A wind power transient process division method and device

By performing first- and second-order difference processing on wind farm sampling data, the transient process of the response curve is automatically divided, which solves the problem of inaccurate division of the transient interval of the response curve in high-proportion wind power systems, and realizes the improvement of the safety and stability of wind power systems and online evaluation.

CN112952810BActive Publication Date: 2026-11-20CHINA ELECTRIC POWER RESEARCH INSTITUTE CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202110209420.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-02-24
Publication Date
2026-11-20
Estimated Expiration
2041-02-24

AI Technical Summary

Technical Problem

Existing technologies struggle to automatically segment transient processes in response curves within high-proportion wind power systems, failing to meet the requirements for online monitoring and grid-connected performance evaluation, resulting in insufficient safety and stability of wind power systems.

Method used

By performing first-order and second-order difference processing on the sampled data of the wind farm, transient sub-intervals are determined, and transient intervals are divided based on the second-order difference array. A wind power transient process division method and device are adopted to realize the automatic division of the transient process of the response curve.

Benefits of technology

This method has low computational complexity and high speed, and is suitable for both online and offline calculations. It improves the safety and stability of wind power systems and meets the needs of online monitoring and grid connection performance evaluation for high-proportion wind power systems.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112952810B_ABST
    Figure CN112952810B_ABST
Patent Text Reader

Abstract

The application relates to a wind power transient process division method and device, which comprises the following steps: determining a transient subinterval of a wind farm according to a first-order difference array corresponding to a sampling data array of the wind farm; and dividing a transient interval of the wind farm based on a second-order difference array corresponding to the sampling data array of the wind farm and the transient subinterval of the wind farm. In order to meet the urgent needs of online monitoring of a high-proportion wind power system and online evaluation of grid-connected performance, the transient process of a response curve is automatically divided in the case that no one participates in online detection data, and the safety and stability of the wind power system are effectively improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the fields of adaptive partitioning of transient intervals in the dynamic response curves of wind farms and online calculation of grid-connected performance, specifically to a method and apparatus for partitioning wind power transient processes. Background Technology

[0002] In recent years, with the continuous development of wind power technology and the rapid increase in installed wind power capacity, a grid configuration with a high proportion of wind power systems has been formed in wind-rich regions of my country. Compared with traditional thermal power, wind power has weaker support and insufficient grid connection characteristics. As the proportion of wind power continues to increase, the safety and stability of high-proportion wind power systems are gradually weakening. In order to improve the safety and stability of wind power systems and accurately calculate their grid connection performance, it is necessary to accurately define the transient range of the response curve.

[0003] Currently, the methods for distinguishing the transient processes of data (current, voltage, active power, reactive power, etc.) response curves are mainly determined by humans through visual observation combined with relevant test and evaluation standards. This is difficult to meet the urgent needs of online monitoring and online evaluation of grid-connected performance for high-proportion wind power systems. Therefore, in engineering, there is an urgent need to find a method that can automatically divide the transient processes of response curves through online detection data without human intervention.

[0004] To date, research on automatic division of transient intervals for response curves is limited, and no relevant literature or patents disclose such methods. To address this practical problem in engineering applications, this invention aims to propose an automatic division method for transient intervals of response curves that is easy to implement in software. This method has low computational complexity and high calculation speed, and can be directly used for online calculation of wind farm grid-connected performance indicators, and is also applicable to offline calculation of wind farm grid-connected performance indicators. Summary of the Invention

[0005] To address the shortcomings of existing technologies, the purpose of this invention is to provide a method for classifying transient processes in wind power. This method automatically classifies the transient processes of response curves using online detection data without human intervention, effectively improving the safety and stability of wind power systems.

[0006] The objective of this invention is achieved through the following technical solution:

[0007] This invention provides a method for classifying wind power transient processes, the improvement of which is that the method includes:

[0008] The transient sub-intervals of the wind farm are determined based on the first-order difference array corresponding to the sampled data array of the wind farm.

[0009] The transient intervals of the wind farm are divided based on the second-order difference array corresponding to the sampled data array of the wind farm and the transient sub-intervals of the wind farm.

[0010] Preferably, the sampled data is current, voltage, active power, or reactive power.

