A method for offshore wind farm black start active power control

By constructing a short-term prediction model for offshore wind power and a fuzzy control method, combined with overspeed load reduction control, adaptive adjustment of active power in offshore wind farms was achieved, solving the problem of limited adjustment range in traditional schemes and improving the stability and control accuracy of active power during black start.

CN114792996BActive Publication Date: 2026-11-20中广核如东海上风力发电有限公司 +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210451622.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-04-27
Publication Date
2026-11-20
Estimated Expiration
2042-04-27

AI Technical Summary

Technical Problem

Traditional black start schemes for offshore wind farms cannot adapt to complex and variable climate environments, and existing active power control methods for wind power have limitations, failing to effectively regulate active power and affecting the stability and recovery speed of the power system.

Method used

A short-term prediction model for offshore wind power is constructed. By combining overspeed load reduction control and fuzzy control methods, the wind turbine speed and power output are adjusted through an auxiliary power compensation circuit to achieve adaptive adjustment of active power.

Benefits of technology

It improves the stability and control accuracy of active power during the black start process of offshore wind farms, expands the active power regulation range, and enhances the recovery speed and stability of the power system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114792996B_ABST
    Figure CN114792996B_ABST
Patent Text Reader

Abstract

The application discloses a kind of offshore wind farm black start active power control methods, belong to new energy conversion and control technical field, including the following steps: step 1, constructs offshore wind power short-term prediction model, calculates system active demand;Step 2, configure frequency modulation spare capacity of fan and diesel generator capacity, using the overspeed load shedding control of optimal speed, set load shedding ratio;Step 3, calculate the system active demand fluctuation value in the process of offshore wind farm black start, make fan obtain the spare capacity exceeding maximum speed limit by auxiliary power compensation method;The offshore wind farm black start active power control method, utilizes the operating characteristics of offshore wind farm to design the active control of fan, solves the frequency fluctuation influence caused by system operating state and island system self-starting process, increases the active regulation range, improves the control precision and response speed of scheme, greatly improves the active power stability in the process of offshore wind farm black start.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of new energy conversion and control technology, specifically relating to a black-start active power control method for offshore wind farms. Background Technology

[0002] With the widespread application of offshore wind power in power systems, while increasing the wind power penetration rate of coastal local power systems, it also increases the stability risks of the power system. Using offshore wind farms as black start power sources can accelerate the recovery speed of local coastal power systems. However, traditional black start schemes cannot fully adapt to the complex and variable climate environment at sea, and traditional wind power active power control methods also have many limitations. On the one hand, the output power loss of offshore wind farms is affected by wake effects and atmospheric stability, requiring the establishment of more targeted short-term power prediction models for offshore wind farms to provide active power calculation basis for the design scheme of offshore wind farms as black start power sources. On the other hand, traditional wind turbine active power frequency regulation schemes all have certain limitations, especially the power reduction start-up required during the black start process of offshore wind power and the frequency fluctuations caused by the continuous switching of loads. Both require the design of active power control schemes suitable for the black start stage of offshore wind farms.

[0003] In traditional active power control schemes for wind turbines, pitch angle control is simple and easy to operate, but long-term adjustment will damage the service life of the equipment; overspeed load shedding control has a fast response speed and flexible control, but the adjustment range is limited by the maximum speed; using energy storage to regulate frequency fluctuations has good response characteristics, but it increases additional costs and is not economically viable; therefore, it is necessary to develop a black start active power control method for offshore wind farms to solve the existing problems. Summary of the Invention

[0004] The purpose of this invention is to provide a black-start active power control method for offshore wind farms, so as to solve the problem that offshore wind farms cannot achieve adaptive adjustment of active power during power system restoration when used as black-start power sources.

[0005] To achieve the above objectives, the present invention provides the following technical solution: a method for controlling active power during black start in offshore wind farms, comprising the following steps:

[0006] Step 1: Construct a short-term forecast model for offshore wind power and calculate the system's active power demand;

[0007] Step 2: Configure the wind turbine frequency regulation standby capacity and diesel generator capacity, use the optimal speed overspeed load reduction control, and set the load reduction ratio;

[0008] Step 3: Calculate the fluctuation value of the active power demand of the system during the black start process of the offshore wind farm, and use the auxiliary power compensation method to enable the wind turbine to obtain a reserve capacity exceeding the maximum speed limit;

[0009] Step 4: Set the compensation coefficient, trigger threshold, and input quantization factor for the auxiliary power compensation. Using fuzzy control, the auxiliary power compensation absorbs and releases power at several levels.

