, a time-to-failure distribution is used. This includes environmental variables that act continuously on the item (e.g., temperature, axial loads, pressure differential, vibration, humidity, electrical potential, etc.).) causing its failure due to mechanisms such as fatigue, corrosion, erosion, and so on. The appropriate choice for the time-to-failure distribution depends on the form of the PPoF model that best represents the failure mechanism. The PPoF modeling structure is subject to the nature of the underlying failure and degradation mechanism, which may be stress-life, damage-endurance, or performance degradation.
[023] The final sub-step, c3, consists of developing the MRM based on the modeling obtained in sub-step c1 and the failure mechanisms obtained in sub-step c2. d) - Step 4: Prior Estimation of Reliability (Gate 0)
[024] Once the basic event models have been defined and the tests that will provide experimental data have been designed, it is necessary to define the prior distribution, which will provide the first reliability estimate. The prior distribution allows obtaining reliability and associated uncertainty even at TRL 3 (Technology Readiness Level), at the time of proof of concept. The following are used: Petition 870250037343, dated 08 / 05 / 2025, pp. 58 / 81 15 / 24 sources of information derived from expert opinion elicitation and / or similar equipment. The a priori distribution will be updated, at each TRL, as new information (e.g., test data) becomes available.
[025] In sub-step d1, expert opinions are elicited. To use expert opinion in determining a priori reliability, it is necessary to develop a structured elicitation process. The elicitation aims to obtain estimates of the probability of occurrence of specific failure modes. For this, elicitation forms are generated based, for example, on the FTAs provided by the user. A non-limiting example of an elicitation form is found in Figures 5A to 5C. These forms are used to extract information about the probability of equipment failure in different failure modes. Elicitation can be performed remotely, but the participation of experts with different experiences and levels of knowledge regarding the equipment under analysis is essential.Therefore, a lead analyst must select the experts who will participate in the elicitation, taking into account their different levels of knowledge and experience. It is important to emphasize that the experts will answer questions about the probability of failure of the top event (i.e., equipment failure), and then about the probabilities of the failure having been caused by the different failure modes, represented by the intermediate events immediately below the top event in the fault tree, and so on.
[026] Sub-step d2 refers to the collection and processing of partially relevant data. For similar equipment, the DRUM + RM methodology provides for the use of relevance factors, which are calculated according to a systematic procedure involving the main functional and operational characteristics. Petition 870250037343, dated 08 / 05 / 2025, pages 59 / 81 16 / 24 of the systems considered. Thus, criteria are defined (type of operation, geology, operational envelope, geometry, material), to which representative values are assigned, which are then compared using distance measurements. In this description, distance is a measure of similarity between equipment, such that small distances mean high similarity and large distances mean low similarity. The greater the distance between the equipment, the less relevant the data from the similar equipment will be on the reliability of the equipment being developed.
[027] With this information, we arrive at the level of basic events and can use the method of moments or the maximum entropy method to perform sub-step d3): obtain a distribution over the MRM parameters, which consists of estimating the prior distribution for the probability of occurrence of each of them. With the prior distributions of the basic events defined, sub-step d4 is performed: obtain the distribution of reliability over mission time, where uncertainty is propagated in a bottom-up approach that uses Monte Carlo Simulation to find the prior probability distribution of the top event, associated with equipment failure and, complementarily, with the reliability of the equipment under analysis. e) - Step 5: Support for Reliability Testing
[028] After identifying the basic events and their associated failure mechanisms, the next step foreseen by DRUM + RM is the design of specific tests for data collection. In general, two types of tests are possible: functional tests and long-term reliability tests. Functional tests are those normally performed in industry-standard qualification programs. However, they are not capable of providing reliability estimates, given that they are performed over a short period of time and with a very small number of participants. Petition 870250037343, dated 08 / 05 / 2025, pages 60 / 81 17 / 24 reduced sample size. On the other hand, traditional long-term reliability tests are not suitable for the oil and gas industry, as mission times are very long, on the order of decades. In this sense, the most widely used approach in the previous technique is reliability demonstration tests (RDT). These tests do not provide measures of reliability or uncertainty distribution throughout the process; they only guarantee, if there is no failure, that the reliability is above a certain level with the established uncertainty.
