Method and device for resource planning in a factory based on simulation and recording medium thereof

By modeling factory resources into capacity buckets and allocating requirements within a predetermined time period, the limitations of resource allocation in the existing technology are solved, and more effective resource planning and customer satisfaction improvement are achieved.

CN112149944BActive Publication Date: 2024-12-03VMS SOLUTIONS
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202010550703.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Priority Date
2019-06-28
Filing Date
2020-06-16
Publication Date
2024-12-03
Estimated Expiration
2040-06-16

AI Technical Summary

Technical Problem

Existing factory resource scheduling methods are difficult to effectively allocate limited resources to meet all needs, especially when considering resource time unit constraints.

Method used

By modeling factory resources as capacity buckets and re-allocating requirements in bucket rolling cycles over a predetermined time period, using priority rules and machine-level priority adjustments to achieve more efficient and accurate resource planning.

Benefits of technology

More effective and accurate resource planning is achieved, ensuring maximum plant operation efficiency and customer satisfaction are maximized, and unmet needs are avoided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112149944B_ABST
    Figure CN112149944B_ABST
Patent Text Reader

Abstract

The present invention provides a method for resource planning in a factory based on simulation, a device and a recording medium thereof. The resource planning method may include: a step of modeling factory resources as capacity storage buckets; a step of allocating multiple requirements to the modeled capacity storage buckets; and a step of performing capacity storage bucket simulation based on the factory resources allocated with multiple requirements to establish factory resource planning.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to a simulation-based in-factory resource planning method and apparatus, and more specifically, to a simulation-based in-factory resource planning method and apparatus, which allocate multiple demands to factory resources modeled as capacity buckets, and implement factory resource planning for each machine unit within a bucket step by performing a simulation of such demand allocation in a bucket rolling cycle within a predetermined time period. Background Art

[0002] Factories, such as semiconductor manufacturing plants, are among the most sophisticated artificial systems, typically consisting of hundreds or thousands of expensive devices connected to automated resource handling systems. If the optimal work schedule is established within a factory consisting of such a large number of devices, the productivity of the factory can be significantly improved.

[0003] In order to meet all demands in a factory environment with so many resources (equipment, personnel, etc.), it is important to properly allocate multiple demands to limited resources.

[0004] However, existing factory resource scheduling methods (e.g., Order by Order, etc.) simply schedule the process in reverse according to the delivery time of the demand, or only consider the entire process capacity without a separate simulation process. Therefore, it is not only difficult to reflect the time unit constraints of resources, but also has limitations in effectively allocating limited factory resources to meet all demands.

[0005] Therefore, there is a growing demand in the technical field, especially for those responsible for in-plant resource design, for a novel in-plant resource planning method and apparatus thereof, which can take into account the time unit constraints of resources when modeling the resources of a factory as specified time unit capacity storage buckets and performing a simulation of allocating multiple demands to such capacity storage buckets. Summary of the invention

[0006] The present invention is proposed to solve the above-mentioned problem, and an object of the present invention is to provide the following simulation-based factory resource planning method and device, which can utilize the limited resources in the factory to realize effective resource planning for meeting multiple demands.

[0007] Furthermore, an object of the present invention is to provide a simulation-based in-factory resource planning method and apparatus thereof, which can take into account the time unit constraints of resources and thereby achieve more efficient and accurate resource planning.

[0008] Furthermore, an object of the present invention is to provide a simulation-based in-factory resource planning method and device thereof, which establishes resource planning at the machine level within a storage bucket step that performs the same process, thereby enabling more efficient and accurate resource planning.

[0009] Furthermore, an object of the present invention is to provide a simulation-based in-factory resource planning method and device thereof, which establishes resource planning based on the priorities of multiple demands and / or the priorities of multiple machines within a bucket step, thereby more effectively meeting all possible demands.

[0010] Furthermore, an object of the present invention is to provide a simulation-based factory resource planning method and device thereof, which can variably adjust the priorities of multiple demands and / or the priorities of multiple machines within a bucket step according to the process or time, thereby avoiding unmet demands, thereby maximizing factory operating efficiency and customer satisfaction.

[0011] The technical problems of the present invention are not limited to the technical problems mentioned above, and ordinary technicians in the technical field to which the present invention belongs can clearly understand other technical problems not mentioned from the following description.

[0012] A simulation-based factory resource planning method according to an embodiment of the present invention for solving the technical problem may include: a step of modeling factory resources as capacity buckets; a step of allocating multiple demands to the modeled capacity buckets; and a step of establishing factory resource planning by repeating the step of allocating multiple demands to the modeled capacity buckets at a bucket rolling period (BRP) within a predetermined time period.

[0013] Furthermore, the factory resources may include a plurality of bucket steps (BucketStep) respectively constituted by a plurality of machines (machine), and the step of modeling the factory resources as capacity buckets may include the step of modeling the plurality of machines as the capacity buckets respectively.