[0010] Preferably, in step 1, the short-term prediction model for offshore wind power is based on wind direction changes and power loss due to wind farm wake effect, and quantifies the power loss value due to wind direction wake effect. At the same time, atmospheric stability data is collected, and the features that measure atmospheric stability are input into the prediction model.

[0011] The parameters used to measure atmospheric stability include turbulence length and wind shear.

[0012]

[0013]

[0014] In the formula: T and S represent turbulence intensity and wind shear, respectively. V represents the standard deviation of wind speed measurements at a height of 90m on the meteorological mast. 90 V 40 The wind speed values ​​were measured by a rotating cup anemometer at heights of 90m and 40m on the meteorological mast, respectively.

[0015] Preferably, the power loss due to the wind farm wake effect is calculated by using a wind farm wake model to characterize the power loss due to the wind farm wake effect.

[0016] P i =W(v) i ,d i ;α)+δ i

[0017] In the formula: W(·) represents the wake effect loss of the wind farm; v i and d i These represent wind speed and wind direction, respectively; α is the regression parameter; δ i White noise has a mean of 0 and a variance of σ. 2 Gaussian random variables.

[0018] Preferably, the wind direction W(v) i ,d i ;α) can be used with respect to v i The regression function is expressed as:

[0019]

[0020] In the formula: W(v) i ,d i ;α) and v i Nonlinear correlation; [d i[Rounds the wind direction value to the nearest integer;] Indicates v i Column vectors; α [di] v is the corresponding row vector of regression coefficients; c and v r The cut-in wind speed and rated wind speed of the wind turbine are used to obtain the response power and wind direction parameters, which are then input into the short-term prediction model for offshore wind power.

[0021] Preferably, in step 1, the short-term prediction model for offshore wind power is based on a recurrent neural network and uses an Encoder-decoder framework with an attention mechanism.

[0022] Preferably, in step 2, the overspeed load reduction control step includes: active frequency regulation by controlling the rotor speed. When the wind turbine speed increases, it is moved from the maximum power tracking point to the second-best operating point. At this time, the wind turbine output is reduced, so that a part of the power is stored in the rotor and a reserve capacity for frequency regulation is retained.

[0023] The mechanical power P obtained by the fan m Represented as:

[0024]

[0025] In the formula: ρ is the air density; R is the wind turbine radius; v is the wind speed; C p (λ,β) represents the wind energy utilization coefficient of the wind turbine, where λ is the tip speed ratio, λ=ω r R / v; β is the pitch angle; coefficient

[0026] By changing the rotor speed of the wind turbine to reserve power, the unit gains power support capability. The power captured by the turbine in unloaded mode is:

[0027]

[0028] In the formula: the initial load shear output power of the wind turbine is P del0 The initial unloading speed is ω del0 The load reduction ratio is limited by the maximum rotor speed of the fan, and the maximum load reduction of the fan is:

[0029]

[0030] In the formula: v ij This refers to the input wind speed of the fan; This is the maximum permissible rotor speed of the fan.

[0031] Preferably, in step 4, the auxiliary power compensation P ad Based on the adaptive adjustment of frequency change rate and frequency deviation, its expression is:

[0032]

[0033] In the formula: r is the adjustment threshold of the auxiliary power compensation stage, and the absolute value of dω / dt is taken to make P ad For adjustments that are not affected by the sign of the rate of change of frequency, use Δω to determine P. ad Adjust the direction, where K is the adjustment compensation coefficient.

[0034] Preferably, in step 4, the fuzzy control method includes: dividing the frequency deviation and frequency change rate at the command power step into several intervals, obtaining a fuzzy control law table for the auxiliary power compensation link, and constructing a fuzzy controller using the obtained law.

