Bayesian sequential test based turbine disk reliability verification method
By combining Bayesian sequential testing with finite element simulation and response surface modeling, the problems of large test sample size and unsuitability of simulation analysis in existing technologies are solved, and efficient and accurate analysis for turbine disk reliability verification is achieved.
Patent Information
- Application Number
- CN202210789409.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-06
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2042-07-06
AI Technical Summary
Existing technologies cannot effectively utilize test data to update test standards in real time, resulting in a large sample size requirement for turbine disk reliability verification tests, and they are not applicable to log-normal distribution and turbine disk reliability simulation analysis results.
A Bayesian sequential test method was adopted, which combined finite element simulation and response surface model to determine the prior distribution of turbine disk lifetime distribution parameters. The posterior distribution was obtained through Bayesian inference, and the test criteria were updated in real time to reduce the test sample size.
This study enables the prediction of turbine disk life distribution based on finite element simulation analysis results, improves the accuracy of reliability analysis, reduces testing costs, and provides theoretical support for turbine disk reliability design.
Smart Images

Figure CN115203840B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of aerospace engine technology, specifically relating to a turbine disk reliability verification method based on Bayesian sequential testing. Background Technology
[0002] The purpose of turbine disk reliability verification testing is to verify whether the actual reliability level meets the reliability index requirements, and it is one of the fundamental steps in improving turbine disk reliability. This invention studies a turbine disk reliability verification method based on Bayesian sequential testing. Starting from the reliability index of the turbine disk, it gives the null and alternative hypotheses of the overall distribution parameters. The prior distribution of the turbine disk lifetime distribution parameters is determined through simulation analysis, and the posterior distribution of the turbine disk lifetime distribution parameters is obtained through Bayesian inference. The posterior lifetime cumulative distribution is calculated using a sampling method. Considering the risks of misjudgment and omission, a turbine disk reliability verification test method based on Bayesian sequential testing is established.
[0003] Chinese invention patent CN111553073A, based on the distribution law of electronic product index, integrates reliability data from different sources to verify product reliability. However, this method is based on a fixed reliability verification test plan and cannot update the test standard in real time according to the test data, resulting in a large test sample size requirement and making it unsuitable for engineering. Existing literature "[1] Zhou Taogeng, Sha Dingguo. Bayesian reliability sequential verification test method [J]. Journal of Instrumentation, 2001(S2):373-374." establishes a Bayesian sequential test method based on Weibull distribution, but this method cannot be applied to log-normal distribution and cannot consider the turbine disk reliability simulation analysis results, and is not suitable for turbine disk reliability verification. Summary of the Invention
[0004] To overcome the shortcomings of existing technologies, this invention provides a turbine disk reliability verification method based on Bayesian sequential testing. The method involves grouping multiple failure sites of the turbine disk, using a grouping coupling function to characterize the correlation between multiple sites, and determining the coupling parameters in the coupling function based on experimental data. This enables crack propagation life reliability analysis that considers the correlation between multiple failure sites, thus serving and supporting aero-engine life prediction technology.
[0005] The technical solution adopted by this invention to solve the above-mentioned technical problems is as follows: a turbine disk reliability verification method based on Bayesian sequential testing, comprising the following steps:
[0006] (1) Conduct turbine disk life reliability simulation analysis and determine the prior distribution of life distribution parameters based on simulation results: Perform static strength analysis on the turbine disk to obtain the equivalent stress distribution in the turbine disk; use operating temperature and maximum speed as input random variables and maximum equivalent stress as output response to form an automatic simulation loop; based on 500 sets of data obtained from sampling calculation, fit surrogate models for the input random variables and output response of key areas respectively; perform 10 tests on the surrogate models. 5 Substituting the output response into the material stress-life probability model using Monte Carlo sampling, we obtain the life sample points of the critical failure region of the turbine disk; and fit the low-cycle fatigue life of the turbine disk using a log-normal distribution. Where μ1 is the logarithmic lifetime mean, and σ1 is the logarithmic lifetime standard deviation; assuming λ1 follows a gamma distribution, i.e., λ1~Ga(α1,β1), where Ga represents the gamma distribution, and α1 and β1 are the shape parameter and inverse scaling parameter of the gamma distribution, respectively, determined by fitting the sample data; it is assumed that the logarithmic distribution of the true life of the turbine disk has a mean of μ and a variance of σ, and... The prior distribution of a Bayesian sequential experiment can be represented as π(μ,λ)∝N(μ|μ1,(κ1λ)). -1 )×Ga(λ|α1,β1), where κ1 represents the sample size.
