Installation structure of tower crane and self-unloading counterweight

By installing a self-unloading counterweight and a graded locking mechanism on the tower crane, and using a trigger device to release the counterweight, the problem of the tower crane tipping over under sudden unloading is solved, achieving precise control of the crane boom and reducing the risk of tipping over.

CN115557405BActive Publication Date: 2026-11-20HUNAN ZOOMLION CONSTR HOISTING MASCH CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202211125175.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-09-15
Publication Date
2026-11-20
Estimated Expiration
2042-09-15

AI Technical Summary

Technical Problem

Existing tower cranes are prone to overturning accidents under sudden unloading conditions, and traditional methods of strengthening the structure and adjusting the mass distribution are insufficient to meet the overturning resistance requirements of ultra-large cranes.

Method used

Design a tower crane that precisely suppresses the upward movement of the boom by installing a self-unloading counterweight and a graded locking mechanism on the boom and using a triggering device to release a corresponding number of counterweights when the load torque changes.

Benefits of technology

It effectively reduces the risk of crane overturning due to instantaneous load changes, reduces the bending moment impact on the tower body, and improves the anti-overturning performance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115557405B_ABST
    Figure CN115557405B_ABST
Patent Text Reader

Abstract

The present application relates to the field of hoisting equipment, and discloses a tower crane and a mounting structure of self-unloading counterweight, wherein the self-unloading counterweight (4) fixed to the mounting position through a self-unloading locking mechanism (3) and a hierarchical locking mechanism (9) is mounted on the counterweight arm of the tower crane, the self-unloading counterweight (4) comprises a plurality of counterweights (4a), the hierarchical locking mechanism (9) is arranged to release the locking of the corresponding counterweight (4a) according to the load torque of the hoisting arm (23), and the self-unloading locking mechanism (3) can be triggered by a triggering device to release the self-unloading counterweight (4) and make the corresponding counterweight (4a) released by the hierarchical locking mechanism (9) fall off from the mounting position when the hoisting arm is raised. The tower crane can mechanically trigger the release of the corresponding number of counterweights on the counterweight arm according to the load torque when the hoisting arm is raised relative to the tower body, so as to reduce the risk of overturning accidents by accurately suppressing the raising of the hoisting arm.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to lifting equipment, and more specifically to a tower crane. Furthermore, this invention also relates to an installation structure for a self-unloading counterweight. Background Technology

[0002] In industrial production and construction, various types of cranes are often used to vertically lift and horizontally move heavy objects within a certain range. For example, tower cranes (also known as "tower cranes") have tall towers and are widely used in the construction of buildings, bridges, wind power, ports, and nuclear power plants. With the trend of large-scale, modular, and intensive development of construction projects, there is a demand for ultra-large tower cranes. Ultra-large tower cranes are characterized by high operating height, large lifting capacity, and long operating radius. Compared with ordinary tower cranes, they are more expensive and larger in size, thus significantly increasing property damage and secondary damage caused by overturning accidents.

[0003] In response, traditional tower cranes typically improve their anti-overturning performance by enhancing the overall and local structural strength of the tower or adjusting the mass distribution. Other types of cranes also improve their anti-overturning performance through similar technical means.

[0004] However, as the load increases, this method is difficult to meet the anti-overturning performance requirements of ultra-large cranes. Especially in the case of sudden unloading such as the wire rope of the suspended load breaking, the instantaneous load on the boom changes drastically, which will generate huge bending moment impact on the installation foundation of the boom (such as the tower body of the tower crane). Simply relying on strengthening the structural strength and adjusting the mass distribution is difficult to prevent the crane from overturning. Summary of the Invention

[0005] The purpose of this invention is to overcome the problem that tower cranes in the prior art are prone to overturning accidents when suddenly unloaded, and to provide a tower crane that can mechanically trigger the release of a corresponding number of counterweights on the counterweight arm according to the load torque when the jib rises relative to the tower body, so as to reduce the risk of overturning accidents by precisely suppressing the upward movement of the jib.

[0006] To achieve the above objectives, the present invention provides a tower crane, comprising:

[0007] Tower body;

[0008] A boom, hinged to the top of the tower via a hinge shaft, includes a counterweight extending from the hinged position to one side of the tower and a lifting boom extending to the opposite side. The counterweight is equipped with a self-unloading counterweight fixed in position by a self-unloading locking mechanism and a tiered locking mechanism. The self-unloading counterweight includes multiple counterweights. The tiered locking mechanism is configured to release the locking of a corresponding counterweight based on the load torque of the lifting boom.