[0035] Preferably, the step of constructing the fuzzy controller includes:

[0036] Fuzzification steps: The input variables of frequency deviation and frequency change rate are normalized using quantization factors. K1 and K2 are the input quantization factors, and K1 and K2 are the amplitudes of angular frequency deviation and angular frequency change rate under maximum power fluctuation, respectively. The basic universe of discourse of angular frequency deviation and angular frequency change rate is set to [-1, 1]. The range of output variable is set to [-1, 1], representing the adjustment ratio U of the inertial auxiliary power compensation link. By defining membership functions, the input and output can be converted into fuzzy variables. The membership functions use triangular and S-shaped membership functions to divide the quantized input and output into five levels: NL represents negative large, NS represents negative small, ZO represents zero, PS represents positive small, and PL represents positive large.

[0037] Fuzzy inference steps: Based on the fuzzy control law and the input-output membership function, design fuzzy rules based on the Mamdani type;

[0038] Defuzzing step: The output is defuzzified using the centroid method to obtain the auxiliary power compensation stage adjustment P. ad Where P ad The design logic is that the absorbed power is negative and the released power is positive.

[0039] The technical effects and advantages of this invention are as follows: This active power control method for black start of offshore wind farms utilizes the operating characteristics of offshore wind farms to design active power control of wind turbines, solves the influence of frequency fluctuations caused by system operating status and the self-starting process of isolated systems, increases the active power adjustment range, improves the control accuracy and response speed of the scheme, and greatly improves the stability of active power during the black start process of offshore wind farms. It has important academic significance and engineering practical value.

[0040] This invention considers the fluctuations in active power demand during the black start process of offshore wind farms. It adds an auxiliary power compensation stage within the existing speed control, expanding the frequency regulation range and enabling the wind turbines to obtain reserve capacity exceeding the maximum speed limit, thus improving the active power regulation range. By rationally setting the expression and trigger threshold of the auxiliary power compensation, frequent operation of the auxiliary power compensation stage caused by slight frequency fluctuations is avoided. Simultaneously, the introduced auxiliary power compensation stage can adaptively adjust according to frequency changes and deviations, improving the active power regulation speed. For the setting of the compensation coefficient and input quantization factor of the auxiliary power compensation stage, a fuzzy control method is adopted, setting fuzzy rules according to the scenario. This allows the auxiliary power compensation stage to absorb and release power at multiple levels, improving the accuracy of active power regulation. Attached Figure Description

[0041] Figure 1 This is a schematic diagram of the process of the present invention;

[0042] Figure 2 This is a flowchart of the black start active power control scheme for offshore wind farms according to the present invention;

[0043] Figure 3 This is a diagram of the offshore wind power prediction Encoder-decoder framework of the present invention;

[0044] Figure 4 This invention provides a fuzzy controller for the auxiliary power compensation stage. Detailed Implementation

[0045] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0046] This invention provides, for example Figure 1 , Figure 2 The method for controlling the active power during black start of an offshore wind farm, as shown, includes the following steps:

[0047] Step 1: Construct a short-term forecast model for offshore wind power and calculate the system's active power demand; determine the number of wind turbines to be started and the active power demand values ​​of other equipment to be started in the system.

[0048] Based on the equipment startup sequence of the black start scheme for offshore wind farms, the active power demand of the startup equipment at each stage is calculated. Considering the complex meteorological environment of offshore wind farms, to determine the number of wind turbines to start, the influence of atmospheric stability and wake effects is fully considered when making short-term wind power forecasts. Characteristics measuring atmospheric stability are used as inputs to the forecast model. Simultaneously, a power-wind direction model is constructed based on wind direction changes and the power loss due to the wake effect of the wind farm, thereby quantifying the power loss value due to the wake effect at each wind direction. The atmospheric stability measurement parameter uses the Moning-Obuhoff length, whose value can be characterized by turbulence length and wind shear.

[0049]

[0050]

[0051] In the formula: T and S represent turbulence intensity and wind shear, respectively. V represents the standard deviation of wind speed measurements at a height of 90m on the meteorological mast. 90 V 40 The wind speed values ​​were measured by a rotating cup anemometer at heights of 90m and 40m on the meteorological mast, respectively.