[029] To advance the perspective of testing in the industry, using specific reliability tests, the accelerated testing methodology is suggested. In this way, it is possible to deal with long mission times in feasible times from a cost and duration point of view. The main way to do this is the physical modeling of the failure mechanism, via PPoF, described in Step 3 (S3), and the use of acceleration factors, performing accelerated tests. These two methods are intrinsically connected.
[030] The accelerated testing methodology consists of using PPoF equations to predict which stressor levels should be applied to emulate field use in a shorter time, using more severe stresses than normally expected. The main equation relating PPoF and accelerated testing is expressed by the acceleration factor, and the relationship between the stressor and life should be established based on a linear, exponential, power-law, or multi-stress relationship. The specific relationship should be defined based on the physical modeling of the failure mechanism, but general guidelines can be established. Thermal mechanisms are generally modeled by the exponential relationship, while mechanical fatigue mechanisms generally employ the power law. When coupled mechanisms are present, multi-stress models are adopted. Petition 870250037343, dated 08 / 05 / 2025, pages 61 / 81 18 / 24
[031] Thus, it is possible to estimate the stressor level that corresponds to the accelerated life of the component. This level can be used in the test, the result of which will represent the life distribution (or probability of failure) of the equipment under accelerated conditions. It can then be extrapolated to stresses under normal conditions through the likelihood function and the stressor-life relationships presented. f) - Step 6: Bayesian Reliability Update (Gates > 0)
[032] As the development process evolves and a variety of data sources become available, the DRUM + RM methodology updates the reliability distribution parameters with the new test and field data that become available in subsequent TRLs through a Bayesian approach. Thus, for each TRL, starting from TRL 4, the present invention performs substep f1): collecting data from tests performed on the current Gate, where it determines which data should be obtained through testing of the equipment under development. Each type of equipment will require a particular test to extract specific information, so only the type of data and information required will be listed below. The person skilled in the art will be able to choose the appropriate test for particular applications without departing from the scope of the invention.
[033] TRL 4: Data type: Component-level bench tests.
[034] Information collected: a. Conditions and duration of the tests. b. Number of specimens tested. c. Complete, interval, and / or censored failure times. d. Number of failures observed.
[035] TRL 5: Data type: System-level bench tests. Petition 870250037343, dated 08 / 05 / 2025, pp. 62 / 81 19 / 24
[036] Information collected: e. Conditions and duration of the tests. f. Number of specimens tested. g. Complete, interval, and / or censored failure times. h. Number of failures observed.
[037] TRL 6: Data type: Laboratory tests in the well at the system level.
[038] Information collected: I. Conditions and duration of the tests. j. Number of specimens tested. k. Complete, interval, and / or censored failure times. l. Number of failures observed.
[039] TRLs 7 and 8: Data type: m. TRL 7: Operation in a well for a predetermined time. n. TRL 8: Operation in three wells for a predetermined time.
[040] Information collected: o. Complete, interval, and / or censored failure times. p. Number of failures observed.
[041] TRL 9: Data type: Equipment operation in one or more wells.
[042] Information collected: q. Complete, interval, and / or censored failure times.
[043] Number of failures observed.
[044] Thus, the method moves to substep f2): update the distribution of the MRM parameters, for the current TRL. Each step Petition 870250037343, dated 08 / 05 / 2025, pages 63 / 81 20 / 24 of the analysis (or TRL) of the development consists of a Bayesian update, taking into account the particularities of each type of data or information available at that stage. Different posterior distributions for the MRM parameters are estimated at each decision epoch (Gate). The result of this estimation provides uncertainty distributions on the MRM parameters. From the FTAs or any other reliability logic diagram, the parameters are extrapolated to the global equipment failure event in sub-step f3): updating the reliability distribution at mission time, for the current Gate, providing the reliability and uncertainty associated with the system considered, at the established mission time.