[0009] A triggering device, connected to the tower body, allows the boom to rotate relative to the tower body about the hinge axis when the lifting torque of the boom suddenly decreases, causing the boom to rise relative to the tower body. This triggers the self-unloading locking mechanism to release the self-unloading counterweight and causes the corresponding counterweight, which has been unlocked by the graded locking mechanism, to fall off from the installation position.

[0010] Preferably, the self-unloading locking mechanism includes a load-bearing beam and a support mechanism respectively hinged to the counterweight arm, wherein the load-bearing beam is supported by the support mechanism to hold the self-unloading counterweight in the installation position.

[0011] Preferably, the triggering device includes a pulling mechanism, which includes a pivot plate hinged to the boom and having a first fulcrum and a second fulcrum, a first tie rod with both ends connected to the first fulcrum and the tower body respectively, and a second tie rod with both ends connected to the second fulcrum and the support mechanism respectively. When the boom rotates relative to the tower body to raise the jib relative to the tower body, the pulling mechanism pulls the support mechanism to rotate relative to the bearing beam about its hinge axis with the boom until it is disengaged from the bearing beam, so that the self-unloading counterweight falls freely from the bearing beam.

[0012] Preferably, the pivot plate is formed as a sector-shaped plate, and the boom is hinged to the central corner of the sector-shaped plate, with the first fulcrum and the second fulcrum located at the other two corners respectively; or, the pivot plate is formed as a triangular plate, and the boom is hinged to one corner of the triangular plate, with the first fulcrum and the second fulcrum located at the other two corners respectively.

[0013] Preferably, the second tie rod comprises a plurality of tie rod sections connected in sequence, wherein adjacent tie rod sections are detachably connected to each other and / or connected such that the second tie rod is flexible at the connection position.

[0014] Preferably, the boom includes a connecting arm that connects the counterweight boom and the lifting boom, the hinge shaft is disposed on the lower side of the connecting arm, and the pivot plate is hinged to the center position of the connecting arm.

[0015] Preferably, the triggering device includes a pulling mechanism, which includes a fixed support fixed to the top of the tower body and a third pull rod connected between the fixed support and the support mechanism, the third pull rod being connected to the fixed support via a flexible rope.

[0016] Preferably, one of the load-bearing beam and the support mechanism has a groove, and the other has a spherical surface that mates with the groove, so that the spherical surface can be dislodged from the groove and removed from the position supporting the load-bearing beam by rotating the support mechanism.

[0017] Preferably, the boom and the load-bearing beam extend horizontally, and the support mechanism is hinged to the bottom beam of the boom. When supporting the load-bearing beam, the angle between the support mechanism and the load-bearing beam toward the side of the self-unloading counterweight is greater than 90°.

[0018] Preferably, the tower crane further includes a damping device for reducing the relative rotational speed of the jib and the tower body, which is hinged at both ends to the tower body and the boom respectively, or a self-locking device for locking the jib in the extreme upward position.

[0019] Preferably, the graded locking mechanism includes an electrically controlled or hydraulic pin that is mounted to the counterweight arm and extends to prevent the counterweight from falling off the mounting position. The electrically controlled or hydraulic pin retracts sequentially according to the change in the load torque of the crane arm to release the locking of the corresponding counterweight.

[0020] A second aspect of the present invention provides an installation structure for a self-unloading counterweight, including a boom and a self-unloading counterweight fixed to an installation position by a self-unloading locking mechanism and a tiered locking mechanism. The self-unloading counterweight includes a plurality of counterweights, and the tiered locking mechanism is configured to selectively release the locking of different numbers of the counterweights, so as to allow the self-unloading locking mechanism to be triggered so that the released counterweights fall off from the installation position.

[0021] Preferably, the self-unloading locking mechanism includes a load-bearing beam and a support mechanism respectively hinged to the boom, wherein the load-bearing beam is supported by the support mechanism to hold the self-unloading counterweight in the installation position.

[0022] Preferably, the graded locking mechanism includes a plurality of electrically controlled or hydraulic pins mounted to the boom and extending to prevent the counterweights from falling off the mounting position. The electrically controlled or hydraulic pins can be driven to selectively retract from the extended position to release the locking of the corresponding counterweights.

