A control-scheduling integrated resource configuration decision system and method
By using an integrated control and scheduling resource allocation decision-making system, edge computing and adaptive communication strategies are employed to solve the problems of hierarchical management and information exchange barriers in the train operation control system, thereby improving train operation efficiency and optimizing resource allocation.
Patent Information
- Application Number
- CN202210898407.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-28
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2042-07-28
AI Technical Summary
The existing train operation control system suffers from problems such as multi-level hierarchical management, information exchange barriers, and weak computing power of onboard equipment, making it difficult to achieve autonomous operation adjustment and improve control and scheduling efficiency.
An integrated control and scheduling resource allocation decision-making system is adopted, including an information sensing system unit, a line global information processing unit, a communication adaptive modulation unit, a hierarchical decision-making unit, and an integrated operation and control scheduling unit. Through edge computing and adaptive communication strategies, it realizes global information management and resource optimization allocation.
It breaks down information and business silos in the layered architecture, improves train operation efficiency, realizes efficient overall management of autonomous adjustment and resource allocation, and reduces train delay time and energy consumption.
Smart Images

Figure CN115409323B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of train operation optimization technology, specifically relating to an integrated control and scheduling resource allocation decision system and method. Background Technology
[0002] Current train operation control systems primarily receive global commands from the dispatch center. The dispatch command system (CTC) controls and monitors train operation by issuing control and dispatch commands, ensuring trains run on schedule and on time. The CTC system issues control and dispatch commands based on the timetable and train operation status. The train operation control system, based on the dispatch commands, the status of trains ahead, and track conditions, generates a speed control curve for the train operation and supervises the driver's safe driving. Train operation status information is fed back to the dispatch center via wireless communication networks and wired ground networks, where dispatchers manually monitor the train's operation. When a train deviates from its operating plan due to unforeseen events, the dispatcher manually adjusts the train operation online and informs the driver of the dispatch command by telephone. The driver then completes the driving task under the safety protection of the train operation control system.
[0003] Therefore, given the existing system's problems such as multi-level hierarchical management, information exchange barriers, and weak computing power of onboard equipment, how to achieve autonomous operation and adjustment of control and scheduling and improve the efficiency of control and scheduling has become an urgent problem to be solved. Summary of the Invention
[0004] This invention provides an integrated control and scheduling resource allocation decision-making system and method to solve the above problems.
[0005] The technical solution of this invention is:
[0006] An integrated control and scheduling resource allocation decision system includes: an information perception system unit (1), a line global information processing unit (2), a communication adaptive modulation unit (3), a hierarchical decision unit (4), an integrated operation control and scheduling unit (5), and an on-board equipment unit (6); wherein, the information perception system unit (1) includes an edge acquisition node (1.1) and an edge computing node (1.2), and the on-board equipment unit (6) includes a single-vehicle intelligent adjustment unit (6.1) and a multi-vehicle collaborative adjustment unit (6.2).
[0007] A resource allocation decision-making method integrating control and scheduling includes the following steps:
[0008] S1, the information sensing system unit (1) receives the sensing information transmitted back by the edge acquisition node (1.1), which includes an energy management acquisition node, a passenger flow detection acquisition node, and a disaster early warning acquisition node;
[0009] S2: transmitting the sensing information in S1 to an edge computing node (1.2), wherein the edge computing node (1.2) adopts a principal component analysis method to perform data dimensionality reduction on the sensing information, that is, projecting a high-dimensional data set onto a low-dimensional space;
[0010] S3: receiving, by a line global information processing unit (2), the sensing information sent by an information sensing system unit (1) in S2, performing processing regularization and data alignment, and then uploading the processed information to a communication adaptive modulation unit (3) for transmission; meanwhile, the line global information processing unit (2) receives a computing task from a vehicle-mounted device unit (6), and issues the computing task to the edge computing node (1.2) according to the deployment status of the edge computing node (1.2);
[0011] S4: performing compression modulation on the information transmitted by the line global information processing unit (2) by the communication adaptive modulation unit (3), including an information transmission strategy and a communication strategy;
[0012] S5: a hierarchical decision-making unit (4), wherein the hierarchical decision-making unit (4) takes resource allocation optimization as a target, and decides to call a single train, multiple trains or integrated resources according to the number of affected trains and a delay time;
[0013] S6: an operation control and dispatching integrated unit (5), which comprehensively considers existing dispatching system information, vehicle-mounted device information, line vehicle information, information system information, plan information and the like, realizes overall management of global information, directly communicates with each system, takes minimum train delay time and energy consumption as a comprehensive optimization target, and performs intelligent adjustment and optimization on a train operation diagram, a train control curve, station route allocation and the like.