[045] As prior distributions are defined, likelihood functions must be constructed from test data performed in subsequent stages of the development process. Naturally, if the failure mechanism is addressed by a specific test, then the likelihood of the data extracted from this test can be obtained as a function of θ, based on the reliability model ^(t^,) . Thus, let Tj,ko be the set of tests performed at Gate k, which covers event í, and Eiika the evidence collected from each test, with Δζ^I,^Iθ,} being the likelihood function of the obtained data. It can be said that the posterior distribution of the parameters θ, of the MRM, obtained through Bayesian updating, is given by equation 1: nk&lEiik) κ π^θίΐΕ^ x ί(Ει,,|θί) (1) where: mk is the posterior distribution in Gate k; θ is the failure mechanism of event i; Eiiké is the evidence collected by the test of event í in Gate k; rnk_1 is the prior distribution in Gate k; L stands for likelihood; and Ei,k_1é a evidência coleta pelo teste do evento í no Gate Petition 870250037343, dated 08 / 05 / 2025, pages 64 / 81 21 / 24 k — 1;
[046] At Gate k = 0, Bayesian inference for θι comprises the step immediately preceding the first reliability test, when the prior distribution is obtained, as per step (d). The methods used by the DRUM + RM methodology to perform the Bayesian update calculation include the analytical approach (when a conjugate prior distribution can be obtained for the likelihood functions), the Markov Chain Monte Carlo (MCMC) based approach, and Variational Inference. g) - Step 7: Assess Technological Risk (Gates >0)
[047] As reliability distributions are updated throughout the TRLs, it is possible to monitor and analyze the behavior of uncertainty levels at each stage of development. Uncertainty curves, together with cost, duration, and integration criteria, can be used to analyze the risk associated with new technology to be included in well configurations.
[048] Uncertainty about the reliability target is expected to decrease across the Gates as new evidence about the reliability of the equipment becomes available, until it reaches the maximum permissible uncertainty target at one of the final Gates. The distance from the uncertainty estimated at a Gate to the uncertainty target is called Residual Uncertainty. In substep g1): verifying the residual uncertainty about the reliability target, the method calculates the residual uncertainty of the technology at the current Gate. Thus, across the Gates, the Residual Uncertainty must be verified to assess the risk that the target will not be reached at the end of development.
[049] In sub-stage g2, updated cost and duration estimates for the project are checked to determine what action will be taken. The cost and time spent on making design modifications or re-running tests are Petition 870250037343, dated 08 / 05 / 2025, pages 65 / 81 22 / 24 evaluated, as well as the expected gains to be obtained in reducing uncertainty in each case.
[050] Next, the method executes substep g3): determine if the technological risk is tolerable for the current Gate. If, at any point, the risk is considered intolerable, the method executes substep g3.1): decide the type of action to be taken, where the outputs provided by DRUM + RM can be used to assess whether, by modifying certain test parameters, such as duration, number of specimens, or applied stress levels, it is possible to achieve the desired reliability target. If this is the case, the method executes substep g3.1.1): suggest and implement the design change and return to step (c). This enables a proactive approach to adjusting test planning and execution, ensuring that reliability targets are achieved efficiently.
[051] Or, if failures are observed in the tests, the multilevel model allows identifying the failure mechanisms, and the associated components, that most contribute to the technological risk of the project, providing guidelines for design modification actions in the equipment. In this case, the method executes substep g3. 1.2): return to step 5 (e), to perform new tests, since failure mechanisms can be introduced and / or removed from the MRM. The treatment of partially relevant data may be necessary for a portion of the data obtained for the previous version of the design.
[052] All decisions must be made from the perspective of the impacts on the cost and duration of the project. If such impacts are considered critical, or if a design modification has already been made and the process has already returned to step 3 (c) and / or step 5 (e), then it may be decided to consider the unfeasibility of continuing the project at sub-step g3.1.3), thus terminating it. Alternatively, the risk associated with Residual Uncertainty may be accepted to ensure the reduction of Petition 870250037343, dated 08 / 05 / 2025, pages 66 / 81 23 / 24 risks related to the cost and duration of the technology development project. Therefore, the importance of the criteria - cost, duration, integration and reliability - must be analyzed in the decision-making process.
[053] Thus, the outputs provided by DRUM + RM not only support risk-based decision making, but also allow continuous adjustments to the technology development strategy.
[054] On the other hand, if substep (g3) determines that the technological risk is tolerable for the current Gate, the method executes substep g3.2): check if the current Gate is the final Gate.