[0023] Through the above technical solution, the tower crane of the present invention can release the locking of the corresponding counterweight by the graded locking mechanism according to the load torque during the lifting process, and allow the boom to rotate relative to the tower body around the hinge axis in the event of sudden unloading of the boom. Then, the self-unloading locking mechanism is triggered by the triggering device to release the self-unloading counterweight, thereby causing the counterweight that has been released by the graded locking mechanism to fall off, so as to accurately suppress the upward movement of the boom caused by the sudden change of instantaneous load, thereby reducing or avoiding the bending moment impact on the tower body and effectively reducing the risk of overturning accidents. Attached Figure Description

[0024] Figure 1 This is a structural schematic diagram of a tower crane according to a preferred embodiment of the present invention;

[0025] Figure 2 It is Figure 1 An enlarged view showing the crane boom after it has been cut off;

[0026] Figure 3 This is a schematic diagram showing what happens after the crane boom suddenly unloads.

[0027] Figure 4 It is Figure 3 An enlarged view showing the crane boom after it has been cut off;

[0028] Figure 5 yes Figure 1 A schematic diagram of the triggering device of a medium-sized tower crane;

[0029] Figure 6 This is a schematic diagram of a structure that uses a self-unloading locking mechanism to fix the self-unloading counterweight in the installation position.

[0030] Figure 7 This is a schematic diagram of a structure that uses a self-unloading locking mechanism and a graded locking mechanism to fix the self-unloading counterweight in the installation position.

[0031] Figure 8 yes Figure 7 A top view of the fixed structure, with one of the electrically or hydraulically controlled pins in the unlocked position;

[0032] Figure 9 A schematic diagram of a tower crane according to another preferred embodiment of the present invention, wherein the boom is truncated for clearer display.

[0033] Explanation of reference numerals in the attached figures

[0034] 1-Tower body; 1a-Fixed support; 2-Boom; 21-Counter boom; 22-Connecting boom; 22a-Hinged shaft; 22b-Support shaft; 23-Lifting boom; 3-Self-unloading locking mechanism; 31-Bearing beam; 32-Supporting mechanism; 4-Self-unloading counterweight; 4a-Counterweight; 5-First tie rod; 6-Pivot plate; 7-Second tie rod; 8-Damping device; 9-Graded locking mechanism; 10-Fixed support; 11-Third tie rod; 12-Flexible rope; 13-Electrically controlled or hydraulic pin. Detailed Implementation

[0035] The specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are for illustration and explanation only and are not intended to limit the present invention.

[0036] Reference Figures 1 to 4 As shown, a tower crane according to a preferred embodiment of the present invention includes a tower body 1 and a boom 2 connected to the top of the tower body 1. The boom 2 is hinged to the tower body 1 via a hinge shaft 22a and includes a counterweight 21 extending from the hinge position to one side of the tower body 1 and a lifting boom 23 extending to the opposite side. The lifting boom 23 may be equipped with a sling assembly, such as a wire rope or a hook, for connecting to the load being lifted. A self-unloading counterweight 4 is installed on the counterweight 21, and the self-unloading counterweight 4 is fixed in the installation position by a self-unloading locking mechanism 3. When the lifting boom 23 is suddenly unloaded due to failure of the connection between the sling assembly and the load being lifted, or breakage of the wire rope, the instantaneous load on the lifting boom 23 changes drastically, thereby causing the boom 2 to rotate about its hinge shaft 22a with the tower body 1, resulting in the lifting boom 23 rising. Therefore, the tower crane of the present invention also includes a triggering device connected to the tower body 1, which can trigger the self-unloading locking mechanism 3 to release the self-unloading counterweight 4 during the upward movement of the boom 23 relative to the tower body 1, so as to suppress the upward movement of the boom 23.

[0037] Combination Figure 7 and Figure 8 As shown, the self-unloading counterweight 4 includes multiple counterweights 4a, which are simultaneously locked in their installation positions by a tiered locking mechanism 9. This tiered locking mechanism 9 can release the locking of the corresponding counterweight 4a according to the load torque of the boom 23, so that the total weight of these counterweights 4a matches the current load torque. When the triggering device triggers the self-unloading locking mechanism 3 to release the self-unloading counterweight 4, only the counterweight 4a unlocked by the tiered locking mechanism 9 detaches from the boom 21, while the remaining counterweights 4a (if any) remain on the boom 21. This precisely suppresses the upward movement of the boom caused by drastic changes in instantaneous load, thereby reducing or avoiding bending moment impact on the tower and effectively reducing the risk of overturning accidents.