[0014] Preferably, the information transmission strategy in S4 is specifically: adjusting a data packet size and switching a transmission mode, and taking a minimum bit error rate and a minimum packet loss rate as targets; the communication strategy is specifically: when a tracking interval dis between trains is smaller than L, selecting a train-to-train communication modulation mode, otherwise, selecting a base station relay mode, considering communication delay and transmission power consumption in a communication process, and completing adaptive selection of a communication mode, wherein a wireless communication distance L and a radio propagation path loss L B are constrained as:
[0015] 20log 10 L=L B -κ-20log 10 f MHZ (1)
[0016] L B =10log(G t G r )P t (dBm)-S(dBm)-Δ (2)
[0017] Where f MHZ It is the communication frequency, κ is the adaptive channel loss constant free space, and G is the communication frequency. t and G r These are the gains of the transmitting and receiving antennas, P and P, respectively. t S and S represent the transmit power and the sensitivity of the receiving antenna, respectively, and Δ represents the loss caused by the communication cable.
[0018] Preferably, the specific steps of hierarchical decision-making in S5 are as follows:
[0019] Event A is designated as 1-2 affected trains, event B as 3-5 affected trains, and event C as 5 or more affected trains.
[0020] The estimated total delay time is 0-10 minutes, which is condition L1; the estimated total delay time is 10-30 minutes, which is condition L2; and the estimated total delay time is more than 30 minutes, which is condition L3.
[0021] When 1-2 trains are affected and the total delay time is expected to be within 10 minutes, that is, when A&L1 occurs, the single-train intelligent adjustment unit (6.1) in the on-board equipment unit (6) is called to perform intelligent adjustment of the single train. The adjustment includes online generation of train operation curve and switching adjustment of train operation conditions.
[0022] When 3-5 trains are affected and the estimated total delay time is less than 10 minutes, or when 1-2 trains are affected and the estimated total delay time is greater than 10 minutes but less than 30 minutes, i.e. when B&L1 or A&L2 occurs, the multi-train coordinated adjustment unit (6.2) is invoked.
[0023] When 1-2 trains are affected and the total delay is expected to be more than 30 minutes, or when 3-5 trains are affected and the total delay is expected to be greater than 10 minutes but less than 30 minutes or more than 30 minutes, or when 5 or more trains are affected, i.e. when A&L3 or B&(L2 or L3) or C occurs, the integrated operation control and dispatching unit (5) is invoked.
[0024] Preferably, the multi-vehicle cooperative adjustment unit (6.2) is based on the train cooperative operation control method of alternating multiplier-model predictive control (ADMM-MPC), specifically: define the state variable of a certain train in the train fleet as x, and the coupled state variable of another train affected by it as y, the coupling relationship between the two is Ax+by-c, and define the optimization target L(x,y) considering evaluation indicators such as tracking error;
[0025] Since adjacent trains can exchange state information in real time, within a model prediction cycle, each train independently calculates and transmits its control strategy under the coupled state equations. Adjacent trains alternately optimize their control strategies based on the Alternating Multiplier Method (ADMM) and proceed to the next iteration. The transformed ADMM optimization problem is:
[0026]
[0027] Where L(x, y, λ) is the transformed ADMM optimization problem, x is the state variable of a train in the platoon, such as speed and position, y is the coupled state variable of another train affected by it, Ax+by-c is the coupling relationship between the two, A, b, and c are the state coupling matrices, λ is the dual variable, and ρ is the penalty parameter.