[0014] Furthermore, the step of allocating the plurality of requirements to the modeled capacity storage bucket may include the step of prioritizing the plurality of requirements according to a prescribed priority rule, and allocating the plurality of requirements to the modeled capacity storage bucket based on the prioritized plurality of requirements.

[0015] Furthermore, it may also include a step of prioritizing multiple machines included in each storage bucket step, and the step of allocating multiple demands to the modeled capacity storage bucket may include a step of further allocating the multiple demands to the modeled capacity storage bucket based on the prioritized multiple machines.

[0016] Furthermore, the step of allocating the plurality of demands to the modeled capacity storage bucket may include: the step of dividing the plurality of demands into one or more batches respectively; and the step of allocating the one or more divided batches to the modeled capacity storage bucket.

[0017] And, the bucket rolling period (BRP) may correspond to a time unit of the capacity bucket.

[0018] Furthermore, the simulation-based in-factory resource planning method may further include: a step of determining whether there is a demand among the multiple demands that cannot meet the delivery time condition; when the determination result is that there is at least one demand that cannot meet the delivery time condition, a step of adjusting the priority of the corresponding demand; and a step of allocating the multiple demands based on a new priority rule reflecting the adjusted priority.

[0019] Furthermore, a simulation device of another embodiment of the present invention for solving the technical problem, which is used to establish a simulation-based in-factory resource planning, may include: a modeling unit for modeling factory resources as capacity buckets; a demand allocation unit for allocating multiple demands to the modeled capacity buckets; and a control unit for repeatedly allocating multiple demands to the modeled capacity buckets at a bucket rolling period (BRP) within a predetermined time period to establish a factory resource planning.

[0020] Furthermore, a computer-readable recording medium according to another embodiment of the present invention for solving the technical problem may record a program for executing the simulation-based in-plant resource planning method.

[0021] According to a simulation-based factory resource planning method and device thereof according to an embodiment of the present invention, limited resources within the factory can be used to implement effective resource planning for meeting multiple demands.

[0022] Furthermore, the simulation-based in-factory resource planning method and device thereof according to an embodiment of the present invention can take into account the time unit constraints of resources, thereby achieving more efficient and accurate resource planning.

[0023] Furthermore, according to a simulation-based in-factory resource planning method and apparatus thereof according to an embodiment of the present invention, resource planning is established at the machine level set within the bucket stepping executing the same process, thereby achieving more efficient and accurate resource planning.

[0024] Furthermore, according to a simulation-based factory resource planning method and device according to an embodiment of the present invention, resource planning is established based on the priorities of multiple demands and / or the priorities of multiple machines within a bucket step, so that all possible demands can be met more effectively.

[0025] Furthermore, according to a simulation-based factory resource planning method and device according to an embodiment of the present invention, the priorities of multiple demands and / or the priorities of multiple machines within a bucket step can be variably adjusted according to the process or time, thereby avoiding unmet demands, thereby maximizing factory operating efficiency and customer satisfaction. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] In order to more fully understand the drawings referenced in the detailed description of the present invention, a brief description of each drawing is provided below.

[0027] Figure 1a FIG. 1 is a simplified diagram for explaining the steps of resource planning in a factory based on simulation according to an embodiment of the present invention. Figure 1b is a conceptual diagram for explaining a capacity bucket in which factory resources are modeled. Figure 1c A conceptual diagram used to illustrate the correlation between demand and batch.

[0028] Figure 2a to Figure 2c The diagram is an illustration of a series of processes for establishing a simulation-based resource planning within a factory according to an embodiment of the present invention for a plurality of bucket steps within the factory and machines within each bucket step.

[0029] Figure 3 FIG. 1 is a block diagram of a simulation device 100 for establishing a simulation-based resource planning within a factory according to an embodiment of the present invention.

[0030] Figure 4 It is a sequence diagram for describing a method for resource planning in a factory based on simulation according to an embodiment of the present invention.

[0031] Explanation of symbols

[0032] 100: Simulation Device

[0033] 110: Control unit

[0034] 120: Communication unit

[0035] 130: Modeling Unit

[0036] 140: Demand Allocation Unit

[0037] 150: Storage unit DETAILED DESCRIPTION

[0038] Hereinafter, embodiments of the present invention will be described with reference to the accompanying drawings. It should be noted that in the process of assigning reference numerals to the structural elements of each of the accompanying drawings, the same reference numerals are assigned to the same structural elements as much as possible even if they are shown in different drawings. Furthermore, in the process of describing the present invention, when it is determined that the specific description of the relevant known structure or function may confuse the main purpose of the present invention, the detailed description thereof will be omitted. Furthermore, embodiments of the present invention will be described below, but the technical idea of ​​the present invention is not limited or restricted by the described embodiments, but can be implemented in various ways by ordinary technicians in the technical field to which the present invention belongs through deformation.