[0038] Triggering device

[0039] In the tower crane of the present invention, the triggering device can trigger the self-unloading locking mechanism 3 to release the self-unloading counterweight 4 after the lifting boom 23 rises, so as to allow the self-unloading counterweight 4 to detach from the counterweight boom 21. Specifically, as Figure 5 As shown, in a preferred embodiment of the present invention, the triggering device includes a pulling mechanism, which includes a pivot plate 6 hinged to the boom 2. The pivot plate 6 has a first fulcrum and a second fulcrum. The first fulcrum is connected to the tower body 1 via a first tie rod 5, and the second fulcrum is driven to the self-unloading locking mechanism 3. In the event of a sudden unloading of the hoisting assembly, the boom 2 can rotate relative to the tower body 1 around the hinge axis 22a, causing the boom 23 to rise relative to the tower body 1. Under the action of the first tie rod 5, the pivot plate 6 remains stationary relative to the tower body 1. At the same time, the self-unloading locking mechanism 3 moves relative to the pivot plate 6 as the boom 2 rotates. Thus, under the linkage action of the pivot plate 6, the self-unloading locking mechanism 3 can be triggered by pulling, causing it to release the self-unloading counterweight 4 on the balance arm 21. This can suppress the upward movement of the boom 2 caused by drastic changes in instantaneous load, thereby reducing or avoiding the bending moment impact on the tower body 1 and effectively reducing the risk of overturning accidents.

[0040] The second fulcrum of the pivot plate 6 can be driven to the self-unloading locking mechanism 3 in various ways to apply a pulling force to the self-unloading locking mechanism 3. In the illustrated preferred embodiment, the second fulcrum of the pivot plate 6 is hinged to a second tie rod 7, which extends along the counterweight arm 21 and is driven to the self-unloading locking mechanism 3 (e.g., hinged to the support mechanism 32 of the self-unloading locking mechanism 3, as described later). Since the position of the self-unloading locking mechanism 3 changes during the rotation of the boom 2 relative to the tower body 1, the extension path of the second tie rod 7 also changes accordingly. Therefore, in addition to hinged both ends of the second tie rod 7 to the pivot plate 6 and the self-unloading locking mechanism 3 respectively, the second tie rod 7 can also be made flexible to adapt to the movement of the boom 2. For example, the second tie rod 7 can be configured to include multiple tie rod sections connected in sequence to allow the second tie rod 7 to bend at the connection position. In addition, the multiple tie rod sections can also be configured to be detachably connected to each other.

[0041] Under normal operating conditions, the extension directions of the boom 2 and the tower 1 are typically arranged perpendicular to each other. However, the self-unloading triggering device of this invention requires the tower 1 as the traction base to trigger the self-unloading locking mechanism 3 on the boom 2. Therefore, a pivot plate 6 hinged to the boom 2 is needed to change the direction of the tension transmission. In the self-unloading triggering device provided by this invention, the pivot plate 6 can be formed as a triangular plate and hinged to the boom 2 at one corner. The other two corners are provided with a first fulcrum connecting the first tie rod 5 and a second fulcrum connecting the second tie rod 7. By setting the hinge point, the first fulcrum, and the second fulcrum alternately, the tension applied to the pivot plate 6 by the first tie rod 5 can cause the pivot plate 6 to rotate relative to the boom 2 around the hinge point or have a tendency to rotate relative to it. This allows a tension along the extension direction of the boom 2 to be applied to the second tie rod 7, thereby triggering the self-unloading locking mechanism 3 to release the self-unloading counterweight 4 when the boom 2 rotates relative to the tower 1.

[0042] In another preferred embodiment, the pivot plate 6 can also be formed as a fan-shaped plate, which can be hinged to the boom 2 at its central corner position, and a first fulcrum and a second fulcrum are set at two other corners near the top of the arc, which can also transmit the pulling force through the first tie rod 5 and the second tie rod 7 to trigger the self-unloading locking mechanism 3.