[0028] In each MPC prediction cycle, adjacent trains perform the following calculations in a distributed and alternating manner:
[0029] x k+1 =argmin x L(x, y) k , λ k (4)
[0030] x k+1 =argmin y L(x k+1 ,y,λ k (5)
[0031] λ k+1 =λ k +ρ(Ax k+1 +by k+1 -c) (6)
[0032] Where k represents the number of iterations, adjacent trains will update the predictive control information and status information, and the cycle continues until the global optimum is reached, and then the next prediction cycle begins.
[0033] The beneficial effects of this invention are as follows:
[0034] By breaking down the hierarchical architecture of scheduling and control, the problem of information and business silos caused by the hierarchical structure of existing scheduling, command and operation control systems is solved. The analysis and design of information flow between systems is carried out to create an adaptive transmission mechanism for information perception results. Through a hierarchical decision-making system, adaptive policy modulation is performed for different degrees of delay. Furthermore, edge computing support is provided to onboard equipment units with insufficient computing power by leveraging the global information processing unit of the line, thereby improving the train operation efficiency under integrated control and scheduling. Attached Figure Description
[0035] Figure 1 A flowchart of an integrated control and scheduling resource allocation decision system provided in an embodiment of the present invention;
[0036] Figure 2 This invention provides an information transmission strategy and communication strategy diagram for an integrated control and scheduling resource allocation decision-making method.
[0037] Figure 3 This invention provides a hierarchical decision graph in an integrated control and scheduling resource allocation decision-making method.
[0038] Figure 4 This is a comparison diagram between the integrated control and scheduling system and the original system in an integrated resource allocation decision-making method for control and scheduling provided in an embodiment of the present invention. Detailed Implementation
[0039] The present invention will be further described below with reference to the accompanying drawings and specific embodiments, so that those skilled in the art can better understand and implement the present invention. The embodiments of the present invention are not limited thereto.
[0040] like Figure 1 As shown, an integrated control and scheduling resource allocation decision system includes: an information sensing system unit 1, a line global information processing unit 2, a communication adaptive modulation unit 3, a hierarchical decision unit 4, an integrated operation control and scheduling unit 5, and an on-board equipment unit 6; wherein, the information sensing system unit 1 includes an edge acquisition node 1.1 and an edge computing node 1.2, and the on-board equipment unit 6 includes a single-vehicle intelligent adjustment unit 6.1 and a multi-vehicle collaborative adjustment unit 6.2.
[0041] A resource allocation decision-making method integrating control and scheduling includes the following steps:
[0042] S1, the information sensing system unit 1 receives the sensing information transmitted back by the edge acquisition node 1.1. The edge acquisition node 1.1 includes an energy management acquisition node, a passenger flow detection acquisition node, and a disaster early warning acquisition node. The edge acquisition node collects information around the line, such as video information collected by cameras, wind speed information collected by wind speed sensors, and sensors for rainfall, snowfall, etc.
[0043] S2 transmits the perceived information from S1 to edge computing node 1.2. Edge computing node 1.2 uses principal component analysis to reduce the dimensionality of the perceived information, that is, to project the high-dimensional dataset onto a low-dimensional space. In this process, the edge computing node performs preliminary calculations on this data to reduce the additional bandwidth consumed by transmitting the relevant collected data to the center.
[0044] S3, the line global information processing unit 2 receives the sensing information sent from the information sensing system unit 1 in S2, processes and regularizes the data and aligns it, and then uploads it to the communication adaptive modulation unit 3 for transmission; at the same time, the line global information processing unit 2 receives the computing task from the vehicle equipment unit 6, and sends the computing task to the edge computing node 1.2 according to the deployment of the edge computing node 1.2.
