A research method for distribution network planning in high altitude areas

By constructing a distribution network system and optimization model in high-altitude areas, combined with improved genetic algorithms, the location and capacity of photovoltaic generators and wind turbines were planned, and the problem of unstable power supply in the distribution network in high-altitude areas was solved, and the problem of instability in the distribution network was realized. More efficient and economical energy utilization.

CN114492983BActive Publication Date: 2024-11-29YANSHAN UNIV
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202210079414.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-01-24
Publication Date
2024-11-29
Estimated Expiration
2042-01-24

AI Technical Summary

Technical Problem

Due to the harsh natural conditions and poor operating reliability of traditional power supply, the distribution network in high-altitude areas is difficult to effectively utilize the rich local wind and solar energy resources, resulting in unstable power supply.

Method used

A research method for planning distribution networks in high altitude areas, including building distribution network systems, establishing a steady-state power output model of each unit, drawing typical sunlight, wind and load curves, and through optimization models and improved adaptive genetics The algorithm reasonably plans the location and capacity of photovoltaic generators and wind turbines, and comprehensively considers the initial investment, operation and maintenance and wind and power disposal costs.

Benefits of technology

It provides a more realistic distribution network planning scheme, which improves the reliability and economicality of power supply in high-altitude areas, meets local energy needs, and reduces the operation and maintenance costs of the power system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114492983B_ABST
    Figure CN114492983B_ABST
Patent Text Reader

Abstract

The invention discloses a research method for planning a distribution network in a high-altitude area. According to the natural resource conditions and load change states in the high-altitude area, a distribution network system is constructed; according to the basic conditions and characteristics of various local units, a steady-state power output model of each unit is established, and typical sunlight, wind power and load curves are drawn; according to the drawn typical sunlight, wind power and load curves, an optimization model with annual equivalent initial investment cost, operation and maintenance cost and penalty cost for abandoning wind and power as targets is established to reasonably plan the location and capacity of distributed power sources in the system; comprehensively considering the mutual influence of three objective functions, a linear weighted summation method is used to convert multi-objective problems into single-objective problems for solving; an adaptive genetic algorithm is improved, which not only maintains the diversity between populations, but also prevents falling into local optimum in the late stage of evolution. The invention solves the planning problem of site selection and capacity determination of distributed power sources in a distribution network in a high-altitude Tibetan area.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a research method for distribution network planning in high altitude areas, belonging to distribution network planning methods. Background Art

[0002] With the continuous development of science and technology and the continuous improvement of economic level, the demand for energy in domestic and foreign societies is increasing. Non-renewable resources such as coal, oil and natural gas have high mining costs and low storage capacity. Large-scale mining will lead to irreversible resource loss or even depletion. In particular, when fossil fuels are used in large quantities, a large amount of polluting gases will be produced, causing pollution to the environment. Renewable energy such as wind power and solar energy have the characteristics of sufficient energy, low pollution and wide distribution. Their large-scale development and utilization will alleviate the dual pressure of energy and environment. Therefore, the use of renewable energy distributed power generation has also become an important part of today's engineering construction and scientific research. Distributed power generation, due to its dispersed location distribution, can reasonably meet the actual power demand based on the actual energy distribution situation, providing a guarantee for the reliable operation of the system.

[0003] High-altitude areas are areas with an altitude of more than 1,000 meters. Due to their natural geographical location, these areas have long been surrounded by mountains and have poor transportation. The reliability of their power supply operation is poor, and the difficulty of power supply operation and maintenance is high. Traditional power supply can hardly withstand the frequent power outages caused by the harsh natural conditions in high-altitude areas. However, high-altitude areas have thin air, high atmospheric transparency, and high solar radiation, so they are extremely rich in solar energy resources. Since high-altitude areas are surrounded by mountains, wind energy gathers in the mountains in high-altitude areas to form natural wind outlets, which also lays the foundation for the future construction of wind power generation. Therefore, on the basis of traditional distribution networks in high-altitude areas, it is of certain practical significance to make full and rational use of the local abundant natural resources and build a high-altitude distribution network with wind, light and storage. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide a more realistic distribution network planning method for high-altitude areas, which solves the planning problem of site selection and capacity determination of distributed power sources in distribution networks in high-altitude Tibetan areas.