[0043] It should be understood that in the event of a sudden unloading, the boom 2 rotates relative to the tower body 1 as a whole, causing the lifting boom 23 to rise. Therefore, the counterweight boom 21 and lifting boom 23 described in this invention are only distinguished by different extensions of the boom 2 relative to the tower body 1 for clarity of explanation, and they are connected as a whole (i.e., the boom 2 can be an integral truss structure). Therefore, the boom 2 also includes a connecting arm 22 connecting the counterweight boom 21 and the lifting boom 23, and a hinge shaft 22a for hinged to the tower body 1 can be provided on the lower side of the connecting arm 22.

[0044] To avoid interference with the hoisting wire rope and other related components, the pivot plate 6 can be hinged to the center position of the connecting arm 22. The center position of the connecting arm 22 mentioned here refers to the center position of the connecting arm 22 in the extension direction and the height direction. For example, for a boom 2 with a rectangular cross-section, a pair of pivot plates 6 can be provided on two truss planes in its vertical direction, and connected to the self-unloading locking mechanism 3 through corresponding second tie rods 7.

[0045] Under normal operating conditions, the tower body 1 bears the pressure of the boom 2, thus requiring sufficient support for the boom 2. For this purpose, a support shaft 22b can be provided on the lower side of the end of the connecting arm 22 that connects to the lifting arm 23, and the boom 2 is supported on the top of the tower body 1 by the support shaft 22b.

[0046] As construction progresses, the height of tower 1 will be increased by adding standard sections, which typically requires a fixed support 1a at the top of tower 1 to connect to the boom 2. This fixed support 1a may have a groove for supporting 22b, which can limit the extension of the boom 2. In this case, the first tie rod 5 can also be connected to the fixed support 1a at its bottom end, so that its connection to tower 1 does not need to be adjusted during construction.

[0047] Figure 9 Another preferred embodiment of the tower crane shown has a triggering device with a different structural form, which includes a fixed support 10 fixed to the top of the tower body 1 and a traction mechanism connected between the fixed support 10 and the self-unloading locking mechanism 3. The fixed support 5 and the traction mechanism can trigger the self-unloading locking mechanism 3 to release the self-unloading counterweight 4 after the boom 23 is raised, so as to allow the self-unloading counterweight 4 to fall off the counterweight boom 21.

[0048] Specifically, in a preferred embodiment of the present invention, the pulling mechanism includes a third pull rod 11 hinged to the self-unloading locking mechanism 3 (the support mechanism 32). The third pull rod 11 extends along the extension direction of the balance arm 23 and is connected at the other end to the fixed support 10 via a flexible rope 12, such as a steel wire rope. Thus, under the linkage action of the pulling mechanism, the self-unloading locking mechanism 3 can be triggered by pulling, causing it to release the self-unloading counterweight 4 on the balance arm 21. This can suppress the upward movement of the boom 2 caused by the drastic change in instantaneous load, thereby reducing or avoiding the bending moment impact on the tower body 1 and effectively reducing the risk of overturning accidents.

[0049] Under normal operating conditions, the extension directions of the boom 2 and the tower 1 are typically arranged perpendicular to each other. However, the self-unloading triggering device of this invention requires the tower 1 as the traction base to trigger the self-unloading locking mechanism 3 on the boom 2. Therefore, a pulling mechanism is needed to change the direction of the tension transmission. By making the third tie rod 11 flexible and connecting it to the fixed support 10 using a flexible rope 12, a tension along the extension direction of the boom 2 is applied to the self-unloading locking mechanism 3. This allows the self-unloading locking mechanism 3 to be triggered to release the self-unloading counterweight 4 when the boom 2 rotates relative to the tower 1.