[0045] S4, the communication adaptive modulation unit 3 performs compression and modulation on the information transmitted from the line global information processing unit 2, including information transmission strategies and communication strategies;
[0046] S5, the hierarchical decision-making unit 4 aims to optimize resource allocation, and determines whether to deploy single-train, multi-train, or integrated resources based on the number of affected trains and the delay time;
[0047] S6, the integrated operation control and dispatching unit 5 comprehensively considers existing dispatching system information, on-board equipment information, line rolling stock, information system information, plan information, etc., to realize overall management of global information, directly communicates with each system, and takes the minimum train delay time and energy consumption as the comprehensive optimization goal to intelligently adjust and optimize the train working diagram, train control curves, station route allocation, etc.
[0048] As Figure 2 shown, the information transmission strategy in S4 is specifically: adjusting the data packet size and switching transmission modes, with the goal of minimizing the bit error rate and packet loss rate; the communication strategy is specifically: when the tracking interval dis between trains is less than L, select the train-to-train communication modulation mode; otherwise, select the base station relay mode. The communication delay and transmission power consumption in the communication process are considered to complete the adaptive selection of the communication mode, where the wireless communication distance L and the radio propagation path loss L B are constrained as:
[0049] 20log 10 L = L B -κ - 20log 10 f MHZ (1)
[0050] L B = 10log(G t G r )P t (dBm) - S(dBm) - Δ (2)
[0051] where f MHZ is the communication frequency, κ is the free-space adaptive channel loss constant, preferably 32.44, G t and G r are the gains of the transmitting and receiving antennas respectively, P t and S are the transmit power and the sensitivity of the receiving antenna respectively, and Δ is the loss caused by the communication cable.
[0052] As Figure 3 shown, the specific steps of hierarchical decision-making in S5 are:
[0053] Specify 1-2 affected trains as event A, 3-5 affected trains as event B, and more than 5 affected trains as event C;
[0054] The estimated total delay time is 0-10 minutes, which is condition L1; the estimated total delay time is 10-30 minutes, which is condition L2; and the estimated total delay time is more than 30 minutes, which is condition L3.
[0055] When 1-2 trains are affected and the total delay time is expected to be within 10 minutes, i.e. when A&L1 occurs, the single-train intelligent adjustment unit 6.1 in the on-board equipment unit 6 is invoked to perform intelligent adjustment of the single train. The adjustment includes online generation of train operation curve and switching adjustment of train operation conditions.
[0056] When 3-5 trains are affected and the estimated total delay time is less than 10 minutes, or when 1-2 trains are affected and the estimated total delay time is greater than 10 minutes but less than 30 minutes, i.e. when B&L1 or A&L2 occurs, the multi-train coordinated adjustment unit 6.2 is invoked.
[0057] When 1-2 trains are affected and the total delay is expected to be more than 30 minutes, or when 3-5 trains are affected and the total delay is expected to be greater than 10 minutes but less than 30 minutes or more than 30 minutes, or when 5 or more trains are affected, i.e. when A&L3 or B&(L2 or L3) or C occurs, the integrated operation control and dispatching unit 5 is invoked.
[0058] like Figure 4 As shown, the layered architecture of the existing system overcomes the information and business silos problem in the dispatching, command and operation control system. The integrated operation and dispatching unit 5 takes into account the existing dispatching system information, on-board equipment information, line and vehicle information, information system information, and planning information, so as to achieve overall information management. It communicates directly with each system and takes minimizing train delay time and energy consumption as the comprehensive optimization goal. It intelligently adjusts and optimizes train timetables, train control curves, station access routes and other aspects.
[0059] In addition, the single-vehicle intelligent adjustment unit 6.1 mainly realizes automatic operation control (ATO) of the speed and position of a single train.
[0060] The multi-vehicle cooperative adjustment unit (6.2) is based on the train cooperative operation control method of alternating multiplier-model predictive control (ADMM-MPC). Specifically, the state variable of a certain train in the train fleet is defined as x, and the coupled state variable of another train affected by it is y. The coupling relationship between the two is Ax+by-c. Considering the evaluation index such as tracking error, the optimization target L(x,y) is defined.