[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is:

[0006] A method for planning and studying a distribution network in a high altitude area comprises the following steps:

[0007] S1. According to the natural resource conditions in high altitude areas and the changing state of user loads, a distribution network system is constructed, wherein the distribution network system includes a photovoltaic generator unit, a wind turbine generator unit, a diesel generator unit and an energy storage battery unit;

[0008] S2. According to the basic conditions and characteristics of each unit in the local distribution network system, a steady-state power output model of each unit was established, and typical sunlight, wind power and load curves were drawn;

[0009] S3. Based on the typical sunlight, wind power and load curves drawn, an optimization model with annual equivalent initial investment cost, operation and maintenance cost and penalty cost for wind and power abandonment is established to reasonably plan the location and capacity of photovoltaic generator units and wind turbine generator units;

[0010] S4, comprehensively considering the mutual influence of the three objective functions in step S3, using the linear weighted summation method, converting the multi-objective problem into a single-objective problem for solution;

[0011] S5. Aiming at the solution method of distributed power location capacity planning, an adaptive genetic algorithm is improved. By changing the crossover and mutation operators in the genetic process, the concentration and dispersion of fitness in genetic evolution are fully utilized, which not only maintains the diversity among populations, but also prevents falling into local optimality in the late stage of evolution.

[0012] A further improvement of the technical solution of the present invention is that: the steady-state power output model of each unit includes a wind turbine power output model and a photovoltaic power generation system power output model.

[0013] A further improvement of the technical solution of the present invention is that the wind turbine power output model uses a conventional power output model, which only considers the effect of wind speed on output power. The model is as follows:

[0014]

[0015] In formula (1): P w is the actual output power of the wind turbine; P r is the rated power of the wind turbine; v is the actual wind speed, unit: m / s; v r is the rated wind speed, unit: m / s; v ci is the cut-in wind speed, unit: m / s; v co It is the cut-out wind speed, unit: m / s.

[0016] A further improvement of the technical solution of the present invention is that the power output model of the photovoltaic power generation system adopts a conventional power output model, which is as follows:

[0017]

[0018] In formula (2): P pv is the actual output power of the photovoltaic power generation system; P stc is the output power of the photovoltaic power generation system at standard solar radiation intensity and temperature; I is the actual solar radiation intensity, unit is w / m 2;I stc Standard solar radiation intensity, take 1000w / m 2 β t is the power temperature coefficient of the photovoltaic power generation system; T is the actual temperature; T stc The standard temperature is 25℃.

[0019] A further improvement of the technical solution of the present invention is that the optimization model in step S3 includes:

[0020] Optimization model of initial investment cost with equal annual value:

[0021]

[0022] Where:

[0023] F1—initial investment cost of equal annual value, unit: yuan;

[0024] N—system equipment type;

[0025] C eq,i —Total initial investment cost of each equipment in the system;

[0026] r — bank rate;

[0027] n—Service life of each device in the system;

[0028] α—plateau coefficient;

[0029] Operation and maintenance cost optimization model:

[0030] F2=α(F op +F ma ) (4),

[0031] Where:

[0032] F2—system operation and maintenance cost, unit: yuan;

[0033] F op —System operation and management cost, unit: yuan;

[0034] F ma —System maintenance cost, unit: yuan;

[0035] Optimization model for penalty cost of wind and power curtailment:

[0036] F3=C waste E i (5)

[0037] Where:

[0038] F3—penalty cost for abandoning wind and power, unit: yuan;

[0039] C waste—Unused electricity penalty coefficient, unit: yuan / kwh;

[0040] E i —Unused electricity, unit: kwh.

[0041] A further improvement of the technical solution of the present invention is that the function obtained in step S4 is as follows:

[0042]

[0043] Where ω1, ω2, and ω3 are the weights of the three objectives, satisfying ω1+ω2+ω3=1.

[0044] A further improvement of the technical solution of the present invention is that the process of the adaptive genetic algorithm is as follows:

[0045] (5) Initialize the population and set the population size, chromosome size and convergence conditions;

[0046] (6) Calculate individual fitness, average fitness and maximum fitness;

[0047] (7)Judgment Is it true? If true, it means that the average fitness and the maximum fitness are not much different, and the population difference is small; if not true, it means that the average fitness and the maximum fitness are very different, and the population difference is large; through such a criterion, the subsequent crossover and mutation selection are performed;

[0048] (8) Perform crossover, mutation, and selection operations to determine whether the convergence conditions are met. If so, output the result; if not, return to step (2).

[0049] And proposed adaptive crossover and mutation probability formula:

[0050]

[0051]

[0052] When f av / f max When f ≤1 / 2, it means that the average fitness value of the population is very different from the maximum fitness value of the population. At this time, the population has a large difference, rich species, and good population diversity. Therefore, it is necessary to increase the crossover probability and operation, exchange chromosome genes, and achieve high-quality evolution; on the contrary, f av / f max When ≥1 / 2, it means that the average population fitness is not much different from the maximum population fitness. At this time, the population difference is small and the diversity is poor, so it is necessary to increase the mutation probability and operation to prevent the algorithm from entering the local optimum.