[055] If not, the method proceeds to substep g3.2.2): advance to the next Gate and return to step (f), to continue with the development of the technology.
[056] If yes, the method proceeds to substep g3.2.1), to determine that the equipment is suitable, thus ending the method.
[057] Fig. 4 illustrates in detail the steps revealed above.
[058] The method described here allows for the estimation and monitoring of the reliability and risk of new equipment throughout all stages of the development process. To this end, the main challenge is to aggregate various types of data, available throughout the process, which need to be analyzed and processed to provide a probability distribution for reliability and its respective uncertainty. The developed method contains statistical tools that use Bayesian inference to aggregate data from multiple sources, such as expert opinions, similar equipment, reliability tests, life tests and / or accelerated degradation tests, computational and physical failure simulation. In addition, the procedure is based on a multilevel reliability model (MRM), which establishes the analysis of various hierarchical levels and failure modes of the equipment. Petition 870250037343, dated 08 / 05 / 2025, pages 67 / 81 24 / 24 considered, allowing a systemic view of the equipment as a whole. The method is based on the hierarchical construction of the reliability estimate of the equipment under development through the propagation of reliability information at the subsystem / component level to the system level. Thus, the developed method combines tools that had not yet been used together in the literature or in industry to estimate the reliability and risk of new technologies under development. These tools, combined in an unprecedented way, consist of Bayesian inference, a multi-level reliability model, a physical-failure model, estimation of prior probability distribution of reliability using data from different sources, including expert opinions and partially relevant data, and a multi-criteria method for characterization and selection of concepts with respect to the cost, duration, integration, and reliability criteria that comprise technological risk.
[059] Although aspects of the present disclosure may be susceptible to various modifications and alternative forms, specific embodiments have been shown as examples in the drawings and have been described in detail in this document. But it should be understood that the invention is not intended to be limited to the particular forms disclosed. Instead, the invention should cover all modifications, equivalents and alternatives that fall within the scope of the invention, as defined by the following appended claims. Petition 870250037343, dated 08 / 05 / 2025, pp. 68 / 81
Claims
1 / 6 CLAIMS 1. A method for monitoring uncertainty regarding the reliability and technological risk associated with the development of new equipment, characterized by comprising the following steps: a) supporting the allocation process for defining the minimum required reliability level and the maximum tolerated uncertainty; b) performing concept selection, comprising choosing one or more concepts based on a multi-criteria methodology; c) modeling the reliability of the equipment, comprising: c1) determining the failure mechanisms and their logical relationships; c2) creating models that describe the reliability of the failure mechanisms; and c3) developing a multilevel reliability model (MRM); d) estimating a priori distribution of reliability, comprising: d1) eliciting expert opinions; and d2) collecting and processing partially relevant data; d3) obtaining a distribution over the MRM parameters;and d4) obtain the mission time reliability distribution; e) plan reliability tests; f) Bayesian update of reliability, comprising: f1) collect data from tests performed at the current Gate; f2) update the distribution of MRM parameters for the current Gate; and f3) update the mission time reliability distribution for the current Gate; Petition 870250037343, dated 08 / 05 / 2025, page 69 / 81 2 / 6 g) Assess the technological risk at the current Gate, comprising: g1) verify the residual uncertainty about the reliability target; g2) verify the updated cost and duration estimates of the project; g3) define if the technological risk is tolerable for the current Gate; g3.1) if not, decide the type of action to be taken: g3.1.1) if design change, suggest and carry out the design change and return to step (c); g3.1.2) if new tests are performed, return to step (e);g3.1.3) if a design modification has already been made and the process has already returned to step 3 (c) and / or step 5 (e), the technology is considered inadequate and the project is abandoned; g3.2) if yes, check if the current Gate is the final Gate; g3.2.1) if yes, determine that the equipment is adequate; g3.2.2) if no, proceed to the next Gate and return to step (f).
2. Method, according to claim 1, characterized in that the concept selection comprises: modeling the selection problem from a multi-criteria approach, where alternatives will be compared based on 4 evaluation criteria - cost, duration, integration and reliability; defining the weights of each criterion, according to its relevance to the project for different specialists, via Additive Ratio Assessment (ARAS); Petition 870250037343, dated 08 / 05 / 2025, pp. 70 / 81 3 / 6 defining value scales of the alternatives for each criterion and assigning a score to each alternative; obtaining a global score for each alternative that will determine the final ranking, where the weighted values of the scores for each criterion are combined in the ARAS structure, resulting in a weighted sum.