[0007] (2) Establish Bayesian sequential test criteria to obtain acceptance and rejection criteria for reliability tests when test results are available: Assume the lifetime of a single turbine disk test is y. i Given that the null hypothesis H0 and the alternative hypothesis H1 represent "the reliability level of the turbine disk does not meet the requirements" and "the reliability level of the turbine disk meets the requirements," respectively, the probability distributions of the null hypothesis H0 and the alternative hypothesis H1 are expressed as P(H0|y i ) and P(H1|y i The sum of the two is 1, where P() represents the probability distribution; given the reliability index of the turbine disk: the life corresponding to the reliability R is greater than N0, establish the acceptance criteria and rejection criteria for the reliability test of the turbine disk;
[0008] (3) Design a reliability verification test plan, update the reliability test criteria in real time based on the test data, and realize the reliability verification of the turbine disk.
[0009] Furthermore, in step (2), the acceptance criteria and rejection criteria are specifically as follows:
[0010] When existing experimental data y i At that time, the acceptance and rejection criteria for the reliability test of the turbine disk were described as follows:
[0011] ① Acceptance Criterion: This means that if the verification result is "H1: The true reliability level of the turbine disk meets the reliability index", the probability of being judged as not meeting the reliability index should be less than the risk of misjudgment. That is, the acceptance criterion is:
[0012] P(H1|y i )=1-P(H0|y i )≥1-ω (1)
[0013] Wherein, ω represents the risk of misjudgment, that is, the risk incurred when the actual reliability level of the turbine disk meets the reliability index, but is judged to be non-compliant.
[0014] ② Rejection Criterion: This indicates that if the verification result is "H0: The true reliability of the turbine disk does not meet the reliability index," the probability of it being judged as meeting the reliability index should be less than the risk of being missed. Therefore, the rejection criterion is:
[0015] P(H0|y i )=1-P(H1|y i )≥1-υ (2)
[0016] Here, υ represents the risk of missed detection, which is the risk incurred when the actual reliability level of the turbine disk does not meet the reliability index, but is judged to meet it.
[0017] For multiple lifetime samples Y = (y1, y2, ..., y m Based on the prior distribution π(μ,λ) obtained in step (1), the posterior distribution is calculated using the Bayesian inference method as follows:
[0018]
[0019] Where μ1, α1, and β1 are calculated in step one, and Γ(α) is the gamma function. Let μ² represent the sample mean, m represent the sample size for multiple lifetimes, and the formulas for calculating μ², κ², α², and β² are:
[0020]
[0021] The probabilities P(H0|Y) of the null hypothesis H0 being true and P(H1|Y) of the alternative hypothesis H1 being true are calculated as follows:
[0022]
[0023] Among them, Z 1-R The upper quantile of the normal distribution is (1-R).
[0024] Furthermore, the Bayesian sequential experiment in step (3) includes:
[0025] ① Conduct turbine disk life tests, assuming the test life obtained in the i-th test is y. i Each time, the sample data Y = (y1, y2, ..., y3) is used. i Determine whether to accept or reject the message, where i starts from 1;
[0026] ②According to Y=(y1,y2,…,y i ) Calculate expression (4), update the acceptance and rejection criteria, and determine whether acceptance or rejection is satisfied after the i-th trial;
[0027] ③ If the test is accepted, the verification is successful and the test stops; if the test is rejected, the verification is unsuccessful and the test stops; if neither condition is met, then i = i + 1, and proceed to step ①.