[0053] A further improvement of the technical solution of the present invention is that according to the proposed adaptive genetic algorithm, the planning content flow is as follows:

[0054] (1) Input parameters according to the actual conditions of natural conditions and on-site environment, encode the parameters, and generate the initial population;

[0055] (2) Calculate the power flow of the system by forward-backward substitution method;

[0056] (3) Calculate the fitness function of each individual;

[0057] (4) Improve the operation of adaptive genetic algorithm;

[0058] (5) Generate a new generation of population;

[0059] Determine whether the termination condition is met. If not, return to (2). If so, output the optimal result.

[0060] Due to the adoption of the above technical solution, the technical progress achieved by the present invention is:

[0061] The present invention comprehensively considers factors such as natural resources in high-altitude areas, load demand, and working characteristics of each unit of the system, establishes an economic cost model with the optimal annual equivalent initial investment cost, operation and maintenance cost, and penalty cost for abandoned wind and power, and combines the linear weighted summation method with the improved adaptive genetic algorithm to provide a practical solution to the problem of site selection and sizing of distributed power sources in the distribution network in Tibet.

[0062] The present invention utilizes the actual measurement data of Daocheng County, Ganzi Prefecture, Sichuan Province, can fully reflect the local actual situation, and is realistic.

[0063] The present invention takes into account the actual environmental conditions in high altitude areas and establishes an economic cost model. When constructing the optimization model and the constraint model, it takes into account indicators such as the plateau coefficient of equipment operation and makes a distinction from the distribution network in the plain area.

[0064] The present invention combines a linear weighted summation method with an improved genetic algorithm to solve the optimization model and obtain a corresponding distribution network planning formula, which is stable and practical. BRIEF DESCRIPTION OF THE DRAWINGS

[0065] Figure 1 is a flow chart of the present invention;

[0066] Figure 2 It is the flow chart of the improved adaptive genetic algorithm of the present invention;

[0067] Figure 3 It is the result of the distributed power generation site selection and capacity planning of the present invention. DETAILED DESCRIPTION

[0068] The present invention is further described in detail below in conjunction with embodiments:

[0069] like Figure 1 As shown, a method for planning a distribution network in a high altitude area includes the following steps:

[0070] S1. Construct a distribution network system (including photovoltaic generator units, wind turbine generator units, diesel generator units and energy storage battery units) according to the natural resource conditions and load change status in high-altitude areas;

[0071] S2. According to the basic conditions and characteristics of various local units, a steady-state power output model of each unit was established, and typical sunlight, wind power and load curves were drawn. The power output model is as follows:

[0072] Wind turbine power output model:

[0073] A wind turbine is a device that converts wind energy in the natural environment into electrical energy. Its output power is related to factors such as wind speed, wind direction, and control method. The present invention uses a conventional power output model and only considers the effect of wind speed on output power. The model is as follows:

[0074]

[0075] In formula (1): P w is the actual output power of the wind turbine; P r is the rated power of the wind turbine; v is the actual wind speed (unit: m / s); v r is the rated wind speed (unit: m / s); v ci is the cut-in wind speed (unit: m / s); v co is the cut-out wind speed (unit: m / s).

[0076] Photovoltaic power generation system power output model:

[0077] The photovoltaic power generation system is a device that converts light energy in the natural environment into electrical energy. Its output power is related to the solar radiation intensity, temperature and temperature coefficient. The present invention uses a conventional power output model, which is as follows:

[0078]

[0079] In formula (2): P pv is the actual output power of the photovoltaic power generation system; P stc is the output power of the photovoltaic power generation system at standard solar radiation intensity and temperature; I is the actual solar radiation intensity (unit: w / m 2 );I stc Standard solar radiation intensity (take 1000w / m 2 );β tis the power temperature coefficient of the photovoltaic power generation system; T is the actual temperature; T stc The standard temperature is 25°C.