[0039] Throughout the specification, when it is indicated that one part is "connected" to another part, this includes the case of "direct connection" and the case of "indirect connection" with other components between the two. Throughout the specification, when it is indicated that a part "includes" another structural element, unless otherwise specifically stated, this does not mean that other structural elements are excluded, but other structural elements may also be included. In addition, in the process of describing the structural elements of the present invention, terms such as first, second, A, B, (a), (b), etc. may be used. These terms are only used to distinguish their structural elements from other structural elements, and the nature, order or sequence of the corresponding structural elements are not limited thereto.

[0040] Figure 1a FIG. 1 is a simplified diagram for explaining the steps of resource planning in a factory based on simulation according to an embodiment of the present invention. Figure 1b is a conceptual diagram for explaining a capacity bucket in which factory resources are modeled. Figure 1c A conceptual diagram used to illustrate the correlation between demand and batch.

[0041] First, in the following description of the simulation-based factory resource planning method and device, the relevant terms are defined as follows. Multiple devices configured in the factory are used to perform specific processes, where a group of multiple devices used to perform the same process is called a bucket step. For reference, a bucket step can also be called a station.

[0042] Furthermore, within each bucket step, multiple devices are included, and like this, the devices within the bucket step for performing the same process are called machines. Within the bucket step, multiple machines can be configured to perform the same work, or within the bucket step, multiple machines are configured to perform different work belonging to the same process (for example, although it is the same etching process, different dry etching and wet etching work are performed). In particular, in the latter case, different capacity buckets can be modeled for each machine, which will be described in more detail later.

[0043] Furthermore, the equipment, personnel and other resources configured in the factory are required to manufacture various types of products, rather than a single product, and their delivery time, quantity, etc. are also different. Such customer requirements are called demands, which may at least include information such as items (e.g., TV), quantity (e.g., 1,000), delivery time (e.g., January 5), whether it can be delivered before the delivery time (e.g., no), and the delivery party (e.g., XX Electronics).

[0044] Based on this illustrative definition in this specification, reference is made to Figure 1a In the conceptual diagram, the factory is configured with multiple bucket steps (BucketStep A, BucketStep B, ..., BucketStep Z), each bucket step is provided with multiple machines (M1, M2, ...), and the limited resources as described above can be utilized to perform simulation-based resource planning for meeting multiple demands.

[0045] The resources in the factory can be modeled as capacity buckets of time units. Figure 1a In the diagram, “①” is used to schematically illustrate this capacity bucket modeling. The term “capacity bucket” is equivalent to representing the amount of work that can be done on a specific machine within a specified time. Figure 1b Equivalent to a conceptual diagram used to illustrate the capacity buckets in which factory resources are modeled.

[0046] For example, in Figure 1bIn the example, machine 1 is set in bucket step A. Assuming that bucket step A is a bucket step for the etching process, machine 1 can be modeled as the number of pieces that can be etched within a unit time (Time 1, Time 2, Time 3, Time 4, Time 5, etc.). For example, each machine in the bucket step can be modeled as a capacity bucket that etches 1000 pieces / day, etches 500 pieces / 8 hours, etc. For reference, the time unit of the modeled capacity bucket can be various (for example, 4h, 6h, 12h, 1 day, 2 days, 1 week, etc.). In the following description, "1 day" will be used as an example for description to make it easier to understand the present invention.

[0047] As schematically shown Figure 1a ①, after modeling the factory resources as capacity storage buckets, a step of allocating multiple requirements to the modeled capacity storage buckets may be performed, which Figure 1a Of course, multiple demands can also be randomly assigned to the factory resources modeled as capacity buckets, but there are also work priorities among multiple demands based on delivery time, importance, delivery party, etc. Therefore, it is preferred to prioritize multiple demands according to predetermined (or specified) priority rules and assign them to the factory resources modeled as capacity buckets starting with the demands with the highest priority.

[0048] Multiple requirements can be allocated to capacity buckets modeled as batches. Figure 1c A conceptual diagram for illustrating the relationship between demand and batches. Batches can be called "work items", such as Figure 1c As shown in part (a) of , a single demand can be considered as a single batch, or, as Figure 1c As shown in part (b) of FIG. 1 , a single demand may be considered as multiple batches. In the latter case, the simulation-based in-factory resource planning method of an embodiment of the present invention may further include: (i) dividing the multiple demands into more than one batch; and (ii) allocating the divided more than one batch to the modeled capacity storage bucket. For reference, in the following description Figure 2a to Figure 2c In the exemplary description, each requirement is implemented as a structure of a single batch, but it can be clearly understood that the embodiments described below can also be applied to structures implemented as multiple batches.