[0011] Preferably, the calculation formula for the elements in the first-order difference array corresponding to the sampled data array of the wind farm is as follows:

[0012] a dif1 (n)=(a(n+1)-a(n))*k,n=(1…N-1)

[0013] The calculation formula for the elements in the second-order difference array corresponding to the sampled data array of the wind farm is as follows:

[0014] a dif2 (n)=(a dif1 (n+1)-a dif1 (n)), n=(1…N-2)

[0015] Where k is the sampling rate of the wind farm sampling data, a(n) is the nth element in the wind farm sampling data array, a(n+1) is the (n+1)th element in the wind farm sampling data array, and a dif1 (n) represents the nth element in the first-order difference array corresponding to the sampled data array of the wind farm, a dif1 (n+1) is the (n+1)th element in the first-order difference array corresponding to the wind farm's sampled data array, a dif2 (n) is the nth element in the second-order difference array corresponding to the sampled data array of the wind farm, and N is the total number of sampled data of the wind farm.

[0016] Preferably, determining the transient sub-interval of the wind farm based on the first-order difference array corresponding to the sampled data array of the wind farm includes:

[0017] Continuous first-order difference data points with a value not less than a first preset threshold are sequentially selected from the first-order difference array corresponding to the wind farm's sampling data array as transient sub-intervals of the wind farm, and the transient sub-intervals are numbered according to the selection order of the transient sub-intervals.

[0018] Preferably, the step of dividing the transient interval of the wind farm based on the second-order difference array corresponding to the sampled data array of the wind farm and the transient sub-interval of the wind farm includes:

[0019] The transient subintervals are merged based on the element values ​​of adjacent numbered transient subintervals to obtain the merged transient subintervals, and then the merged transient subintervals are numbered sequentially.

[0020] The transient intervals of the wind farm are obtained by merging the second-order difference array corresponding to the sampling data array of the wind farm and the numbers of the elements in the adjacent merged transient sub-intervals.

[0021] Furthermore, the step of merging the transient sub-intervals based on the element values ​​of adjacent numbered transient sub-intervals to obtain the merged transient sub-intervals includes:

[0022] If the difference between the element value corresponding to the smallest label in the (j+1)th transient subinterval and the element value corresponding to the largest label in the jth transient subinterval is not greater than a preset time threshold, then the jth transient subinterval and the (j+1)th transient subinterval are merged, where j∈(1,2,...,Q-1), and Q is the total number of transient subintervals of the wind farm.

[0023] Furthermore, the step of merging the merged transient sub-intervals based on the second-order difference array corresponding to the sampled data array of the wind farm and the element numbers of adjacent merged transient sub-intervals to obtain the transient interval of the wind farm includes:

[0024] If the average of the absolute values ​​of the absolute values ​​of the elements corresponding to the largest label in the i-th merged transient sub-interval and the smallest label in the (i+1)-th merged transient sub-interval is not less than the second preset threshold, then the i-th merged transient sub-interval and the (i+1)-th merged transient sub-interval are merged, where i∈(1,2,...,K-1), and K is the total number of merged transient sub-intervals of the wind farm.

[0025] Based on the same inventive concept, the present invention also provides a wind power transient process segmentation device, wherein the improvement is that the device includes:

[0026] The determination module is used to determine the transient sub-intervals of the wind farm based on the first-order difference array corresponding to the sampled data array of the wind farm;

[0027] The partitioning module is used to partition the transient intervals of the wind farm based on the second-order difference array corresponding to the sampled data array of the wind farm and the transient sub-intervals of the wind farm.

[0028] Preferably, the determining module is specifically used for:

[0029] Continuous first-order difference data points with a value not less than a first preset threshold are sequentially selected from the first-order difference array corresponding to the wind farm's sampling data array as transient sub-intervals of the wind farm, and the transient sub-intervals are numbered according to the selection order of the transient sub-intervals.

[0030] Preferably, the partitioning module is specifically used for:

[0031] The transient subintervals are merged based on the element values ​​of adjacent numbered transient subintervals to obtain the merged transient subintervals, and then the merged transient subintervals are numbered sequentially.