[0061] Since adjacent trains can exchange state information in real time, within a model prediction cycle, each train independently calculates and transmits its control strategy under the coupled state equations. Adjacent trains alternately optimize their control strategies based on the Alternating Multiplier Method (ADMM) and proceed to the next iteration. The transformed ADMM optimization problem is:
[0062]
[0063] Where L(x, y, λ) is the transformed ADMM optimization problem, x is the state variable of a train in the platoon, such as speed and position, y is the coupled state variable of another train affected by it, Ax+by-c is the coupling relationship between the two, A, b, and c are the state coupling matrices, λ is the dual variable, and ρ is the penalty parameter.
[0064] In each MPC prediction cycle, adjacent trains perform the following calculations in a distributed and alternating manner:
[0065] x k+1 =argmin x L(x, y) k , λ k (4)
[0066] x k+1 =argmin y L(x k+1 ,y,λ k (5)
[0067] λ k+1 =λ k +ρ(Ax k+1 +by k+1 -c) (6)
[0068] Where k represents the number of iterations. Adjacent trains will update their predictive control information and status information, repeating this process until the global optimum is reached, at which point the next prediction cycle begins.
[0069] Those skilled in the art will understand that the accompanying drawings are merely schematic diagrams of one embodiment, and the processes depicted in the drawings are not necessarily essential for implementing the present invention.
Claims
1. A resource allocation decision-making system integrating control and scheduling, characterized in that, include: The information sensing system unit (1) receives sensing information transmitted back from the edge acquisition node (1.1), which includes an energy management acquisition node, a passenger flow detection acquisition node, and a disaster early warning acquisition node; and transmits the sensing information to the edge computing node (1.2). The edge computing node (1.2) uses principal component analysis to reduce the dimensionality of the sensing information, that is, to project the high-dimensional dataset onto a low-dimensional space. The line global information processing unit (2) receives the sensing information sent by the information sensing system unit (1), processes and regularizes the data and aligns it, and then uploads it to the communication adaptive modulation unit (3) for transmission; at the same time, the line global information processing unit (2) receives the computing task from the vehicle equipment unit (6) and sends the computing task to the edge computing node (1.2) according to the deployment of the edge computing node (1.2); The communication adaptive modulation unit (3) is used to receive and transmit the information uploaded by the line global information processing unit (2); The hierarchical decision-making unit (4) aims to optimize resource allocation and decides to call up single, multiple, or integrated resources based on the number of trains affected and the delay time. The integrated operation and control unit (5) takes into account the existing dispatch system information, on-board equipment information, line vehicles, information system information, and plan information to achieve overall information management. It communicates directly with each system and takes the minimum train delay time and energy consumption as the comprehensive optimization goal. It intelligently adjusts and optimizes the train operation diagram, train control curve, and station access route. Vehicle-mounted equipment unit (6); Among them, the information perception system unit (1) includes an edge acquisition node (1.1) and an edge computing node (1.2), and the vehicle equipment unit (6) includes a single vehicle intelligent adjustment unit (6.1) and a multi-vehicle collaborative adjustment unit (6.2).
2. A resource allocation decision-making method integrating control and scheduling, characterized in that, Includes the following steps: S1, the information sensing system unit (1) receives the sensing information transmitted back by the edge acquisition node (1.1), which includes an energy management acquisition node, a passenger flow detection acquisition node, and a disaster early warning acquisition node; S2 transmits the perceived information from S1 to the edge computing node (1.2). The edge computing node (1.2) uses principal component analysis to reduce the dimensionality of the perceived information, that is, to project the high-dimensional dataset onto the low-dimensional space. S3, the line global information processing unit (2) receives the sensing information sent from the information sensing system unit (1) in S2, processes and regularizes the data and aligns it, and then uploads it to the communication adaptive modulation unit (3) for transmission; at the same time, the line global information processing unit (2) receives the computing task from the vehicle equipment unit (6), and sends the computing task to the edge computing node (1.2) according to the deployment of the edge computing node (1.2); S4, the communication adaptive modulation unit (3) compresses and modulates the information transmitted from the line global information processing unit (2), including information transmission strategy and communication strategy; S5, Hierarchical Decision Unit (4), the hierarchical decision unit (4) aims at optimizing resource allocation and decides to call up single, multiple or integrated resources based on the number of trains affected and the delay time; S6, Operation Control and Dispatch Integrated Unit (5) takes into account the existing dispatch system information, on-board equipment information, line vehicles, information system information, and plan information to achieve overall information management. It communicates directly with each system and takes the minimum train delay time and energy consumption as the comprehensive optimization goal. It intelligently adjusts and optimizes the train operation diagram, train control curve, and station access route.