[0052] For calculating the power loss due to the wake effect in wind farms, a Pd model is proposed to characterize the power loss caused by the wake effect:

[0053] P i =W(v) i ,d i ;α)+δ i

[0054] In the formula: W(·) represents the wake effect loss of the wind farm; v i and d i These represent wind speed and wind direction, respectively; α is the regression parameter; δ i White noise has a mean of 0 and a variance of σ. 2 The Gaussian random variable; therefore, the power loss P of the wind farm. i Primarily generated by the wake effect, and also influenced by atmospheric stability; where W(v) of a certain wind direction i ,d i ;α) can be used with respect to v i The regression function is expressed as:

[0055]

[0056] In the formula: W(v) i ,d i ;α) and v i Nonlinear correlation; [d i [Rounds the wind direction value to the nearest integer;] Indicates v i Column vectors; v is the corresponding row vector of regression coefficients; c and v r These are the cut-in wind speed and rated wind speed of the wind turbine, respectively; the response power wind direction parameter derived from this formula is also called the Pd parameter, which serves as the model input for short-term prediction of offshore wind power.

[0057] The model employs a recurrent neural network, considers atmospheric stability factors, and uses an Encoder-decoder framework with an attention mechanism, such as... Figure 3 As shown, this improves prediction accuracy;

[0058] Step 2: Configure the wind turbine frequency regulation reserve capacity and diesel generator capacity, use the optimal speed overspeed load reduction control, and set the load reduction ratio; comprehensively consider the frequency regulation factors of both wind turbine frequency regulation reserve capacity and diesel generator capacity configuration, in the initial stage of startup with a small load, use rotor kinetic energy to store reserve capacity, adopt the optimal speed overspeed load reduction control, and reasonably set the load reduction ratio without exceeding the maximum allowable speed of the wind turbine.

[0059] Overspeed load reduction control is a method of active frequency regulation by controlling the rotor speed. When the wind turbine speed increases, it is moved from the maximum power tracking point to the second-best operating point. At this time, the wind turbine output is reduced, which allows some power to be stored in the rotor, leaving a reserve capacity for frequency regulation.

[0060] In this embodiment, the fan is a doubly-fed fan, and the fan obtains mechanical power P. m It can be represented as:

[0061]

[0062] In the formula: ρ is the air density; R is the wind turbine radius; v is the wind speed; C p (λ,β) represents the wind energy utilization coefficient of the wind turbine, where λ is the tip speed ratio, λ=ω r R / v; β is the pitch angle; coefficient

[0063] To enable wind turbines to operate under reduced load at a non-maximum power point, the rotor speed of the wind turbine needs to be changed to reserve power, thus giving the unit power support capability. The power captured by the wind turbine in reduced load mode is:

[0064]

[0065] In the formula: the initial load shear output power of the wind turbine is P del0 The initial unloading speed is ω del0 However, its load reduction ratio is limited by the maximum rotor speed of the fan, and the maximum load reduction of the fan is:

[0066]

[0067] In the formula: v ij This refers to the input wind speed of the fan; This refers to the maximum permissible rotor speed of the fan;

[0068] Step 3: Calculate the active power demand fluctuation during the black start of the offshore wind farm, and use auxiliary power compensation methods to enable the wind turbines to obtain reserve capacity exceeding the maximum speed limit. Considering the active power demand fluctuation during the black start of the offshore wind farm, an auxiliary power compensation stage is added within the original speed control to expand the frequency regulation range, enabling the wind turbines to obtain reserve capacity exceeding the maximum speed limit and improving the active power regulation range. The added auxiliary power compensation stage P... ad It can adaptively adjust based on the rate of change of frequency and frequency deviation, and its expression is:

[0069]

[0070] In the formula: r is the adjustment threshold of the auxiliary power compensation circuit. Setting the threshold avoids frequent operation of the auxiliary power compensation circuit caused by slight frequency fluctuations; taking the absolute value of dω / dt is to make P ad Adjustments that are independent of the sign of the rate of change of frequency are determined using Δω. ad Adjust the direction to ensure the adjustment is conducive to frequency stability; K is the adjustment compensation coefficient, and this coefficient must be set to ensure that the compensation power adjustment value does not exceed the maximum power fluctuation value, otherwise it will have side effects on the system; such as Figure 1 As shown,