[0032] The transient intervals of the wind farm are obtained by merging the second-order difference array corresponding to the sampling data array of the wind farm and the numbers of the elements in the adjacent merged transient sub-intervals.

[0033] Compared with the closest existing technology, the present invention has the following advantages:

[0034] The technical solution provided by this invention determines the transient sub-intervals of a wind farm based on the first-order difference array corresponding to the wind farm's sampled data array, and divides the transient intervals of the wind farm based on the second-order difference array corresponding to the wind farm's sampled data array and the transient sub-intervals of the wind farm. This solution addresses practical problems faced in engineering applications, has low computational load, fast computation speed, and is easy to implement in software. It is applicable to both online and offline calculations and has universality, suitable for any situation requiring analysis of the transient characteristics of the response curve. It directly solves the engineering problem of inaccurate division of the transient intervals of the response curve. By automatically dividing the transient process of the response curve through online detection data without human intervention, it meets the urgent need for online monitoring and online evaluation of grid-connected performance of high-proportion wind power systems, while effectively improving the safety and stability of the wind power system. Attached Figure Description

[0035] Figure 1 This is a flowchart of a method for classifying wind power transient processes;

[0036] Figure 2 This is a flowchart of the transient interval calculation method for a wind power transient process partitioning method;

[0037] Figure 3 This is a schematic diagram of the active power setpoint of a wind farm, which is a method for classifying wind power transient processes.

[0038] Figure 4 This is a schematic diagram of the actual active power value of a wind farm, based on a method for classifying wind power transient processes.

[0039] Figure 5 It is a measurement of the generator terminal voltage, which is part of a method for classifying wind power transient processes.

[0040] Figure 6 It is a first-order difference value of a method for classifying wind power transient processes;

[0041] Figure 7It is a second-order difference value for a method of classifying wind power transient processes;

[0042] Figure 8 This is a partially enlarged view of the terminal voltage drop process in a wind power transient process division method;

[0043] Figure 9 This is a locally enlarged view of the first-order difference result of a wind power transient process partitioning method;

[0044] Figure 10 This is a magnified view of the second-order difference result of a wind power transient process partitioning method;

[0045] Figure 11 This is a partially enlarged view of the terminal voltage recovery process in a wind power transient process division method;

[0046] Figure 12 This is a locally enlarged view of the first-order difference result of a wind power transient process partitioning method;

[0047] Figure 13 This is a magnified view of the second-order difference result of a wind power transient process partitioning method;

[0048] Figure 14 This is a magnified view of the terminal voltage drop period during a wind power transient process division method.

[0049] Figure 15 This is a locally enlarged view of the first-order difference result of a wind power transient process partitioning method;

[0050] Figure 16 This is a magnified view of the second-order difference result of a wind power transient process partitioning method;

[0051] Figure 17 This is a structural diagram of a wind power transient process division device. Detailed Implementation

[0052] The specific embodiments of the present invention will be further described in detail below with reference to the accompanying drawings.

[0053] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0054] To date, there is limited research on automatic division methods for transient intervals of response curves, and no relevant literature or patents disclose such methods. To meet the urgent need for online monitoring and online evaluation of grid-connected performance in high-proportion wind power systems, this invention proposes a wind power transient process division method, which will be described in detail below. Figure 1 As shown, it includes the following steps:

[0055] Step 101: Determine the transient sub-intervals of the wind farm based on the first-order difference array corresponding to the sampled data array of the wind farm;

[0056] Step 102: Divide the transient interval of the wind farm based on the second-order difference array corresponding to the sampled data array of the wind farm and the transient sub-interval of the wind farm.

[0057] Preferably, the sampled data is current, voltage, active power, or reactive power.

[0058] A flowchart illustrating the transient interval calculation process of a wind power transient process partitioning method, as shown below. Figure 2 The diagram shown illustrates the determination of active power control performance indicators for wind farms. Figure 3 and Figure 4 As shown (other methods for determining control performance indicators are similar), control performance indicators typically include steady-state deviation, response time, and response rate. In the figure, X represents active power, reactive power, and voltage; X1 is the initial value; X2 is the target value; and t... p,0 To begin adjusting the time, t p,1 To ensure continuous operation within the allowed starting time, t p,2 The time t is the time for active power to reach a steady state. p,3 To adjust the termination time, the following uses response rate as an example to illustrate the calculation method of performance indicators. The response rate λ can be calculated using the following formula:

[0059]

[0060] Where X t Indicates at t p,1 The active power measurement value obtained at any given time.