3. The integrated control and scheduling resource allocation decision-making method according to claim 2, characterized in that, The specific information transmission strategy in S4 is to adjust the data packet size and switch the transmission mode, with the goal of minimizing the bit error rate and the packet loss rate. The communication strategy is specifically as follows: when the train tracking interval dis < L, the train-to-train communication modulation mode is selected; otherwise, the base station relay mode is selected. The communication delay and transmission power consumption during the communication process are considered to complete the adaptive selection of the communication mode, where the wireless communication distance L and the radio propagation path loss are constrained as: (1) (2) in It is a communication frequency. For the adaptive channel loss constant free space, and These are the gains of the transmitting and receiving antennas, respectively. and These are the transmit power and the sensitivity of the receiving antenna, respectively. The losses caused by communication cables.
4. The integrated control and scheduling resource allocation decision-making method according to claim 2, characterized in that, The specific steps of hierarchical decision-making in S5 are as follows: Event A is designated as 1-2 affected trains, event B as 3-5 affected trains, and event C as 5 or more affected trains. The estimated total delay time is 0-10 minutes, which is condition L1; the estimated total delay time is 10-30 minutes, which is condition L2; and the estimated total delay time is more than 30 minutes, which is condition L3. When 1-2 trains are affected and the total delay time is expected to be within 10 minutes, that is, when A&L1 occurs, the single-train intelligent adjustment unit (6.1) in the on-board equipment unit (6) is called to perform intelligent adjustment of the single train. The adjustment includes online generation of train operation curve and switching adjustment of train operation conditions. When 3-5 trains are affected and the estimated total delay time is less than 10 minutes, or when 1-2 trains are affected and the estimated total delay time is greater than 10 minutes but less than 30 minutes, i.e. when B&L1 or A&L2 occurs, the multi-train coordinated adjustment unit (6.2) is invoked. When 1-2 trains are affected and the total delay is expected to be more than 30 minutes, or when 3-5 trains are affected and the total delay is expected to be greater than 10 minutes but less than 30 minutes or more than 30 minutes, or when more than 5 trains are affected, i.e. when A&L3 or B& (L2 or L3) or C occurs, the integrated operation control and dispatching unit (5) is invoked.
5. The integrated control and scheduling resource allocation decision-making method according to claim 4, characterized in that, The multi-train coordinated adjustment unit (6.2) is based on the train coordinated operation control method of alternating multiplier-model predictive control (ADMM-MPC), specifically: defining the state variable of a certain train in the train fleet as... Another coupled state variable of the train affected by it is The coupling relationship between the two is Considering the tracking error evaluation index, define the optimization objective. ; Since adjacent trains can exchange state information in real time, within a model prediction cycle, each train independently calculates and transmits its control strategy under the coupled state equations. Adjacent trains alternately optimize their control strategies based on the Alternating Multiplier Method (ADMM) and proceed to the next iteration. The transformed ADMM optimization problem is: (3) in The optimization problem for the transformed ADMM. Let the speed and position state variables be those of a specific train within the convoy. For another train affected by it, To illustrate the coupling relationship between the two, A, b, and c are the state coupling matrices, respectively. As dual variables, For penalty parameters; In each MPC prediction cycle, adjacent trains perform the following calculations in a distributed and alternating manner: (4) (5) (6) Where k represents the number of iterations, adjacent trains will update the predictive control information and status information, and the cycle continues until the global optimum is reached, and then the next prediction cycle begins.