[0028] Beneficial effects:
[0029] This invention determines the turbine disk lifetime distribution based on finite element simulation and response surface modeling, using this as the prior distribution of turbine disk lifetime, thus fully utilizing the results of finite element simulation analysis. It establishes a Bayesian sequential testing method to judge the reliability verification results of the turbine disk, and updates the boundaries of accepting and rejecting reliability hypotheses in real time based on experimental data, providing a theoretical method for the reliability verification of high-cost mechanical structures such as turbine disks. This method can reduce the experimental sample size and save experimental costs. Finally, this invention obtains the posterior distribution of turbine disk lifetime by combining simulation analysis and small sample experimental data, further improving the accuracy of turbine disk reliability analysis and providing methodological support for turbine disk reliability design. Attached Figure Description
[0030] Figure 1 Integration process for Isight;
[0031] Figure 2 The flowchart shows the turbine disk reliability verification method based on Bayesian sequential testing.
[0032] Figure 3 This is a schematic diagram of a sequential test scheme. Detailed Implementation
[0033] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the invention. Furthermore, the technical features involved in the various embodiments of this invention described below can be combined with each other as long as they do not conflict with each other.
[0034] like Figure 2 As shown, the turbine disk reliability verification method based on Bayesian sequential testing of the present invention includes the following steps:
[0035] Step 1: Conduct turbine disk life reliability simulation analysis and determine the prior distribution of life distribution parameters based on the simulation results. Perform static strength analysis on the turbine disk to obtain the equivalent stress distribution within the turbine disk. Use operating temperature and maximum speed as input random variables, and the maximum equivalent stress as the output response. For example... Figure 1 As shown, the automatic simulation iteration process is formed by integrating ANSYS and MATLAB in Isight. Based on 500 sets of data obtained from Isight sampling calculations, surrogate models for the input random variables and output responses of key regions are fitted respectively. This invention selects a fourth-order response surface model as the surrogate model, with the expression:
[0036]
[0037] Where x1 represents the maximum speed and x2 represents the operating temperature.
[0038] Using MATLAB to perform 10... 5 Substituting the output response into the material stress-life probability model using Monte Carlo sampling, we obtain life sample points for the critical failure region of the turbine disk. The failure probability expression for a given life N is:
[0039]
[0040] The low-cycle fatigue life of the turbine disk was fitted using a log-normal distribution. Where μ1 is the logarithmic lifetime mean, and σ1 is the logarithmic lifetime standard deviation. Based on the characteristics of the normal distribution, The variance σ1 follows an inverse gamma distribution, i.e. Where IG represents the inverse gamma distribution. Assume... Then λ1 follows a gamma distribution, i.e., λ1~Ga(α1,β1), where Ga represents the gamma distribution, and α1 and β1 are the shape parameter and inverse scaling parameter of the gamma distribution, respectively, which are determined by fitting the sample data.
[0041] Therefore, assuming the logarithmic distribution of the true lifespan of the turbine disk has a mean of μ and a variance of σ, and... The prior distribution of a Bayesian sequential experiment can be represented as π(μ,λ)∝N(μ|μ1,(κ1λ)). -1 )×Ga(λ|α1,β1), where κ1 represents the sample size. In this invention, it is assumed that the equivalent sample size of the prior distribution is κ1=12.
[0042] Step 2: Establish Bayesian sequential testing criteria to obtain acceptance and rejection criteria for reliability tests when test results are available. Assume the lifetime of a single turbine disk test is y. iGiven that the null hypothesis H0 and the alternative hypothesis H1 represent "the reliability level of the turbine disk does not meet the requirements" and "the reliability level of the turbine disk meets the requirements," respectively, the probability distributions of the null hypothesis H0 and the alternative hypothesis H1 are expressed as P(H0|y i ) and P(H1|y i The sum of the two is 1, where P() represents the probability distribution.
[0043] Given the reliability index of the turbine disk: the lifetime corresponding to reliability R is greater than N0, then the expressions for the null hypothesis H0 and the alternative hypothesis H1 are:
[0044]
[0045] Among them, Z 1-R The upper quantile of the standard normal is shown in Table 1.