[0050] Installation structure of self-unloading counterweight

[0051] In the tower crane of the present invention, the self-unloading counterweight 4 can be released after the lifting boom 23 is raised, so as to detach from the counterweight boom 21. The self-unloading counterweight 4 is fixed in the installation position by a self-unloading locking mechanism 3, wherein, as... Figure 6As shown, the self-unloading locking mechanism 3 may include a load-bearing beam 31 and a support mechanism 32. One end of the support mechanism 32 is hinged to the boom 2, and the other end supports the load-bearing beam 31, so that the self-unloading counterweight 4 can be held on the boom 2 by the load-bearing beam 31. The support mechanism 32 is arranged to be driven to rotate about its hinge axis with the boom 2 until the load-bearing beam 31 is disengaged from the supported state, thereby allowing the self-unloading counterweight 4 to fall freely from the load-bearing beam 31. When the tower crane suddenly unloads due to failure of the connection between the hoisting assembly and the hoisted load, wire rope breakage, etc., the boom 2 can rotate about its hinge axis 22a with the tower body 1, causing the boom 2 to rise. During the upward movement of the boom 2, the support mechanism 32 is triggered to rotate around its hinge axis with the boom 2 until the load-bearing beam 31 is disengaged from the supported state, thereby allowing the self-unloading counterweight 4 to fall freely from the load-bearing beam 31. This can suppress the upward movement of the boom 2 caused by the drastic change in instantaneous load, thereby reducing or avoiding the bending moment impact on the tower body 1 and effectively reducing the risk of overturning accidents.

[0052] The supporting beam 31 and the supporting mechanism 32 are connected by a spherical surface and a groove. For example, a groove is provided on the supporting beam 31, and correspondingly, the end of the supporting mechanism 32 is designed as a spherical surface, so that the spherical end of the supporting mechanism 32 is located in the groove on the supporting beam 31, thereby supporting the supporting beam 31. When the supporting mechanism 32 is driven to rotate a certain angle, the spherical surface disengages from the groove, thereby causing the supporting mechanism 32 to move away from the position supporting the supporting beam 31. This allows the supporting beam 31 to rotate downwards around its hinge point with the balance arm 21, releasing the self-unloading counterweight. 4. This allows the self-unloading counterweight 4 to detach from the balance arm 21; alternatively, the bearing beam 31 can be formed into a spherical shape, and the end of the support mechanism 32 can be designed as a groove, with the spherical surface located in the groove. The support mechanism 32 supports the bearing beam 31 through the groove. When the support mechanism 32 is driven to rotate a certain angle, the spherical surface is dislodged from the groove, thereby causing the support mechanism 32 to disengage from the position supporting the bearing beam 31. This causes the bearing beam 31 to rotate downwards around its hinge point with the balance arm 21, releasing the self-unloading counterweight 4, so that the self-unloading counterweight 4 detaches from the balance arm 21.

[0053] The load-bearing beam 31 and the support mechanism 32 constitute a self-unloading locking mechanism 3. The self-unloading locking mechanism 3 is connected to the transmission mechanism. After the lifting arm 23 is raised, the transmission mechanism triggers the self-unloading locking mechanism 3 to release the self-unloading counterweight 4, causing the self-unloading counterweight 4 to detach from the counterweight arm 21. The self-unloading counterweight 4 is held on the counterweight arm 21 by the load-bearing beam 31. One end of the load-bearing beam 31 is hinged to the counterweight arm 21, and the other end is supported by the support mechanism 32, which is hinged to the counterweight arm 21. The support mechanism 32 is connected to the transmission mechanism, which can be pulled to apply a pulling force away from the direction of the self-unloading counterweight 4, so that the support mechanism 32 disengages from the position supporting the load-bearing beam 31.

[0054] Under normal working conditions, refer to Figure 1 and Figure 6 As shown, the extension directions of the boom 2 and the tower 1 are typically arranged perpendicular to each other. The boom 2 extends horizontally, and correspondingly, the supporting beam 31 also extends horizontally. The support mechanism 32 is hinged to the bottom beam of the boom 2. When supporting the supporting beam 31, the angle between the support mechanism 32 and the supporting beam 31 on the side facing the self-unloading counterweight 4 is greater than 90°. The transmission mechanism of the present invention requires the tower 1 as the traction base to trigger the self-unloading locking mechanism 3 on the boom 2. Thus, the direction of tension transmission can be changed by the aforementioned pivot plate 6 hinged to the boom 2.

[0055] Graded locking mechanism

[0056] The self-unloading counterbalance 4 includes multiple counterweights 4a, each of which may be equipped with lifting lugs. A tiered locking mechanism 9 includes multiple electrically controlled or hydraulic pins 13 mounted on the boom 2 and extending out to insert into the lifting lugs to prevent the corresponding counterweights 4a from detaching. During lifting operations by the boom 2, the tiered locking mechanism 9 is controlled to extend or retract the corresponding electrically controlled or hydraulic pins 13, thereby allowing a corresponding number of counterweights 4a, matched to the current load torque, to detach from the boom 2, thus relatively precisely suppressing the upward movement of the boom.