[0049] Figure 1a The process of modeling factory resources as capacity buckets shown in ① and Figure 1aThe process of allocating multiple requirements to the modeled capacity buckets shown by ② in FIG. 1 is equivalent to a simulation process, wherein the simulation is performed based on the resources modeled as capacity buckets, and is therefore referred to as capacity bucket simulation (CBS) in the following specification, and the device that performs such simulation is referred to as simulation device 100 (hereinafter, referred to as simulation device 100). Figure 3 ), or simply referred to as the capacity storage bucket simulation module 100.

[0050] like Figure 1a As shown by "③", this simulation is performed in a predetermined time period (e.g., 30 days, 60 days, etc.) with a bucket rolling period (BRP). In the following description, the bucket rolling period (BRP) is described as 1 day to facilitate understanding of the present invention. Therefore, if the predetermined time period is 30 days, the simulation processes of ① and ② can be performed 30 times at 1-day intervals to establish the specified factory resource planning (③).

[0051] For reference, such capacity bucket simulation (CBS) corresponds to discrete event-based simulation rather than continuous event-based simulation, and thus can be considered as a part of discrete event simulation (DES).

[0052] Figure 2a to Figure 2c The diagram is an illustration of a series of processes for establishing a simulation-based resource planning within a factory according to an embodiment of the present invention for a plurality of bucket steps within the factory and machines within each bucket step.

[0053] like Figure 1a As schematically described in , a simulation-based in-factory resource planning method according to an embodiment of the present invention may be accompanied by the steps of modeling factory resources as capacity buckets (①); allocating multiple demands to the modeled capacity buckets (②); and repeatedly allocating demands in a bucket rolling period (BRP) within a predetermined time period to establish a factory resource plan (③). Figure 2a to Figure 2c This simulation-based factory resource planning method is described in more detail with reference to the exemplary requirements and exemplary factory resources in FIG.

[0054] First, in the process of allocating multiple demands to a modeled capacity storage bucket, the simulation-based factory resource planning method of an embodiment of the present invention can prioritize the multiple demands according to prescribed priority rules, and allocate the multiple demands to the modeled capacity storage bucket based on the multiple demands prioritized in the manner as described above.

[0055] In order to make the present invention easier to understand, Figure 2a According to the prescribed priority rules, among these multiple requirements, January 1 is taken as the standard, and it is assumed that the requirement "TV, 1000, ACB, January 5" has the highest priority. Among them, the requirement "TV, 1000, ACB, January 5" means that 1000 TV products need to be manufactured by January 5, and the process sequence of ACB is required to manufacture TVs in the factory. For reference, in addition to the exemplified information, the requirements may further include information such as whether it can be delivered before the delivery time (for example, it cannot be delivered), the delivery party (for example, XX Electronics), etc.

[0056] like Figure 2a As shown, the TV needs to execute the A process first, so the TV-demand is first allocated to the storage bucket step A ( Figure 2a In the case of bucket step A, since the capacity of the bucket is 1000 per day, it is estimated that one day is required to process the TV-required process A in bucket step A. Therefore, in order to process the TV-required process A on January 1, multiple machines (M A 1. M A 2. ..., M A L ) (where L is a natural number greater than 2). In the process of selecting one of the multiple machines belonging to the same storage bucket step, a specified priority rule can be considered, wherein the priority rule can be based on, for example, factory environment, constraints, quality, settings, etc. In the process of allocating multiple demands to the modeled capacity storage buckets, the simulation-based factory resource planning method of an embodiment of the present invention can further reflect the priority changes of the demands based on time changes and / or the priority changes of the machines, thereby more realistically and completely meeting the conditions of multiple demands.

[0057] Therefore, the simulation-based in-factory resource planning method of another embodiment of the present invention may also include a step of prioritizing the multiple machines included in each storage bucket step, and may further allocate multiple demands to the modeled capacity storage bucket based on the multiple machines prioritized by the method described above.

[0058] If the A process of 1000 TVs is completed, the demand allocation for the C process that needs to be performed later can be performed. Since the C process needs to be performed later, the TV-demand ( Figure 2aIn the case of bucket step C, since the capacity of the bucket is 1000 per day, it is estimated that one day is required to process the TV-required C process in bucket step C. Therefore, in order to process the TV-required C process on January 2, multiple machines (M C 1. M C 2. ..., M C K ) (where K is a natural number greater than 2). Here too, in the process of selecting one of the multiple machines belonging to the same bucket step, a prescribed priority rule may be considered, for example, the priority rule may be based on factory environment, constraints, quality, settings, etc.

[0059] If the C process of 1000 TVs is completed, the demand allocation for the subsequent B process can be performed. Since the B process needs to be performed later, the TV-demand ( Figure 2a In the case of bucket step B, since the capacity of the bucket is 500 per day, it is estimated that it will take 2 days to process the TV-demanded process B in bucket step B. Therefore, in order to process the TV-demanded process C on January 3 and January 4, multiple machines (M B 1. M B 2. ..., M B N ) (where N is a natural number greater than 2). Here too, in the process of selecting one of the multiple machines belonging to the same bucket step, a prescribed priority rule may be considered, for example, the priority rule may be based on factory environment, constraints, quality, settings, etc.

