一种斜拉桥索塔钢横梁施工方法及其组装方法
By setting up positioning reflective stickers and temporary support plates on the cable-stayed bridge towers, and combining this with the T-shaped weld full penetration backing plate welding technology, the steel crossbeams were installed efficiently and safely, solving the problems of low construction efficiency and high cost.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- MCC5 GROUP SHANGHAI CORPORATION LIMITED
- Filing Date
- 2021-06-02
- Publication Date
- 2026-07-17
AI Technical Summary
The construction efficiency of steel crossbeams between cable-stayed bridge towers is low, there are risks of installation and dismantling, and the construction cost is high. In particular, the inconsistent length of the crossbeams in bidirectional torsional structures makes hoisting difficult.
Positioning reflective stickers are set at the intended installation positions of the tower columns and steel beams, and temporary support plates are set below them. The positioning reflective stickers provide reference coordinates and support to ensure that the steel beams are hoisted into place in one go. T-shaped weld seam full penetration backing plate welding technology is adopted.
This improved construction efficiency, reduced construction costs, ensured the installation accuracy and safety of the steel beams, and avoided the impact of environmental changes on welding quality.
Smart Images

Figure CN113322820B_ABST