[0071] interval Δω dω / dt <![CDATA[P ad ]]> 1 >0 >>0 Appropriately increase absorption 2 >>0 >0 Increase absorption 3 >>0 0 Increase absorption 4 >>0 <0 Appropriately reduce release 5 >0 <<0 Reduce release 6 0 <<0 constant 7 <0 <<0 Appropriately increase release 8 <<0 <0 Increase release 9 <<0 0 Increase release 10 <<0 >0 Appropriately reduce absorption 11 <0 >>0 Reduce absorption 12 0 >>0 constant

[0072] Table 1

[0073] Step 4: Set the compensation coefficient, trigger threshold, and input quantization factor for the auxiliary power compensation. Using fuzzy control, the auxiliary power compensation absorbs and releases power at several levels. By reasonably setting the expression and trigger threshold of the auxiliary power compensation, frequent operation of the auxiliary power compensation stage caused by slight frequency fluctuations can be avoided. At the same time, the introduced auxiliary power compensation stage can adaptively adjust according to frequency changes and frequency deviations, thereby improving the active power regulation speed. For the setting of the compensation coefficient and input quantization factor of the auxiliary power compensation stage, a fuzzy control method is adopted. Fuzzy rules are set according to the scenario, so that the auxiliary power compensation stage can absorb and release power at multiple levels, further improving the accuracy of active power regulation.

[0074] The frequency deviation and rate of change of the command power step are divided into multiple intervals, and a fuzzy control law table for the auxiliary power compensation link is obtained. A fuzzy controller is designed using these laws; where K1 and K2 are input quantization factors, and P...ad The design logic is that the absorbed power is negative and the released power is positive;

[0075] like Figure 4 As shown, the fuzzy controller construction steps include: fuzzification step, fuzzy inference step, and defuzzification step; Fuzzification step: The two input variables, frequency deviation and frequency change rate, are normalized using a quantization factor. K1 and K2 are the amplitudes of angular frequency deviation and angular frequency change rate under maximum power fluctuation, respectively. The basic universe of discourse for angular frequency deviation and angular frequency change rate is set to [-1, 1]; The range of output variable is also set to [-1, 1], representing the adjustment ratio U of the inertial auxiliary power compensation link. By defining the membership function, the input and output can be converted into fuzzy variables; Triangular and S-shaped membership functions are used for the membership function, and the quantized input and output are divided into five levels: NL (negative large), NS (negative small), ZO (zero), PS (positive small), and PL (positive large); Table 2 shows the fuzzy control rules for the auxiliary power compensation link;

[0076]

[0077] Fuzzy inference steps: Based on the fuzzy control law and the input-output membership function, design fuzzy rules based on the Mamdani type;

[0078] Defuzzification steps: The output is defuzzified using the centroid method, ultimately obtaining the auxiliary power compensation stage adjustment P. ad .

[0079] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.