[0061] If performance metrics need to be calculated, t must first be automatically determined based on the collected data. p,0 t p,1 t p,2 and t p,3 First, determine the time frame, then find the corresponding data values ​​at each time point, and finally calculate the relevant performance metrics. p,0 -t p,2 This period is the transient interval of the curve, t p,2 -t p,3This refers to the steady-state interval of the curve. This invention proposes an automatic method for dividing and calculating the transient interval of a response curve based on field-measured data. Using this algorithm, the t-interval of the response curve composed of field-collected data points can be automatically calculated. p,0 t p,1 t p,2 and t p,3 The system calculates the response indicators automatically by matching the data values ​​at each time point with the corresponding data values.

[0062] During the on-site data collection process Figure 3 and Figure 4 The curve shown can be represented by an array 'a' with a fixed sampling rate.

[0063] Where a = [a1, a2, ..., a n ]. From t p,0 At time t, the curve enters a transient adjustment process. According to the principles of calculus, t... p,0 The absolute value of the derivative at time + will suddenly increase, and when the curve reaches a local extremum (maximum or minimum), the derivative of the curve is 0. For discrete data points, the differentiation process is the difference process. Since high-frequency measurement noise is unavoidable in the measured data, the difference operation will amplify the measurement noise. To avoid the influence of measurement noise, the measurement data needs to be filtered first to remove high-frequency measurement noise. To achieve step 101, the present invention provides a preferred embodiment. Taking the field low-voltage ride-through positive sequence voltage measurement data of a certain type of unit as an example, the transient interval division and calculation method of the present invention is applied. The terminal voltage test data of a certain unit during low-voltage ride-through and the results of the first-order difference and second-order difference calculated in the invention are as follows: Figure 5 , Figure 6 and Figure 7 As shown, the measurement data sampling frequency is 1.5kHz.

[0064] The specific methods for dividing and calculating transient intervals are as follows:

[0065] Terminal voltage measurement data a f Low-pass filtering is performed to obtain the filtered array 'a'. The transfer function of the filter used is:

[0066]

[0067] Where T takes the value 0.01.

[0068] Perform a difference operation on array a to obtain the difference array a. dif1 A schematic diagram of the result of the difference operation, as shown below. Figure 5 , Figure 6 and Figure 7 As shown.

[0069] Preferably, the calculation formula for the elements in the first-order difference array corresponding to the sampled data array of the wind farm is as follows:

[0070] a dif1 (n)=(a(n+1)-a(n))*k,n=(1…N-1)

[0071] The calculation formula for the elements in the second-order difference array corresponding to the sampled data array of the wind farm is as follows:

[0072] a dif2 (n)=(a dif1 (n+1)-a dif1 (n)), n=(1…N-2)

[0073] Where k is the sampling rate of the wind farm sampling data, a(n) is the nth element in the wind farm sampling data array, a(n+1) is the (n+1)th element in the wind farm sampling data array, and a dif1 (n) represents the nth element in the first-order difference array corresponding to the sampled data array of the wind farm, a dif1 (n+1) is the (n+1)th element in the first-order difference array corresponding to the wind farm's sampled data array, a dif2 (n) is the nth element in the second-order difference array corresponding to the sampled data array of the wind farm, and N is the total number of sampled data of the wind farm.

[0074] Select a threshold ε1 = 150, and determine the element a in the array. dif1 The absolute value of (n) |a dif1 (n) | Intervals k1, k2, ..., k greater than the threshold ε1 n .by Figure 8 , Figure 9 and Figure 10 Taking the transient process of the terminal voltage drop around 9.37s as an example, k1 = [t1, t2], k1 = [t3, t4]. The array a records the intervals k1 and k2. dif1 index k 1i ,k 1j k 2i ,k 2j , where k 1i ,k 1j Let k be the index of the interval k1. 2i ,k 2j Let be the index of the interval k2. Figure 11 , Figure 12 and Figure 13 Taking the transient process of terminal voltage recovery in about 10 seconds as an example, the initially determined transient intervals are k3, k4, ..., k 12 .

