A special trolley for rapid transfer of tunnel widening section and construction method

By designing an adjustable tunnel widening section special trolley and corresponding construction methods, the construction problem caused by the difference in the contour space inside the emergency parking belt and the tunnel section size is solved, and the flexible movement of the trolley in the tunnel is realized. Effective pouring of parking belt location.

CN110259482BActive Publication Date: 2024-11-05HEILONGJIANG WATER CONSERVANCY & HYDROPOWER GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910717766.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-08-05
Publication Date
2024-11-05
Estimated Expiration
2039-08-05

Smart Images

  • Figure CN110259482B_ABST
    Figure CN110259482B_ABST
Patent Text Reader

Abstract

A special trolley for rapid transfer of tunnel widening sections and a construction method relate to the field of civil engineering construction equipment. In order to solve the problem that the existing emergency parking strip has a large difference in the internal contour space size and the overall cross-sectional size of the tunnel, the secondary lining trolley cannot be directly cast as a whole at the parking strip position using traditional technology. The support mechanism is hinged to the inner surface of the outer shell through multiple screw rods, and a driving mechanism is provided at the bottom end of the support mechanism; one end of the top template is hinged to one end of the No. 1 side template, and the other end of the top template is hinged to one end of the No. 2 side template; the support mechanism adopts a longitudinal support arm provided at each end of the crossbeam, the bottom end of the longitudinal support arm is connected to one end of the heightening box, and the other end of the heightening box is connected to the driving mechanism, and a widening frame is provided at the outer center of the longitudinal support arm, and two oil cylinders are evenly provided on the upper surface of the crossbeam, and the output ends of the two oil cylinders are fixedly connected to the top template. The present invention is suitable for the construction of tunnels.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of civil engineering construction equipment, and in particular to a special trolley for rapid transition of a tunnel widening section and a construction method. Background Art

[0002] The domestic section tunnel has a total of 12 sections of emergency parking strips (widened sections) on the left and right lines, each 50 meters long. An emergency parking strip is set every 750 meters on the right side of the tunnel driving direction, with a width of 4 meters and a length of 50 meters (including a 2.5×5M transition section).

[0003] For safety reasons, emergency parking strips are installed in the extra-long tunnels of my country's highways. Since the dimensions of the contour space in the emergency parking strip are quite different from the overall cross-sectional dimensions of the tunnel, the secondary lining trolley cannot directly cast the parking strip as a whole. Therefore, the traditional process is to process a new trolley or modify the secondary lining trolley to solve this construction problem. Summary of the invention

[0004] In order to solve the problem that the outer contour space size of the existing emergency parking strip is quite different from the overall cross-sectional size of the tunnel, and the parking strip position cannot be directly cast as a whole by the secondary lining trolley using traditional technology, the present invention proposes a special trolley for rapid transfer of the tunnel widening section and a construction method.

[0005] The invention discloses a special trolley for fast transfer of tunnel widening section, which comprises a housing, a plurality of screw rods, a supporting mechanism and a driving mechanism;

[0006] The support mechanism is hingedly connected to the inner surface of the housing through a plurality of screw rods, and a driving mechanism is provided at the bottom end of the support mechanism;

[0007] The shell comprises a top template, a first side template and a second side template; one end of the top template is hinged to one end of the first side template, the other end of the top template is hinged to one end of the second side template, and the top template, the first side template and the second side template form a semi-cylindrical shape with a cavity;

[0008] The supporting mechanism includes a widening frame, a crossbeam, a cylinder, a cylinder frame, a heightening box, a rib plate and a longitudinal support arm;

[0009] A longitudinal arm is provided at each end of the crossbeam, the bottom end of the longitudinal arm is connected to one end of the heightening box, the other end of the heightening box is connected to the driving mechanism, a rib plate is provided between the inner side of the longitudinal arm and the lower surface of the crossbeam, a widening frame is provided at the outer center of the longitudinal arm, two oil cylinders are evenly provided on the upper surface of the crossbeam, and the two oil cylinders are symmetrically arranged, and the output ends of the two oil cylinders pass through the oil cylinder frame and are fixedly connected to the lower surface of the top template;