[0080] S3. Based on the typical sunlight, wind power and load curves drawn, an optimization model with annual equivalent initial investment cost, operation and maintenance cost and penalty cost for wind and power abandonment is established to reasonably plan the location and capacity of the system's distributed power sources (photovoltaic generators, wind turbines);

[0081] The optimization model includes:

[0082] Optimization model of initial investment cost with equal annual value:

[0083]

[0084] Where:

[0085] F1—initial investment cost of equal annual value, unit: yuan;

[0086] N—system equipment type;

[0087] C eq,i —Total initial investment cost of each equipment in the system;

[0088] r — bank rate;

[0089] n—Service life of each device in the system;

[0090] α—plateau coefficient;

[0091] Operation and maintenance cost optimization model:

[0092] F2=α(F op +F ma ) (4),

[0093] Where:

[0094] F2—system operation and maintenance cost, unit: yuan;

[0095] F op —System operation and management cost, unit: yuan;

[0096] F ma —System maintenance cost, unit: yuan;

[0097] Optimization model for penalty cost of wind and power curtailment:

[0098] F3=C waste E i (5)

[0099] Where:

[0100] F3—penalty cost for abandoning wind and power, unit: yuan;

[0101] C waste —Unused electricity penalty coefficient, unit: yuan / kwh;

[0102] E i —Unused electricity, unit: kwh.

[0103] S4. Comprehensively consider the mutual influence of the three objective functions and use the linear weighted summation method to transform the multi-objective problem into a single-objective problem for solution, as shown in the following formula:

[0104]

[0105] Where ω1, ω2, and ω3 are the weights of the three objectives, satisfying ω1+ω2+ω3=1.

[0106] S5. For the distributed power location capacity planning solution method, the present invention improves an adaptive genetic algorithm. By changing the crossover and mutation operators in the genetic process, the concentration and dispersion of fitness in genetic evolution are fully utilized, which not only maintains the diversity between populations, but also prevents falling into the local optimum in the late stage of evolution. The algorithm process is as follows:

[0107] (1) Figure 2 As shown, the population is initialized, and the population size, chromosome size and convergence conditions are set;

[0108] (2) Calculate individual fitness, average fitness and maximum fitness;

[0109] (3)Judgment Is it true? If true, it means that the average fitness and the maximum fitness are not much different, and the population difference is small; if not true, it means that the average fitness and the maximum fitness are very different, and the population difference is large; through such a criterion, the subsequent crossover and mutation selection are performed;

[0110] (4) Perform crossover, mutation, and selection operations to determine whether the convergence conditions are met. If so, output the result; if not, return to step (2).

[0111] And propose adaptive crossover and mutation probability formula:

[0112]

[0113]

[0114] When f av / f maxWhen f ≤1 / 2, it means that the average fitness value of the population is very different from the maximum fitness value of the population. At this time, the population has a large difference, rich species, and good population diversity. Therefore, it is necessary to increase the crossover probability and operation, exchange chromosome genes, and achieve high-quality evolution; on the contrary, f av / f max When ≥1 / 2, it means that the average population fitness is not much different from the maximum population fitness. At this time, the population difference is small and the diversity is poor, so it is necessary to increase the mutation probability and operation to prevent the algorithm from entering the local optimum.

[0115] According to the proposed adaptive genetic algorithm, the planning content process is as follows:

[0116] (1) Input parameters according to the actual conditions of natural conditions and on-site environment, encode the parameters, and generate the initial population;

[0117] (2) Calculate the power flow of the system by forward-backward substitution method;

[0118] (3) Calculate the fitness function of each individual;

[0119] (4) Improve the operation of adaptive genetic algorithm;

[0120] (5) Generate a new generation of population;

[0121] Determine whether the termination condition is met. If not, return to (2). If so, output the optimal result.

[0122] Figure 3 It is the result of the distributed power site selection and sizing planning of the present invention. The present invention adopts IEEE33 node as the test system, the system means voltage is 12.66kv, the distributed power supply adopts PQ type node with stable output power, the power factor is 1, the distributed power supply capacity that can be connected to the system is 50kVA, the maximum iteration coefficient in the genetic algorithm is 100, the selection probability is 0.2, the initial trial crossover probability is 0.8, the initial mutation probability is 0.2, and the topographic map of Daocheng County, Ganzi Prefecture, Sichuan Province and the information of each node in the map are intercepted as the distribution network map, and MATLAB software is used to reasonably plan the site selection and sizing of the distributed power supply of the distribution network.