[0075] Select threshold ε t =0.1, then k 2i -k 1j ≤ε t If *k holds true, the transient intervals k1 and k2 need to be merged. The merged transient interval is denoted as I1 = [t1, t4], and the array a corresponding to interval I1 is... dif1 The left and right subscript indices are k 1i ,k 2j .

[0076] Preferably, determining the transient sub-interval of the wind farm based on the first-order difference array corresponding to the sampled data array of the wind farm includes:

[0077] Continuous first-order difference data points with a value not less than a first preset threshold are sequentially selected from the first-order difference array corresponding to the wind farm's sampling data array as transient sub-intervals of the wind farm, and the transient sub-intervals are numbered according to the selection order of the transient sub-intervals.

[0078] To achieve step 102, the present invention provides a preferred embodiment for determining the index k of the interval k2, k3. 3i -k 2j ≤ε t *k is invalid; k needs to be redefined. 2j ,k 3i between a dif1 (n) is filtered and then differentially analyzed to obtain a. dif2 The difference results are as follows Figure 14 , Figure 15 and Figure 16 The bottom curve shows the filter used. The filter is also the low-pass filter described in the previous steps, with a T value of 0.025.

[0079] Choosing ε2 = 10, calculations show that a dif2 At index k 2j ,k 3i If the average absolute value between intervals is less than ε2, no interval merging is required.

[0080] The determination requires k3, k4, ..., k 12 Merge the intervals and denote the merged interval as I2 = [t5, t6], and record the index of the interval I2.

[0081] Therefore, it can be determined that the terminal voltage test curve has two transient intervals, I1 and I2, and the subscript indices of the original measurement data corresponding to each interval can be obtained. These subscript indices can then be used to calculate subsequent performance indicators such as steady-state deviation, response time, and recovery rate.

[0082] Preferably, the step of dividing the transient interval of the wind farm based on the second-order difference array corresponding to the sampled data array of the wind farm and the transient sub-interval of the wind farm includes:

[0083] The transient subintervals are merged based on the element values ​​of adjacent numbered transient subintervals to obtain the merged transient subintervals, and then the merged transient subintervals are numbered sequentially.

[0084] The transient intervals of the wind farm are obtained by merging the second-order difference array corresponding to the sampling data array of the wind farm and the numbers of the elements in the adjacent merged transient sub-intervals.

[0085] Furthermore, the step of merging the transient sub-intervals based on the element values ​​of adjacent numbered transient sub-intervals to obtain the merged transient sub-intervals includes:

[0086] If the difference between the element value corresponding to the smallest label in the (j+1)th transient subinterval and the element value corresponding to the largest label in the jth transient subinterval is not greater than a preset time threshold, then the jth transient subinterval and the (j+1)th transient subinterval are merged, where j∈(1,2,...,Q-1), and Q is the total number of transient subintervals of the wind farm.

[0087] Furthermore, the step of merging the merged transient sub-intervals based on the second-order difference array corresponding to the sampled data array of the wind farm and the element numbers of adjacent merged transient sub-intervals to obtain the transient interval of the wind farm includes:

[0088] If the average of the absolute values ​​of the absolute values ​​of the elements corresponding to the largest label in the i-th merged transient sub-interval and the smallest label in the (i+1)-th merged transient sub-interval is not less than the second preset threshold, then the i-th merged transient sub-interval and the (i+1)-th merged transient sub-interval are merged, where i∈(1,2,...,K-1), and K is the total number of merged transient sub-intervals of the wind farm.

[0089] Based on the same inventive concept, the present invention also provides a wind power transient process segmentation device, such as... Figure 17 As shown, the improvement lies in that the device includes:

[0090] The determination module is used to determine the transient sub-intervals of the wind farm based on the first-order difference array corresponding to the sampled data array of the wind farm;

[0091] The partitioning module is used to partition the transient intervals of the wind farm based on the second-order difference array corresponding to the sampled data array of the wind farm and the transient sub-intervals of the wind farm.