[0060] Through this process, the demand "TV, 1000, ACB, January 5" with the highest priority on January 1 can be assigned to the factory resources modeled as capacity storage buckets, so that it can be expected that the demand "TV, 1000, ACB, January 5" can be completed on January 4, that is, the manufacturing can be completed normally before the delivery time (January 5).

[0061] Among them, when the demand "TV, 1000 pieces, ACB, January 5" corresponds to a demand that cannot be delivered before the delivery time, for example, when the customer requests the condition that 1000 televisions must be manufactured on January 5 due to reasons such as the storage costs of the products, the demand allocation unit 140 of the present invention can adjust the delivery time of the demand "TV, 1000 pieces, ACB, January 5" to January 5 by lowering the priority of the demand "TV, 1000 pieces, ACB, January 5" or setting a 1-day pause period between the ACB processes.

[0062] Figure 2b The allocation of the demand "display, 1000, AB, January 7" with a lower priority is briefly shown. The demand "display, 1000, AB, January 7" means that 1000 display products need to be manufactured by January 7, and the process sequence AB needs to be passed in the factory to manufacture the display. For reference, in addition to the information shown, the demand may further include information such as whether it can be delivered before the delivery time (for example, it cannot be delivered), the delivery party (for example, XX Electronics), etc.

[0063] like Figure 2b As shown, the display needs to execute process A first, so the display-demand is first allocated to the storage bucket step A ( Figure 2b In the case of bucket step A, since the capacity of the bucket is 1000 per day, it is estimated that it will take 1 day to process the display-demand process A in bucket step A. It is assumed that the demand allocation to all machines in bucket step A is completed on January 1.

[0064] Therefore, in order to process the display-demand A process on January 2, multiple machines (M) set in the storage bucket step A can be sent to the storage bucket step A. A 1. M A 2. ..., M A L ) (where L is a natural number greater than 2). In the process of selecting one of the multiple machines belonging to the same bucket step, a prescribed priority rule may be considered, wherein the priority rule may be based on, for example, factory environment, constraints, quality, settings, etc. In particular, Figure 2b In the example of selecting a machine for process A that processes the display-demand, M A The priority of machine 1 is set very low because AMachine 1 is adjusted to perform process A of manufacturing TV on January 1, so if the TV as a manufactured product is changed to a monitor in the same machine, that is, the same line, a setup will occur. Therefore, it is preferred to set the priority of multiple machines in the bucket step in the direction of minimizing setup. Figure 2b Shown in A 2 machines instead of M A 1 Machine allocation display - Example of demand.

[0065] If the A process of 1000 displays is completed, the demand allocation for the subsequent B process can be performed. Since the B process needs to be performed later, the display demand ( Figure 2b In the case of bucket step B, since the capacity of the bucket is 500 per day, it is estimated that it will take 2 days to process the display-required B process in bucket step B. Therefore, in order to process the display-required B process on January 3 and January 4, multiple machines (M B 2. ..., M B N ) (where N is a natural number greater than 2) allocates a display-demand to one of the machines, Figure 2b The example shows that the allocation in M B N Example of a machine.

[0066] Through this process, the demand "monitors, 1000 units, AB, January 7" with a lower priority based on January 1 can be assigned to the factory resources modeled as capacity storage buckets, so that it can be expected that the demand "monitors, 1000 units, AB, January 7" can be completed on January 4, that is, the manufacturing can be completed normally before the delivery time (January 7).

[0067] Similarly, when the demand "display, 1000 pieces, AB, January 7" corresponds to a demand that cannot be delivered before the delivery time, the demand allocation unit 140 of the present invention can adjust the delivery time of the demand "display, 1000 pieces, AB, January 7" to January 7 by further lowering the priority of the demand "display, 1000 pieces, AB, January 7" or setting a 3-day pause period between the AB processes.

[0068] Figure 2c Corresponding to the description Figure 2b A conceptual diagram of an embodiment in which time unit constraints of resources are further considered in the demand allocation process is shown.

[0069] To process the B process with the demand "monitor, 1000, AB, January 7", multiple machines (M B 2. ..., M B N ) (where N is a natural number greater than 2) allocates display-demand to one of the machines in M B N In the case of a machine, preventive maintenance (PM) can be scheduled from January 3 to January 4. In this case, the simulation device 100 (see Figure 3 )'s demand allocation unit 140 can execute the demand allocation unit in the process of selecting the machine in the bucket step B for the B process for the demand "display, 1000, AB, January 7", and exclude M B N machine.