[0123] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A research method for distribution network planning in high altitude areas, characterized in that: The steps include: S1. According to the natural resource conditions in high altitude areas and the changing state of user loads, a distribution network system is constructed, wherein the distribution network system includes a photovoltaic generator unit, a wind turbine generator unit, a diesel generator unit and an energy storage battery unit; S2. According to the basic conditions and characteristics of each unit in the local distribution network system, a steady-state power output model of each unit was established, and typical sunlight, wind power and load curves were drawn; The steady-state power output model of each unit includes a wind turbine power output model and a photovoltaic power generation system power output model; The wind turbine power output model uses a conventional power output model, which only considers the effect of wind speed on output power. The model is as follows: In formula (1): P w is the actual output power of the wind turbine; P r is the rated power of the wind turbine; v is the actual wind speed, unit: m / s; v r is the rated wind speed, unit: m / s; v ci is the cut-in wind speed, unit: m / s; v co is the cut-out wind speed, unit: m / s; The photovoltaic power generation system power output model uses a conventional power output model, which is as follows: In formula (2): P pv is the actual output power of the photovoltaic power generation system; P stc It is the output power of the photovoltaic power generation system at standard solar radiation intensity and temperature; I is the actual solar radiation intensity, unit is w / m 2 ; I stc Standard solar radiation intensity, take 1000w / m 2 ; β t is the power temperature coefficient of the photovoltaic power generation system; T is the actual temperature; T stc The standard temperature is 25℃; S3. Based on the typical sunlight, wind power and load curves drawn, an optimization model with annual equivalent initial investment cost, operation and maintenance cost and penalty cost for wind and power abandonment is established to reasonably plan the location and capacity of photovoltaic generator units and wind turbine generator units; S4, comprehensively considering the mutual influence of the three objective functions in step S3, using the linear weighted summation method, converting the multi-objective problem into a single-objective problem for solution; S5. Aiming at the solution method of distributed power location capacity planning, an adaptive genetic algorithm is improved. By changing the crossover and mutation operators in the genetic process, the concentration and dispersion of fitness in genetic evolution are fully utilized, which not only maintains the diversity among populations, but also prevents falling into local optimality in the late stage of evolution.

2. A method for researching distribution network planning in high altitude areas according to claim 1, characterized in that: The optimization model in step S3 includes: Optimization model of initial investment cost with equal annual value: Where: F1—initial investment cost of equal annual value, unit: yuan; N—system equipment type; C eq,i —Total initial investment cost of each equipment in the system; r — bank rate; n—Service life of each device in the system; α—plateau coefficient; Operation and maintenance cost optimization model: F2=α(F op +F ma ) (4), Where: F2—system operation and maintenance cost, unit: yuan; F op —System operation and management cost, unit: yuan; F ma —System maintenance cost, unit: yuan; Optimization model for penalty cost of wind and power curtailment: F3=C waste AND i (5), Where: F3—penalty cost for abandoning wind and power, unit: yuan; C waste —Unused electricity penalty coefficient, unit: yuan / kwh; E i —Unused electricity, unit: kwh.

3. A method for researching distribution network planning in high altitude areas according to claim 1, characterized in that: The function obtained in step S4 is as follows: Where ω1, ω2, and ω3 are the weights of the three objectives, satisfying ω1+ω2+ω3=1.

4. A method for studying distribution network planning in high altitude areas according to claim 1, characterized in that: The process of the adaptive genetic algorithm is as follows: (1) Initialize the population and set the population size, chromosome size and convergence conditions; (2) Calculate individual fitness, average fitness and maximum fitness; (3)Judgment Is it true? If true, it means that the average fitness and the maximum fitness are not much different, and the population difference is small; if not true, it means that the average fitness and the maximum fitness are very different, and the population difference is large; through such a criterion, the subsequent crossover and mutation selection are performed; (4) Perform crossover, mutation, and selection operations to determine whether the convergence conditions are met. If so, output the result; if not, return to step (2); And proposed adaptive crossover and mutation probability formula: When f av / f max When f ≤1 / 2, it means that the average fitness value of the population is very different from the maximum fitness value of the population. At this time, the population has a large difference, rich species, and good population diversity. Therefore, it is necessary to increase the crossover probability and operation, exchange chromosome genes, and achieve high-quality evolution; on the contrary, f av / f max When ≥1 / 2, it means that the average population fitness is not much different from the maximum population fitness. At this time, the population difference is small and the diversity is poor, so it is necessary to increase the mutation probability and operation to prevent the algorithm from entering the local optimum.

5. A method for studying distribution network planning in high altitude areas according to claim 4, characterized in that: According to the proposed adaptive genetic algorithm, the planning content process is as follows: (1) Input parameters according to the actual conditions of natural conditions and on-site environment, encode the parameters, and generate the initial population; (2) Calculate the power flow of the system by forward-backward substitution method; (3) Calculate the fitness function of each individual; (4) Improve the operation of adaptive genetic algorithm; (5) Generate a new generation of population; Determine whether the termination condition is met. If not, return to (2). If so, output the optimal result.

Citation Information

Patent Citations

  • Expansion planning comprehensive optimization method of power distribution network with distributed power supply

    CN103514570A

  • Active power-distribution-network distributed power source planning method based on source and load matching degree

    CN107688879A