[0092] Preferably, the determining module is specifically used for:

[0093] The calculation formula for the elements in the first-order difference array corresponding to the sampled data array of the wind farm is as follows:

[0094] a dif1 (n)=(a(n+1)-a(n))*k,n=(1…N-1)

[0095] The calculation formula for the elements in the second-order difference array corresponding to the sampled data array of the wind farm is as follows:

[0096] a dif2 (n)=(a dif1 (n+1)-a dif1 (n)), n=(1…N-2)

[0097] Where k is the sampling rate of the wind farm sampling data, a(n) is the nth element in the wind farm sampling data array, a(n+1) is the (n+1)th element in the wind farm sampling data array, and a dif1 (n) represents the nth element in the first-order difference array corresponding to the sampled data array of the wind farm, a dif1 (n+1) is the (n+1)th element in the first-order difference array corresponding to the wind farm's sampled data array, a dif2 (n) is the nth element in the second-order difference array corresponding to the sampled data array of the wind farm, and N is the total number of sampled data of the wind farm;

[0098] Continuous first-order difference data points with a value not less than a first preset threshold are sequentially selected from the first-order difference array corresponding to the wind farm's sampling data array as transient sub-intervals of the wind farm, and the transient sub-intervals are numbered according to the selection order of the transient sub-intervals.

[0099] Preferably, the partitioning module is specifically used for:

[0100] The transient subintervals are merged based on the element values ​​of adjacent numbered transient subintervals to obtain the merged transient subintervals, and then the merged transient subintervals are numbered sequentially.

[0101] The transient intervals of the wind farm are obtained by merging the second-order difference array corresponding to the sampling data array of the wind farm and the numbering of the elements in the adjacent merged transient sub-intervals.

[0102] If the difference between the element value corresponding to the smallest label in the (j+1)th transient subinterval and the element value corresponding to the largest label in the jth transient subinterval is not greater than a preset time threshold, then the jth transient subinterval and the (j+1)th transient subinterval are merged, where j∈(1,2,...,Q-1), and Q is the total number of transient subintervals of the wind farm;

[0103] If the average of the absolute values ​​of the absolute values ​​of the elements corresponding to the largest label in the i-th merged transient sub-interval and the smallest label in the (i+1)-th merged transient sub-interval is not less than the second preset threshold, then the i-th merged transient sub-interval and the (i+1)-th merged transient sub-interval are merged, where i∈(1,2,...,K-1), and K is the total number of merged transient sub-intervals of the wind farm.

[0104] Those skilled in the art will understand that embodiments of the present invention can be provided as methods, systems, or computer program products. Therefore, the present invention can take the form of a completely hardware embodiment, a completely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, the present invention can take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0105] This invention is described with reference to flowchart illustrations and / or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the invention. It will be understood that each block of the flowchart illustrations and / or block diagrams, and combinations of blocks in the flowchart illustrations and / or block diagrams, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, special-purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, generate instructions for implementing the flowchart illustrations and / or block diagrams. Figure 1 One or more processes and / or boxes Figure 1 A device that provides the functions specified in one or more boxes.

[0106] These computer program instructions may also be stored in a computer-readable storage medium that can direct a computer or other programmable data processing device to function in a particular manner, such that the instructions stored in the computer-readable storage medium produce an article of manufacture including instruction means, which are implemented in a process Figure 1 One or more processes and / or boxes Figure 1 The function specified in one or more boxes.

[0107] These computer program instructions may also be loaded onto a computer or other programmable data processing equipment to cause a series of operational steps to be performed on the computer or other programmable equipment to produce a computer-implemented process, thereby providing instructions that execute on the computer or other programmable equipment for implementing the process. Figure 1 One or more processes and / or boxes Figure 1 The steps of the function specified in one or more boxes.

[0108] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and not to limit it. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that modifications or equivalent substitutions can still be made to the specific implementation of the present invention. Any modifications or equivalent substitutions that do not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.