[0046] Table 1 Common upper quantiles of the standard normal distribution
[0047] quantile a 0.99 0.95 0.9 0.8 <![CDATA[upper quantile Z a > 2.329 1.645 1.282 0.842
[0048] In turbine disk reliability verification tests, the risk of misjudgment can be expressed as ω, the risk incurred when the actual reliability level of the turbine disk meets the reliability indicators but is judged to be non-compliant; the risk of omission can be expressed as υ, the risk incurred when the actual reliability level of the turbine disk does not meet the reliability indicators but is judged to be compliant. Given existing test data y... i At that time, the acceptance and rejection criteria for turbine disk reliability testing were described as follows:
[0049] ① Acceptance Criterion: This indicates that the verification result is "H1: The true reliability level of the turbine disk meets the reliability index." In this case, the probability of being judged as not meeting the reliability index should be less than the risk of incorrect judgment; that is, the acceptance criterion is...
[0050] P(H1|y i )=1-P(H0|y i )≥1-ω (4)
[0051] ② Rejection Criterion: This indicates that if the verification result is "H0: The true reliability of the turbine disk does not meet the reliability index," the probability of it being judged as meeting the reliability index should be less than the risk of being missed. In other words, the rejection criterion is...
[0052] P(H0|y i )=1-P(H1|y i )≥1-υ (5)
[0053] For multiple lifetime samples Y = (y1, y2, ..., y mAfter that, based on the prior distribution π(μ,λ) obtained in the first step, the posterior distribution is calculated using Bayesian inference methods as follows:
[0054]
[0055] Where μ1, α1, and β1 are calculated in step one, and Γ(α) is the gamma function. Let m represent the sample mean, m represent the sample size for multiple lifetimes, and the formulas for calculating μ², κ², α², and β² are as follows:
[0056]
[0057] According to equation (7), the probability P(H0|Y) of the null hypothesis H0 being true and the probability P(H1|Y) of the alternative hypothesis H1 being true are calculated as follows:
[0058]
[0059] In equation (8), p(μ,λ|Y) is complex, and complex integral calculations are performed through statistical simulation. Taking the expression of P(H0|Y) as an example, we first extract n λ = (λ1,λ2,…,λ) from p(λ|Y)=Ga(λ|α2,β2). n ), for each given λ i A p(μ|λ) can be determined i ,Y), from p(μ|λ i ,Y)=N(μ|μ2,(κ2λ i ) -1 Extract a μ from ) i We obtain μ = (μ1, μ2, ..., μ) n ).
[0060] Step 3: Design a reliability verification test plan, update the reliability test criteria in real time based on the test data, and realize the reliability verification of the turbine disk. Given the design requirements and acceptable false positive and false negative probabilities, and based on the acceptance and rejection criteria derived in Step 2, the turbine disk sequential test plan is obtained as follows: Figure 3 As shown, the specific description is as follows:
[0061] ① Conduct turbine disk life tests, assuming the test life obtained in the i-th test is y. i Each time, the sample data Y = (y1, y2, ..., y3) is used. i Determine whether to accept or reject the message, where i starts from 1;
[0062] ②According to Y=(y1,y2,…,y i ) Calculate expression (8), update the acceptance and rejection criteria, and determine whether acceptance or rejection is satisfied after the i-th trial;
[0063] ③ If the test is accepted, the verification is successful and the test stops; if the test is rejected, the verification is unsuccessful and the test stops; if neither condition is met, then i = i + 1, and proceed to step ①.
[0064] The above embodiments are provided merely for the purpose of describing the present invention and are not intended to limit the scope of the invention. The scope of the invention is defined by the appended claims. Various equivalent substitutions and modifications made without departing from the spirit and principles of the invention should be covered within the scope of the invention.