[0010] The driving mechanism comprises a motor and a driving wheel, the output end of the motor is connected to a large pulley, the large pulley is connected to a small pulley through a belt, and the small pulley is coaxially connected to the driving wheel;

[0011] Furthermore, the driving wheel is provided with grooves along the outer circumferential surface;

[0012] The invention discloses a method for constructing a special trolley for rapid transition of a tunnel widening section, and the specific process is as follows:

[0013] Step 1: Remove the lower template and widening frame;

[0014] Step 2: Remove the mast heightening box;

[0015] Step 3: Continue to lower the main top cylinder to 0 stroke, so that the overall height of the trolley is lower than the main hole contour line;

[0016] Step 4: Replace the edge support screw and shrink the entire template within the standard section:

[0017] Step 5: Move the trolley axis from the center line of the emergency parking strip to the center line of the tunnel;

[0018] Step 6: Move the trolley through the tunnel to the turning area outside the tunnel entrance;

[0019] Step 7: Change the vertical walking to horizontal walking in the turning area;

[0020] Step 8: Walk horizontally to the turning area of ​​another hole, and then change to vertical walking mode according to the above steps;

[0021] Step 9: After reaching the widening section, reverse the above steps and start the secondary lining construction;

[0022] Furthermore, the specific method of removing the lower template and the widening frame in step 1 is as follows: the circumference of the widened section is greater than the circumference of the standard section, and the section can be shrunk only after the lower template is removed. The removal method is to first support the lower template with a long screw rod, then remove the hydraulic jack and the widening frame, and finally remove the lower template;

[0023] Furthermore, the specific method of removing the heightening box in step 2 is as follows:

[0024] Step 21. Prepare safety protection measures;

[0025] Step 22: Lower the cylinder;

[0026] Step 23: Firmly install four sets of mechanical jacks and tighten them;

[0027] Step 24: Loosen all bolts of the heightening box;

[0028] Step 25: Jacks are lifted synchronously;

[0029] Step 26: Remove the heightening box;

[0030] Step 27: Insert the long screw safety positioning bolt into the bolt hole;

[0031] Step 28: Tighten the long screw safety positioning bolt while lowering the jack synchronously. After the trolley is lowered into place, remove the jack and safety protection equipment, and replace the working bolts one by one on the bolt holes;

[0032] Furthermore, the order of shrinking the whole set of templates in step 4 is to shrink the long lead screw first, install the short lead screw, remove the long lead screw, and then shrink the short lead screw, and finally make the whole set of templates within the standard section;

[0033] Furthermore, the specific method of the step 5 of moving the trolley axis from the center line of the emergency parking zone to the center line of the tunnel is: in the widening section, the lateral movement is realized by longitudinal movement with an angle, and the center line of the trolley is moved from the center line of the widening section to the center line of the standard section between the forward and backward movement, and the deflection angle and the longitudinal movement length are determined by calculation according to the spacing between the travel wheel limiting structure and the track edge and the longitudinal spacing between the travel wheels;

[0034] Furthermore, in step 6, the trolley is moved automatically, assisted by manual turnover and reverse transportation of rails, with a daily walking distance of 750m to 850m until it reaches the turning area, where the slope is required to be within 0.5%, and the opening is arranged and the trolley moves horizontally;

[0035] Furthermore, the specific method of converting the longitudinal walking to the lateral walking in the turning area in step 7 is as follows: after the longitudinal walking reaches the turning area, the turning operation is performed, and the turning steps are:

[0036] Step 71: Install safety measures and use the mechanical jack to lift the trolley synchronously;

[0037] Step 72: Use the steering box to convert the longitudinal walking system into a transverse walking system, install the transverse walking track, and return the mechanical jack;

[0038] Step 73: The trolley falls onto the transverse track, the jack and safety device are removed, and the trolley moves laterally.