Claims

1. A method for dividing wind power transient processes, characterized in that, The method includes: The transient sub-intervals of the wind farm are determined based on the first-order difference array corresponding to the sampled data array of the wind farm. The transient intervals of the wind farm are divided based on the second-order difference array corresponding to the sampled data array of the wind farm and the transient sub-intervals of the wind farm. The sampled data includes current, voltage, active power, or reactive power. The step of determining the transient sub-interval of the wind farm based on the first-order difference array corresponding to the sampled data array of the wind farm includes: Continuous first-order difference data that are not less than a first preset threshold are selected sequentially from the first-order difference array corresponding to the sampling data array of the wind farm as transient sub-intervals of the wind farm, and the transient sub-intervals are numbered according to the selection order of the transient sub-intervals. The step of dividing the transient interval of the wind farm based on the second-order difference array corresponding to the sampled data array of the wind farm and the transient sub-interval of the wind farm includes: The transient subintervals are merged based on the element values ​​of adjacent numbered transient subintervals to obtain the merged transient subintervals, and then the merged transient subintervals are numbered sequentially. The transient intervals of the wind farm are obtained by merging the second-order difference array corresponding to the sampling data array of the wind farm and the numbering of the elements in the adjacent merged transient sub-intervals. The step of merging the transient sub-intervals based on the element values ​​of adjacent numbered transient sub-intervals to obtain the merged transient sub-intervals includes: If the first The element value corresponding to the smallest index in the nth transient subinterval is related to the nth... If the difference between the element values ​​corresponding to the largest label in each transient sub-interval is not greater than a preset time threshold, then the first... The transient sub-interval and the first There are transient sub-intervals, among which... , This represents the total number of transient subintervals in the wind farm. The step of merging the transient subintervals based on the second-order difference array corresponding to the sampling data array of the wind farm and the numbers of elements in adjacent merged transient subintervals to obtain the transient intervals of the wind farm includes: If the first The maximum index in the merged transient subintervals is related to the first... If the average of the absolute values ​​of the elements corresponding to the smallest indices in the second-order difference array of the sampled data array is not less than a second preset threshold, then the merged... The merged transient subinterval and the first The merged transient sub-intervals, among which... , This represents the total number of transient subintervals after the wind farm is merged.

2. The method as described in claim 1, characterized in that, The calculation formula for the elements in the first-order difference array corresponding to the sampled data array of the wind farm is as follows: The calculation formula for the elements in the second-order difference array corresponding to the sampled data array of the wind farm is as follows: in, The sampling rate of the wind farm sampling data. The first element in the sampled data array of the wind farm One element, The first element in the sampled data array of the wind farm One element, The first-order difference array corresponding to the sampled data array of the wind farm One element, The first-order difference array corresponding to the sampled data array of the wind farm One element, The second-order difference array corresponding to the sampled data array of the wind farm One element, This represents the total number of sampled data points from the wind farm.

3. A wind power transient process partitioning device, used to implement the method as described in any one of claims 1-2, characterized in that, The device includes: The determination module is used to determine the transient sub-intervals of the wind farm based on the first-order difference array corresponding to the sampled data array of the wind farm; The partitioning module is used to partition the transient intervals of the wind farm based on the second-order difference array corresponding to the sampled data array of the wind farm and the transient sub-intervals of the wind farm.

4. The apparatus as described in claim 3, characterized in that, The determining module is specifically used for: Continuous first-order difference data points with a value not less than a first preset threshold are sequentially selected from the first-order difference array corresponding to the wind farm's sampling data array as transient sub-intervals of the wind farm, and the transient sub-intervals are numbered according to the selection order of the transient sub-intervals.

5. The apparatus as described in claim 3, characterized in that, The partitioning module is specifically used for: The transient subintervals are merged based on the element values ​​of adjacent numbered transient subintervals to obtain the merged transient subintervals, and then the merged transient subintervals are numbered sequentially. The transient intervals of the wind farm are obtained by merging the second-order difference array corresponding to the sampling data array of the wind farm and the numbers of the elements in the adjacent merged transient sub-intervals.

Citation Information

Patent Citations

  • Wind field equivalence modeling and optimal control method based on fuzzy c-means clustering algorithm

    CN107909211A

  • Method and apparatus for planning base station cluster

    CN109391946A