[0070] As such, the simulation-based factory resource planning method of an embodiment of the present invention can reflect or consider the time unit constraints of resources at the machine level, thereby fundamentally preventing the expected date of product manufacturing completion from being postponed due to time unit constraints such as preventive maintenance, and the problem of being unable to meet customer delivery time, which makes it difficult to achieve the unique effect of the present invention by only considering the capacity of the entire process to reversely allocate resources. Figure 2c As shown in ②, it can be confirmed that M is selected to process the B process of the demand "display, 1000 pieces, AB, January 7" B 2 machines, in place of the M that was scheduled for preventive maintenance during the corresponding period (January 3rd to January 4th). B N machine.

[0071] Figure 2a to Figure 2c The steps shown in describe the simulation steps performed with a single bucket rolling cycle (BRP). The simulation-based factory resource planning method of one embodiment of the present invention can establish factory resource planning by repeating this simulation with a bucket rolling cycle (BRP), such as a 1-day cycle, within a predetermined time period (e.g., 30 days, 60 days, etc.).

[0072] For reference, in this specification, the effective sequencing of resources (e.g., equipment, etc.) to meet all requirements is referred to as the term planning, and terms such as scheduling, sequencing, etc. can be used interchangeably depending on the instance or embodiment.

[0073] Figure 3 is a block diagram of a simulation device 100 based on simulation according to an embodiment of the present invention, Figure 4 It is a sequence diagram for describing a method for resource planning in a factory based on simulation according to an embodiment of the present invention.

[0074] First, as described above, the simulation device 100 of an embodiment of the present invention is configured to execute a series (multiple) processes of resource planning in a factory based on simulation, which can be simply referred to as a capacity storage bucket simulation module. Figure 3 As shown, the simulation device 100 according to an embodiment of the present invention may include a control unit 110 , a communication unit 120 , a modeling unit 130 , a demand allocation unit 140 , a storage unit 150 , and the like.

[0075] The control unit 110 is configured to generally control the operation, function, work, etc. of the simulation device 100 of the present invention, and can be implemented as a controller, a micro-controller, a processor, a micro-processor, etc.

[0076] The modeling unit 130 may be configured to model factory resources as capacity buckets, the demand allocation unit 140 may be configured to allocate multiple demands to the modeled capacity buckets, and the control unit 110 may be configured to establish factory resource planning by repeating demand allocation in a bucket rolling period (BRP) within a predetermined time period.

[0077] The communication unit 120 is provided for direct connection with the outside or connection through a network, and may be a wired and / or wireless communication unit 120. More specifically, the communication unit 120 may transmit data from the control unit 110, the storage unit 150, etc. through wired or wireless transmission, or receive data from the outside through wired or wireless transmission to the control unit 110 or store it in the storage unit 150. The data may include content such as text, images, videos, user images, etc.

[0078] The communication unit 120 can communicate through a local area network (LAN), wideband code division multiple access (WCDMA), long term evolution (LTE), wireless broadband Internet (WiBro), radio frequency (RF), wireless local area network (Wireless LAN), wireless fidelity (Wireless Fidelity), near field communication (NFC), Bluetooth, infrared communication, etc. However, this is only exemplary, and according to the embodiment to which the present invention is applicable, various wired and wireless communication technologies applicable in the technical field to which the present invention belongs can be used.

[0079] The storage unit 150 may store various data related to the operation, function, work, etc. of the simulation device 100. For example, the data stored in the storage unit 150 may include information related to factory resources, information related to capacity buckets, information related to bucket rolling cycles (BRPs), information related to multiple demands, information related to demand priorities, information related to machine priorities, information related to (multiple) time constraints of resources, information related to demand-batches, information related to simulations, etc.

[0080] For reference, as known to those skilled in the art, the storage unit 150 may be implemented as a hard disk drive (HDD), a read only memory (ROM), a random access memory (RAM), an electrically erasable and programmable read only memory (EEPROM), a flash memory, a compact flash (CF) card, a secure digital (SD) card, a smart media (SM) card, a multimedia (MMC) card, or a memory stick, etc., which may input and output information in various forms of storage devices, such as Figure 3 As shown, it may be disposed inside the simulation device 100, or may be disposed in a separate device.

[0081] And, if Figure 3The simulation device 100 or the capacity bucket simulation module shown can be provided to the capacity bucket planning in the form of a site package to be used as a master planning (MP) system or a factory planning (FP) system.

[0082] Will use Figure 3 The block diagram of the simulation device 100 is shown to describe the Figure 4 The simulation-based in-factory resource planning method (step S400) is shown.

[0083] First, the modeling unit 130 may model the factory resources as capacity storage buckets (step S410). The factory resources may include multiple storage buckets respectively formed by multiple machines, and the step of modeling the factory resources as capacity storage buckets (step S410) may include the step of modeling the multiple machines as capacity storage buckets respectively (step S411).

[0084] If the capacity storage bucket modeling of the factory resources is completed (step S410), the demand allocation unit 140 may allocate multiple demands to the modeled capacity storage bucket (step S420). The multiple demands may be prioritized according to a prescribed priority rule, and the step of allocating multiple demands to the modeled capacity storage bucket (step S420) may include the step of allocating multiple demands to the modeled capacity storage bucket based on the prioritized multiple demands (step S421).