[0039] Compared with the prior art, the present invention has the following beneficial effects:

[0040] 1. The present invention overcomes the shortcomings of the prior art. The No. 1 side formwork, the No. 2 side formwork and the top formwork are connected in a hinged manner. The No. 1 side formwork and the No. 2 side formwork tend to open outward through the hinged connection. An oil cylinder is provided on the main beam inside to raise or lower the top formwork, thereby expanding or reducing the size of the outer shell to match the overall cross-sectional size of the tunnel.

[0041] 2. The present invention proposes a new construction method, which uses steps 1 to 7 to adjust the size of the trolley shell to adapt to the size of the inner wall of the tunnel, and enables the trolley to move along the tunnel, thereby solving the problem of the secondary lining trolley directly pouring the parking strip as a whole.

[0042] Third, the device of the present invention is easy to operate, and the construction method is also easy to operate. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] Figure 1 is a cross-sectional view of the overall structure of the present invention in use;

[0044] Figure 2 is a cross-sectional view of the overall structure of the present invention;

[0045] Figure 3 It is an operation schematic diagram of step 1 of the construction method of the present invention;

[0046] Figure 4 It is an operation schematic diagram of step 2 of the construction method of the present invention;

[0047] Figure 5 It is an operation schematic diagram of step 4 of the construction method of the present invention;

[0048] Figure 6 It is an operation schematic diagram of step five of the construction method of the present invention;

[0049] Figure 7 It is a schematic diagram of the longitudinal movement state and a schematic diagram of the transverse movement in step seven of the construction method of the present invention;

[0050] Figure 8 It is a top view showing the operation of step seven of the construction method of the present invention. DETAILED DESCRIPTION

[0051] Specific implementation method 1: Combination Figure 1 and 2 To explain this embodiment, a special trolley for fast transition of a tunnel widening section described in this embodiment comprises a housing, a plurality of screw rods 7, a supporting mechanism and a driving mechanism 11;

[0052] The support mechanism is hingedly connected to the inner surface of the housing through a plurality of screw rods 7, and a driving mechanism 11 is provided at the bottom end of the support mechanism;

[0053] The shell includes a top template 5, a first side template 8 and a second side template 14; one end of the top template 5 is hinged to one end of the first side template 8, and the other end of the top template 5 is hinged to one end of the second side template 14, and the top template 5, the first side template 8 and the second side template 14 form a semi-cylindrical shape with a cavity;

[0054] The supporting mechanism includes a widening frame 1, a crossbeam 2, a cylinder 3, a cylinder frame 4, a heightening box 9, a rib plate 10 and a longitudinal support arm 12;

[0055] A longitudinal support arm 12 is provided at each end of the cross beam 2, the bottom end of the longitudinal support arm 12 is connected to one end of the heightening box 9, the other end of the heightening box 9 is connected to the driving mechanism 11, a rib plate 10 is provided between the inner side of the longitudinal support arm 12 and the lower surface of the cross beam 2, a widening frame 1 is provided at the outer center of the longitudinal support arm 12, two oil cylinders 3 are evenly provided on the upper surface of the cross beam 2, and the two oil cylinders 3 are symmetrically arranged, and the output ends of the two oil cylinders 3 pass through the cylinder frame 4 and are fixedly connected to the lower surface of the top template 5.

[0056] Specific implementation method 2: Combination Figure 2 The present embodiment is described. The present embodiment is a further limitation on the trolley described in the first specific embodiment. The present embodiment describes a special trolley for rapid transfer of a tunnel widening section. The driving mechanism 11 comprises a motor and a driving wheel. The output end of the motor is connected to a large pulley, the large pulley is connected to a small pulley via a belt, and the small pulley is coaxially connected to the driving wheel.