Claims
1. A method for verifying the reliability of a turbine disk based on Bayesian sequential testing, characterized in that, The process involves grouping multiple failure sites on the roulette wheel, characterizing the correlation between these sites using a grouping coupling function, determining the coupling parameters in the coupling function based on experimental data, and performing a reliability analysis of crack propagation life considering the correlation of multiple failure sites. This includes the following steps: (1) Conduct life reliability simulation analysis of turbine disk and determine the prior distribution of life distribution parameters with simulation results: conduct static strength analysis on turbine disk to obtain equivalent stress distribution in turbine disk; use operating temperature and maximum speed as input random variables and maximum equivalent stress as output response to form an automatic simulation cycle; Based on 500 sets of data obtained through sampling, surrogate models were fitted for the input random variables and output responses of key regions, respectively; the surrogate models were then subjected to 10... 5 Subsequent Monte Carlo sampling yields the output response, which is then substituted into the material stress-life probability model to obtain lifetime sample points in the critical region of turbine disk failure. The low-cycle fatigue life of the turbine disk was fitted using a log-normal distribution. Where μ1 is the logarithmic lifetime mean and σ1 is the logarithmic lifetime standard deviation; assuming λ1 follows a gamma distribution, i.e. Where Ga represents the gamma distribution, 1 and 1 represents the shape parameter and inverse scaling parameter of the gamma distribution, respectively, determined by fitting the sample data; assuming the mean of the logarithmic distribution of the true lifespan of the turbine disk is μ and the variance is σ, and... The prior distribution of a Bayesian sequential experiment is expressed as: ; Indicates sample size; (2) Establish Bayesian sequential test criteria and obtain acceptance and rejection criteria for reliability tests when test results are available: Assume that the lifetime of a single turbine disk test is y. i Given the null hypothesis and alternative hypotheses These represent "the reliability level of the turbine disk does not meet the requirements" and "the reliability level of the turbine disk meets the requirements," respectively. The null hypothesis... and alternative hypotheses The probability distributions are respectively expressed as and The sum of the two is 1, where P() represents the probability distribution; the reliability index of the given turbine disk is: reliability The corresponding lifespan is greater than Establish acceptance and rejection criteria for turbine disk reliability testing; (3) Design a reliability verification test plan, and update the acceptance and rejection criteria of the reliability test in real time based on the test data to realize the reliability verification of the turbine disk.
2. The turbine disk reliability verification method based on Bayesian sequential testing according to claim 1, characterized in that: In step (2), the acceptance criteria and rejection criteria are specifically as follows: When existing experimental data y i At that time, the acceptance and rejection criteria for the reliability test of the turbine disk were described as follows: ① Acceptance Criterion: This means that if the verification result is "H1: The true reliability level of the turbine disk meets the reliability index", the probability of being judged as not meeting the reliability index is less than the risk of misjudgment. Therefore, the acceptance criterion is: (1) in, This refers to the risk of misjudgment, which is the risk incurred when the actual reliability level of the turbine disk meets the reliability index, but is judged to be non-compliant. ② Rejection Criterion: This indicates that if the verification result is "H0: The true reliability of the turbine disk does not meet the reliability index," the probability of it being judged as meeting the reliability index is less than the risk of being missed. Therefore, the rejection criterion is: (2) in, This indicates the risk of missed detection, which is the risk incurred when the actual reliability level of the turbine disk does not meet the reliability index, but is judged to meet it. For multiple lifetime samples =( , ,…, Based on the prior distribution obtained in step (1), The posterior distribution, calculated using Bayesian inference methods, is as follows: (3) Where μ1, α1, and β1 are calculated in step one. For gamma function, μ represents the sample mean, m represents the sample size across multiple lifecycles, and μ² represents the sample size. The expressions for calculating α² and β² are: (7) Null hypothesis Probability of being true and alternative hypotheses Probability of being true The calculation is as follows: (4) Among them, Z 1-R The upper quantile of the normal distribution is (1-R).
3. The turbine disk reliability verification method based on Bayesian sequential testing according to claim 2, characterized in that: Step (3) specifically includes: ① Conduct turbine disk life tests, assuming the test life obtained in the i-th test is y. i Each time using sample data =( , ,…, Determine whether to accept or reject the message, where i starts from 1; ② According to =( , ,…, ) Calculate expression (4), update the acceptance and rejection criteria, and determine whether acceptance or rejection is satisfied after the i-th trial; ③ If the test is accepted, the verification is successful and the test stops; if the test is rejected, the verification is unsuccessful and the test stops; if neither condition is met, then i = i+1, and proceed to step ①.
Citation Information
Patent Citations
High-reliability electronic product reliability verification method
CN111553073A
Sequential verification test method of Weibull distribution reliability based on monitoring data