[0085] Furthermore, according to another embodiment of the present invention, in the process of allocating multiple requirements to the modeled capacity storage buckets, multiple machines included in each storage bucket step are further prioritized, wherein the priority rules may be based on, for example, factory environment, constraints, quality, settings, etc. Therefore, the step of allocating multiple requirements to the modeled capacity storage buckets (step S420) may also include the step of further allocating multiple requirements to the modeled capacity storage buckets based on the prioritized multiple machines (step S422).

[0086] And, if Figure 1c As shown in part (a) of FIG. 1 , among the multiple requirements of an embodiment of the present invention, a single requirement may be considered as a single batch, or as Figure 1c As shown in part (b), a single demand may be considered as multiple batches. In the latter case, the demand allocation step (step S420) of an embodiment of the present invention may also include dividing the multiple demands into more than one batches, and allocating the more than one divided batches to the modeled capacity storage buckets (step S423).

[0087] Such resource modeling step (step S410) and demand allocation step (step S420) constitute the capacity bucket simulation (CBS) of the present invention, and the control unit 110 can establish a factory resource plan by repeatedly performing demand allocation with a bucket rolling period (BRP) within a predetermined time period. To this end, the control unit 110 can determine whether all allocations are completed within a predetermined time period (e.g., 30 days, 60 days, etc.) (step S430), and if the judgment result is completed, the established factory resource plan is determined, and if the judgment result is not completed, the control unit 110 repeats the step of allocating to the bucket at the next time (step S440).

[0088] The control unit 110 may be controlled to perform the capacity bucket simulation (CBS) with a bucket rolling period (BRP), wherein, as described above, the bucket rolling period (BRP) may be, for example, 1 day. For reference, preferably, the bucket rolling period (BRP) for the capacity bucket simulation is set to a time unit corresponding to the capacity bucket, but the bucket rolling period is not necessarily consistent with the time unit of the capacity bucket.

[0089] For reference, the capacity bucket simulation controlled by the control unit 110 can be based on discrete event simulation (DES). If all discrete events occurring in many devices in the factory are simulated, not only a lot of time is consumed in the simulation, but also the result is quite inefficient. Therefore, the control unit 110 of an embodiment of the present invention can be configured to perform simulation with a specified bucket rolling period (BRP) by controlling the modeling unit 130 and / or the demand allocation unit 140. As described above, the bucket rolling period (BRP) can be set to, for example, 1 day, whereby events within the bucket interval can be omitted.

[0090] For reference, the capacity bucket simulation (CBS) is a virtual simulation that can be simulated by compressing the time unit, for example, compressing the actual 1 day into 1 to 2 seconds, so that simulation results for working periods such as 30 days and 60 days can be quickly obtained.

[0091] In the process of executing the simulation within each time bucket interval, the control unit 110 can determine whether the conditions of multiple demands are met. If the judgment result is that the conditions of all demands are met, the next time bucket interval is performed. If the judgment result is that there are demands that cannot meet the conditions, the priority of the corresponding demand is adjusted, and the demand allocation unit 140 is controlled to repeat the step of allocating multiple demands according to the new priority rule reflecting the adjusted order (step S420).

[0092] As described above, according to a simulation-based in-factory resource planning method and device thereof according to an embodiment of the present invention, limited resources in the factory can be used to implement effective resource planning for meeting multiple demands.

[0093] Furthermore, the simulation-based in-factory resource planning method and device thereof according to an embodiment of the present invention can take into account the time unit constraints of resources, thereby achieving more efficient and accurate resource planning.

[0094] Furthermore, according to a simulation-based in-factory resource planning method and apparatus thereof according to an embodiment of the present invention, resource planning is established at the machine level set within the bucket stepping executing the same process, thereby achieving more efficient and accurate resource planning.

[0095] Furthermore, according to a simulation-based factory resource planning method and device according to an embodiment of the present invention, resource planning is established based on the priorities of multiple demands and / or the priorities of multiple machines within a bucket step, so that all possible demands can be met more effectively.

[0096] Furthermore, according to a simulation-based factory resource planning method and device according to an embodiment of the present invention, the priorities of multiple demands and / or the priorities of multiple machines within a bucket step can be variably adjusted according to the process or time, thereby avoiding unmet demands, thereby maximizing factory operating efficiency and customer satisfaction.

[0097] On the other hand, the various embodiments described in this specification may be implemented by hardware, middleware, microcode, software and / or a combination thereof. For example, the various embodiments may be implemented in one or more application specific integrated circuits (ASICs), digital signal processors (DSPs), digital signal processing devices (DSPDs), programmable logic devices (PLDs), field programmable gate arrays (FPGAs), processors, controllers, microcontrollers, microprocessors, other electronic units designed to perform the functions proposed herein, or a combination thereof.