[0057] Specific implementation method three: Combination Figure 2 This embodiment is described as a further limitation of the trolley described in the second specific embodiment. This embodiment describes a special trolley for rapid transfer of tunnel widening sections, and the driving wheel is provided with a groove along the outer circumferential surface.

[0058] Specific implementation method four: Combination Figure 2 The present embodiment is described as a further limitation of the trolley described in the first specific embodiment. The present embodiment is a special trolley for rapid transition of a tunnel widening section, and the diameter of the screw rod 7 is 20 mm to 30 mm.

[0059] Specific implementation method five: Combination Figure 2 The present embodiment is described as a further limitation of the trolley described in the fourth embodiment. The present embodiment is a special trolley for rapid transition of a tunnel widening section, and the diameter of the screw rod 7 is 25 mm.

[0060] Specific implementation method six: Combination Figure 2 This embodiment is described as a further limitation of the trolley described in the first specific embodiment. This embodiment is a special trolley for rapid transfer of tunnel widening sections, and the top template 5, the first side template 8 and the second side template 14 have the same thickness.

[0061] Specific implementation method seven: Combination Figure 2This embodiment is described as a further limitation of the trolley described in the sixth embodiment. This embodiment describes a special trolley for rapid transition of a tunnel widening section, and the thickness of the top template 5 is 1.5m to 3m.

[0062] Specific implementation method eight: Combination Figure 1 and 2 This embodiment describes a method for constructing a special trolley for rapid transfer of a tunnel widening section, and the specific process is as follows:

[0063] Step 1: Remove the lower template and widening frame;

[0064] Step 2: Remove the mast heightening box;

[0065] Step 3: Continue to lower the main top cylinder to 0 stroke, so that the overall height of the trolley is lower than the main hole contour line;

[0066] Step 4: Replace the edge support screw and shrink the entire template within the standard section:

[0067] Step 5: Move the trolley axis from the center line of the emergency parking strip to the center line of the tunnel;

[0068] Step 6: Move the trolley through the tunnel to the turning area outside the tunnel entrance;

[0069] Step 7: Change the vertical walking to horizontal walking in the turning area;

[0070] Step 8: Walk horizontally to the turning area of ​​another hole, and then change to vertical walking mode according to the above steps;

[0071] Step 9: After reaching the widening section, reverse the above steps and start the secondary lining construction.

[0072] Specific implementation method nine: Combination Figure 2 This embodiment is described. This embodiment is a further limitation of the trolley described in the specific embodiment eight. This embodiment describes a method for constructing a special trolley for rapid transfer of a tunnel widening section. The specific method of step one, removing the lower formwork and the widening frame, is as follows: if the circumference of the widened section is greater than the circumference of the standard section, the lower formwork must be removed before the section can be shrunk. The removal method is to first support the lower formwork with a long screw rod, then remove the hydraulic top and the widening frame, and finally remove the lower formwork.

[0073] Specific implementation method and ten: combination Figure 2 This embodiment is described. This embodiment is a further limitation of the trolley described in the eighth embodiment. The construction method of a special trolley for rapid transfer of a tunnel widening section described in this embodiment, the specific method of removing the heightening box in step 2 is as follows:

[0074] Step 21. Prepare safety protection measures;

[0075] Step 22: Lower the cylinder;

[0076] Step 23: Firmly install four sets of mechanical jacks and tighten them;

[0077] Step 24: Loosen all bolts of the heightening box;

[0078] Step 25: Jacks are lifted synchronously;

[0079] Step 26: Remove the heightening box;

[0080] Step 27: Insert the long screw safety positioning bolt into the bolt hole;

[0081] Step 28. Tighten the long-screw safety positioning bolt while lowering the jack. After the trolley is lowered into place, remove the jack and safety protection equipment, and replace the working bolts on the bolt holes one by one.