3. A method according to claim 1, characterized in that eliciting expert opinions considers experts with different experiences and levels of knowledge regarding the equipment, and that a chief analyst selects which experts will participate in the elicitation process.
4. Method, according to claim 1, characterized in that eliciting expert opinions further comprises: eliciting the probability of failure of a top event of the FTA and then the probabilities of each failure mode of the FTA; using the method of moments or the maximum entropy method to estimate the prior distribution for the probability of occurrence of each basic event of the FTA; propagating the uncertainty based on the prior distributions in a bottom-up approach using Monte Carlo Simulation to find the prior probability distribution of the top event.
5. Method, according to claim 1, characterized in that the Bayesian update of the equipment reliability is performed based on equation 1: ^(θ^) κ πΛ_1(0ί|EίΛ_1) X LfaM (1) where í is a failure event, k is the current Gate, θι is the parameter of the reliability model of the failure mechanism associated with the event í, Eiik is the evidence collected from the test performed at the current Gate, L(Ei,k^i) is the relative likelihood of the reliability model of the failure mechanism associated with the event í, Petition 870250037343, dated 08 / 05 / 2025, page 71 / 81 4 / 6 1^) is the probability distribution over θ, at Gate k.
6. Method, according to claim 5, characterized in that the Bayesian update of equipment reliability is performed via Markov Chain Monte Carlo (MCMC) and Variational Inference.
7. Method, according to claim 1, characterized in that the MRM comprises Criticality, Effects and Failure Modes Analysis (FMECA) with the addition of a column for stressor, Risk Priority Number (RPN), Fault Tree Analysis (FTA) based on FMECA and Probabilistic Failure Physics (PPoF) approach of the basic events of FTA.
8. Method, according to claim 1 or 5, characterized in that each Gate is associated with one or more Technology Readiness Levels (TRL).
9. A method, according to any one of claims 2 to 8, characterized in that the selection of concepts occurs before Gate 0 and between Gates 1 and 2.
10. A method, according to any one of claims 3, 4 or 8, characterized in that the a priori estimation of reliability occurs at Gate 0, during TRL 4 and before the tests are performed.
11. Method, according to claim 8, characterized in that the step of performing equipment tests and obtaining data comprises: for TRL 4, the data are derived from bench tests at the component level and consist of test conditions and duration, number of specimens tested, complete, interval and / or censored failure times, and number of failures observed; for TRL 5, the data are derived from bench tests at the system or subsystem level and consist of test conditions and duration, number of specimens tested, complete, interval and / or censored failure times, and number of failures observed; Petition 870250037343, dated 08 / 05 / 2025, p.72 / 81 5 / 6 for TRL 6, the data comes from well laboratory tests at the system level, and consists of test conditions and duration, number of specimens tested, complete, interval and / or censored failure times, and number of failures observed; for TRL 7, the data comes from operation in one well for a predetermined mission time, and consists of complete, interval and / or censored failure times, and number of failures observed; for TRL 8, the data comes from operation in two additional wells for a predetermined mission time, and consists of complete, interval and / or censored failure times, and number of failures observed; and for TRL 9, the data comes from equipment operation in one or more wells, and consists of complete, interval and / or censored failure times, and number of failures observed.
12. Method, according to claim 1, characterized in that the technological risk assessment step comprises: Verifying the residual uncertainty on the reliability target, considered by the difference between the uncertainty estimated at the current Gate and the target determined in the target definition step; Verifying the updated cost and duration estimates of the equipment development project and comparing them with possible budget and time targets; Determining whether the Residual Uncertainty is tolerable for the current Gate and, if so, the development process may: advance to the next Gate from the perspective of the impacts on the cost and duration of the project or remain at the current Gate to carry out actions aimed at reducing the Residual Uncertainty; Deciding the type of action to be taken if it is determined that the Residual Uncertainty is intolerable: design modification, carrying out new tests, or project termination.Petition 870250037343, dated 08 / 05 / 2025, pp. 74 / 81.