[0098] Also, for example, various embodiments may be included in or encoded on a computer-readable medium containing instructions. The instructions included or encoded on the computer-readable medium may be methods that a programmable processor or other processor performs, such as when executing the instructions. Computer-readable media include computer storage media, which may be any available media that a computer can access. For example, such computer-readable media may include random access memory (RAM), read-only memory (ROM), erasable read-only memory (EEPROM), a compact disc-ROM or other optical disc storage medium, a magnetic disk storage medium, or other magnetic storage device.

[0099] These hardware, software, firmware, etc. can be implemented in the same device or in separate devices to support the various operations and functions described in this specification. In addition, the structural elements, units, modules, components, etc. recorded as "~ parts" in the present invention can be implemented together or as separate but interoperable logical devices. The description of different features of modules, units, etc. is intended to emphasize different functional embodiments and does not necessarily mean that they must be implemented by separate hardware or software components. On the contrary, functions related to more than one module or unit can be performed by separate hardware or software components, or can be incorporated into common or separate hardware or software components.

[0100] Although multiple operations are shown in a specific order in the accompanying drawings, it should not be understood that these operations are performed in the specific order shown or in sequence to achieve the desired result, or that all the operations shown need to be performed. In any environment, multitasking and parallel processing may be more advantageous. In particular, the division of various structural elements in the embodiments should not be understood as requiring such division in all embodiments, and it should be understood that the described structural elements can generally be integrated into a software product, or packaged into multiple software products.

[0101] As described above, the best embodiment is disclosed in the drawings and the specification. Although specific terms are used in the specification, they are only used to illustrate the present invention, and are not used to define the meaning or limit the scope of the present invention as described in the scope of the invention claims. Therefore, a person skilled in the art of the present invention can understand that various variations and equivalent other embodiments can be implemented. Therefore, the true technical protection scope of the present invention should be determined by the technical ideas of the attached invention claims.

Claims

1. A method for resource planning in a factory based on simulation, characterized in that: include: For a factory resource including a plurality of bucket steps consisting of a plurality of machines performing a same process, each machine is modeled as a capacity bucket of a time unit; The step of prioritizing multiple machines included in each bucket step considering the priority rules including factory environment, constraints, quality, and settings; The step of allocating a plurality of demands to the modeled capacity buckets based further on the prioritized plurality of machines, taking into account the time unit constraints of the factory resources at the individual machine levels; as well as The step of establishing a factory resource plan by repeating the step of allocating the plurality of requirements in a bucket rolling cycle within a predetermined time period, The capacity bucket simulation consisting of the steps of performing the modeling and the steps of performing the allocation is based on a discrete event simulation omitting events within the bucket rolling period, wherein the priorities of the plurality of machines within the bucket step are set in a direction that minimizes the setting, The step of allocating a plurality of demands to the modeled capacity storage buckets includes: for a demand that cannot be delivered before the delivery time, lowering the priority of the demand or setting a pause period to adjust the delivery time of the demand.

2. The method for in-factory resource planning based on simulation according to claim 1, characterized in that: The step of allocating a plurality of requirements to the modeled capacity storage buckets comprises: The step of dividing the plurality of requirements into one or more batches respectively; and The step of allocating the divided one or more batches to the modeled capacity storage buckets.

3. The method for in-factory resource planning based on simulation according to claim 1, characterized in that: The bucket rolling period corresponds to a time unit of the capacity bucket.

4. The method for in-factory resource planning based on simulation according to claim 1, characterized in that: Also includes: The step of allocating the plurality of requirements based on a new priority rule reflecting the adjusted priority.

5. A simulation device for establishing a simulation-based resource planning in a factory, characterized in that: include: A modeling unit for modeling each machine as a capacity bucket of a time unit for a factory resource including a plurality of bucket steps consisting of a plurality of machines performing the same process; a demand allocating unit for allocating a plurality of demands to the modeled capacity storage buckets, taking into account the time unit constraints of the factory resources at each machine level and further based on the prioritized plurality of machines; as well as a control unit for repeatedly allocating the plurality of demands in a bucket rolling cycle within a predetermined time period to establish a factory resource plan, A capacity bucket simulation consisting of resource modeling by the modeling unit and demand allocation by the demand allocation unit is based on a discrete event simulation omitting events within a rolling period of the bucket, Among them, the priority rules including factory environment, constraints, quality, and settings are considered to prioritize multiple machines included in each bucket step. and setting priorities of a plurality of machines within the bucket step in a direction that minimizes the setting, The demand allocating unit lowers the priority of a demand that cannot be delivered before the delivery time, or sets a pause period to adjust the delivery time of the demand.

6. A computer-readable recording medium, characterized in that: A program for executing the method according to any one of claims 1 to 4 by a computer is recorded.