[0082] Specific implementation method eleven: Combination Figure 2 To explain this embodiment, this embodiment is a further limitation of the trolley described in the specific embodiment eight. This embodiment describes a method for constructing a special trolley for rapid transfer of a tunnel widening section. The order of shrinking the entire set of templates in step four is to first shrink the long lead screw, install the short lead screw, and remove the long lead screw, then shrink the short lead screw, and finally make the entire set of templates within the standard section.

[0083] Specific implementation method 12: Combination Figure 2 To explain this embodiment, this embodiment is a further limitation of the trolley described in the specific embodiment eight. This embodiment describes a method for constructing a special trolley for rapid transfer of a tunnel widening section. The specific method of moving the trolley axis from the center line of the emergency parking zone to the center line of the tunnel in step five is: within the widening section, this lateral shift is achieved by longitudinal shift with an angle, and the center line of the trolley is moved from the center line of the widening section to the center line of the standard section between the advance and retreat. The size of the deflection angle and the length of the longitudinal shift are determined by calculation based on the spacing between the traveling wheel limiting structure and the edge of the track and the longitudinal spacing between the traveling wheels.

[0084] Specific implementation method 13: Combination Figure 2 This embodiment is described. This embodiment is a further limitation of the trolley described in the specific embodiment eight. This embodiment describes a method for constructing a special trolley for rapid transfer of a tunnel widening section. In step six, the trolley moves automatically, assisted by manual turnover and reverse transportation of rails. The daily walking distance is 750m to 850m until it reaches the turning area. The turning area requires a slope within 0.5%, and the tunnel entrance is arranged and the trolley moves horizontally.

[0085] Specific implementation method 14: Combination Figure 2This embodiment is described. This embodiment is a further limitation of the trolley described in the specific embodiment eight. The construction method of a special trolley for rapid transfer of a tunnel widening section described in this embodiment, the specific method of converting longitudinal walking to lateral walking in the turning area in step seven is as follows: after the longitudinal walking reaches the turning area, the turning operation is performed, and the turning steps are:

[0086] Step 71: Install safety measures and use the mechanical jack to lift the trolley synchronously;

[0087] Step 72: Use the steering box to convert the longitudinal walking system into a transverse walking system, install the transverse walking track, and return the mechanical jack;

[0088] Step 73: The trolley falls onto the transverse track, the jack and safety device are removed, and the trolley moves laterally.

Claims

1. A method for constructing a special trolley for rapid transition of a tunnel widening section, characterized in that: The special trolley for rapid transition of tunnel widening section comprises a housing, a plurality of screw rods (7), a supporting mechanism and a driving mechanism (11); The support mechanism is hingedly connected to the inner surface of the housing through a plurality of screw rods (7), and a driving mechanism (11) is provided at the bottom end of the support mechanism; The shell comprises a top template (5), a first side template (8) and a second side template (14); one end of the top template (5) is hinged to one end of the first side template (8), and the other end of the top template (5) is hinged to one end of the second side template (14), and the top template (5), the first side template (8) and the second side template (14) form a semi-cylindrical shape with a cavity; The supporting mechanism comprises a widening frame (1), a crossbeam (2), an oil cylinder (3), an oil cylinder frame (4), a heightening box (9), a rib plate (10) and a longitudinal support arm (12); A longitudinal arm (12) is provided at each end of the cross beam (2), the bottom end of the longitudinal arm (12) is connected to one end of the heightening box (9), the other end of the heightening box (9) is connected to the driving mechanism (11), a rib plate (10) is provided between the inner side of the longitudinal arm (12) and the lower surface of the cross beam (2), a widening frame (1) is provided at the outer center of the longitudinal arm (12), two oil cylinders (3) are evenly provided on the upper surface of the cross beam (2), and the two oil cylinders (3) are symmetrically arranged, the output ends of the two oil cylinders (3) pass through the oil cylinder frame (4) and are fixedly connected to the lower surface of the top template (5); the driving mechanism (11) comprises a motor and a driving wheel, the output end of the motor is connected to a large pulley, the large pulley is connected to a small pulley through a belt, and the small pulley is coaxially connected to the driving wheel; the driving wheel is provided with a groove along the outer circumferential surface; The specific process of the construction method is as follows: Step 1: Remove the lower template and widening frame; Step 2: Remove the mast heightening box; Step 3: Continue to lower the main top cylinder to 0 stroke, so that the overall height of the trolley is lower than the main hole contour line; Step 4: Replace the edge support screw and shrink the entire template within the standard section: Step 5: Move the trolley axis from the center line of the emergency parking strip to the center line of the tunnel; Step 6: Move the trolley through the tunnel to the turning area outside the tunnel entrance; Step 7: Change the vertical walking to horizontal walking in the turning area; Step 8: Walk horizontally to the turning area of ​​another hole, and then change to vertical walking mode according to the above steps; Step 9: After reaching the widening section, reverse the above steps and start the secondary lining construction.