Claims

1. A method for controlling active power during black start in offshore wind farms, characterized in that: Includes the following steps: Step 1: Construct a short-term forecast model for offshore wind power and calculate the system's active power demand; Step 2: Configure the wind turbine frequency regulation standby capacity and diesel generator capacity, use the optimal speed overspeed load reduction control, and set the load reduction ratio; Step 3: Calculate the fluctuation value of the active power demand of the system during the black start process of the offshore wind farm, and use the auxiliary power compensation method to enable the wind turbine to obtain a reserve capacity exceeding the maximum speed limit; Step 4: Set the compensation coefficient, trigger threshold, and input quantization factor for the auxiliary power compensation. Using fuzzy control, the auxiliary power compensation absorbs and releases power at several levels. In step 2, the overspeed load reduction control step includes: active frequency regulation by controlling the rotor speed. When the wind turbine speed increases, it is moved from the maximum power tracking point to the second-best operating point. At this time, the wind turbine output is reduced, so that a part of the power is stored in the rotor and reserve capacity for frequency regulation is retained. By changing the rotor speed of the wind turbine to reserve power, the unit gains power support capability, and the power P captured by the wind turbine in unloaded mode... del0 for: In the formula: the initial load shear output power of the wind turbine is P del0 The initial load reduction pitch angle is β. del0 The initial unloading speed is ω. del0 The load reduction ratio is limited by the maximum rotor speed of the fan, and the maximum load reduction of the fan is: In the formula: v ij β is the input wind speed of the fan in the i-th row and j-th column; ij The action amount of the turbine pitch angle in the i-th row and j-th column; R represents the maximum permissible rotor speed of the fan in the i-th row and j-th column; tur The radius of the wind turbine rotor corresponding to the i-th row and j-th column; In step 4, the auxiliary power compensation P ad Based on the adaptive adjustment of frequency change rate and frequency deviation, its expression is: In the formula: r is the adjustment threshold of the auxiliary power compensation circuit, and the absolute value of dω / dt is taken to make P ad For adjustments that are not affected by the sign of the rate of change of frequency, use Δω to determine P. ad Adjustment direction, K is the adjustment compensation coefficient; In step 4, the fuzzy control method includes: dividing the frequency deviation and frequency change rate at the command power step into several intervals, obtaining the fuzzy control law table of the auxiliary power compensation link, and using the obtained law to construct a fuzzy controller; The steps for constructing the fuzzy controller include: Fuzzification steps: The input variables of frequency deviation and frequency change rate are normalized using quantization factors. K1 and K2 are the input quantization factors, and K1 and K2 are the amplitudes of angular frequency deviation and angular frequency change rate under maximum power fluctuation, respectively. The basic universe of discourse of angular frequency deviation and angular frequency change rate is set to [-1, 1]. The range of output variable is set to [-1, 1], representing the adjustment ratio U of the inertial auxiliary power compensation link. By defining membership functions, the input and output can be converted into fuzzy variables. The membership functions use triangular and S-shaped membership functions to divide the quantized input and output into five levels: NL represents negative large, NS represents negative small, ZO represents zero, PS represents positive small, and PL represents positive large. Fuzzy inference steps: Based on the fuzzy control law and the input-output membership function, design fuzzy rules based on the Mamdani type; Defuzzing step: The output is defuzzified using the centroid method to obtain the auxiliary power compensation stage adjustment P. ad , where P ad The design logic is that the absorbed power is negative and the released power is positive.

2. The method for controlling active power during black start of an offshore wind farm according to claim 1, characterized in that: In step 1, the short-term offshore wind power prediction model is based on wind direction changes and power loss due to wind farm wake effects, and quantifies the power loss value due to wind wake effects. Simultaneously, atmospheric stability data is collected, and features measuring atmospheric stability are input into the prediction model. The parameters measuring atmospheric stability include turbulence length and wind shear. In the formula: T and S represent turbulence intensity and wind shear, respectively. V represents the standard deviation of wind speed measurements at a height of 90m on the meteorological mast. 90 V 40 The wind speed values ​​were measured by a rotating cup anemometer at heights of 90m and 40m on the meteorological mast, respectively.

3. The method for controlling active power during black start in an offshore wind farm according to claim 2, characterized in that: The power loss due to the wind farm wake effect is calculated by characterizing the power loss due to the wind farm wake effect using a wind farm wake model: P i P i =W(v) i ,d i ;α)+δ i In the formula: W(·) represents the wake effect loss of the wind farm; v i and d i These represent wind speed and wind direction, respectively; α is the regression parameter. δ i White noise has a mean of 0 and a variance of σ. 2 Gaussian random variables.

4. The method for controlling active power during black start in an offshore wind farm according to claim 3, characterized in that: The wind direction W(v) i ,d i ;α) can be used with respect to v i The regression function is expressed as: In the formula: W(v) i ,d i ;α) and v i Nonlinear correlation; [d i [Rounds the wind direction value to the nearest integer;] Indicates v i Column vectors; v is the corresponding row vector of regression coefficients; c and v r The cut-in wind speed and rated wind speed of the wind turbine are used to obtain the response power and wind direction parameters, which are then input into the short-term prediction model for offshore wind power.

5. The method for controlling active power during black start of an offshore wind farm according to claim 1, characterized in that: In step 1, the short-term prediction model for offshore wind power is based on a recurrent neural network and uses an Encoder-decoder framework with an attention mechanism.

6. The method for controlling active power during black start of an offshore wind farm according to claim 1, characterized in that: In the overspeed load reduction control step, the fan obtains mechanical power P. m Represented as: In the formula: ρ is the air density; R is the wind turbine radius; v is the wind speed; C p (λ,β) represents the wind energy utilization coefficient of the wind turbine, where λ is the tip speed ratio, λ=ω r R / v; β is the pitch angle; coefficient .