2. A method for constructing a special trolley for rapid transition of a tunnel widening section according to claim 1, characterized in that: The specific method of removing the lower template and the widening frame in step 1 is as follows: the circumference of the widened section is greater than the circumference of the standard section, and the section can be shrunk only after the lower template is removed. The removal method is to first support the lower template with a long screw rod, then remove the hydraulic top and the widening frame, and finally remove the lower template.

3. The method for constructing a special trolley for rapid transition of a tunnel widening section according to claim 1 is characterized in that: The specific method of removing the heightening box in step 2 is as follows: Step 21. Prepare safety protection measures; Step 22: Lower the cylinder; Step 23: Firmly install four sets of mechanical jacks and tighten them; Step 24: Loosen all bolts of the heightening box; Step 25: Jacks are lifted synchronously; Step 26: Remove the heightening box; Step 27: Insert the long screw safety positioning bolt into the bolt hole; Step 28. Tighten the long-screw safety positioning bolt while lowering the jack. After the trolley is lowered into place, remove the jack and safety protection equipment, and replace the working bolts on the bolt holes one by one.

4. The method for constructing a special trolley for rapid transition of a tunnel widening section according to claim 1 is characterized in that: The order of shrinking the whole set of templates in step 4 is to shrink the long lead screw first, install the short lead screw, remove the long lead screw, and then shrink the short lead screw, and finally make the whole set of templates within the standard section.

5. The method for constructing a special trolley for rapid transition of a tunnel widening section according to claim 1 is characterized in that: The specific method of the step 5 of moving the trolley axis from the center line of the emergency parking zone to the center line of the tunnel is: in the widened section, this lateral movement is achieved by longitudinal movement with an angle, and the center line of the trolley is moved from the center line of the widened section to the center line of the standard section between the forward and backward movements. The size of the deflection angle and the length of the longitudinal movement are determined by calculation based on the spacing between the running wheel limiting structure and the edge of the track and the longitudinal spacing between the running wheels.

6. The method for constructing a special trolley for rapid transition of a tunnel widening section according to claim 1 is characterized in that: In the step six, the trolley moves automatically, assisted by manual turnover and reverse transportation of rails. The daily walking distance is 750m to 850m until it reaches the turning area. The turning area requires a slope within 0.5%, and the tunnel opening is arranged and the trolley moves horizontally.

7. The method for constructing a special trolley for rapid transition of a tunnel widening section according to claim 1 is characterized in that: The specific method of converting longitudinal walking to lateral walking in the turning area in step 7 is as follows: after longitudinal walking to the turning area, a turning operation is performed, and the turning steps are: Step 71: Install safety measures and use the mechanical jack to lift the trolley synchronously; Step 72: Use the steering box to convert the longitudinal walking system into a transverse walking system, install the transverse walking track, and return the mechanical jack; Step 73: The trolley falls onto the transverse track, the jack and safety device are removed, and the trolley moves laterally.