[0057] Based on the above-mentioned triggering device and self-unloading counterweight installation structure, the tower crane of the present invention can be configured to hinge the two ends of the second tie rod 7 to the second fulcrum of the pivot plate 6 and the support mechanism 32 of the self-unloading locking mechanism 3 respectively, or hinge the third tie rod 11 to the support mechanism 32. When the boom 2 rotates relative to the tower body 1 so that the lifting boom 23 rises relative to the tower body 1, the relative movement between the boom 2 and the tower body 1 is used to trigger the support mechanism 32 to rotate relative to the bearing beam 31 around its hinge axis with the boom 2 until it is disengaged from the position supporting the bearing beam 31, so that the self-unloading counterweight 4 can fall freely from the bearing beam 31.

[0058] The tower crane of the present invention can utilize a self-unloading triggering device to release the self-unloading counterweight on the balance arm, thereby suppressing the upward movement of the boom. The upward movement and repositioning of the boom only allow for the conversion between kinetic energy and gravitational potential energy, and this energy must always be transferred to the tower body or consumed during the upward movement. Therefore, in the event of sudden unloading of the boom, the upward movement and repositioning of the boom can be effectively controlled, thereby reducing the impact on the tower body and preventing the tower crane from overturning. For this purpose, a damping device 8 or a self-locking device can be connected between the tower body 1 and the boom 23 to reduce the relative rotational speed between the boom 23 and the tower body 1, or to lock the boom 23 at its maximum upward position. This effectively supports the boom when it reaches its maximum upward position, preventing it from freely repositioning, thus allowing the boom's kinetic energy to be converted into gravitational potential energy and maintained, avoiding the impact on the tower body caused by the boom repositioning, and effectively preventing overturning accidents. Typically, the damping device 8 or the self-locking device can be configured as a hydraulic component (such as a damping cylinder) and can support the boom 23 at its extreme upward position through hydraulic pressure. By controlling the pull-out damping and the push-out damping of the damping cylinder, the boom 23 can be controlled to rise and reset in the event of sudden unloading, which has a high degree of safety.

[0059] Another aspect of the present invention provides a self-unloading counterweight installation structure, which can be used in a tower crane to allow a corresponding number of counterweights 4a to detach from the counterweight boom according to the load torque when the boom is suddenly unloaded. Specifically, see... Figure 7 and Figure 8 As shown, the installation structure includes a self-unloading counterweight 4 fixed to the installation position by a self-unloading locking mechanism 3 and a tiered locking mechanism 9. The self-unloading counterweight 4 includes multiple counterweights 4a. Thus, in the initial installation state, each counterweight 4a of the self-unloading counterweight 4 is not only held in the installation position by the self-unloading locking mechanism 3, but also locked by the tiered locking mechanism 9. When the crane boom is lifting a load, the load torque changes according to the load weight and the position of the boom. Therefore, the tiered locking mechanism 9 is controlled to release the locking of a corresponding number of counterweights 4a, so that the total weight of the counterweights 4a that are allowed to fall off matches the current load torque. When the crane boom is suddenly unloaded due to wire rope breakage or other reasons, as the crane boom rises to the predetermined position, the self-unloading locking mechanism 3 releases its fixing effect on the self-unloading counterweight 4, and the counterweights 4a that have been released from locking by the tiered locking mechanism 9 fall off the counterweight boom. The remaining counterweights (if any) are still held in the installation position by the tiered locking mechanism 9.

[0060] The specific structure and triggering method of the self-unloading locking mechanism 3 can be the structure described above, and it is triggered using the aforementioned triggering device, which will not be repeated here. The graded locking mechanism 9 can control different balance blocks 4a in a graded manner through an appropriate method. In the preferred embodiment shown in the figure, the balance block 4a is provided with a lifting lug, and the graded locking mechanism 9 includes a plurality of electrically controlled or hydraulic pins 13 installed on the boom 2 and extending out to be inserted into the lifting lug, so as to prevent the corresponding balance block 4a from falling off. During the lifting process of the boom 2, the graded locking mechanism 9 is controlled to cause the corresponding electrically controlled or hydraulic pins 13 to extend or retract, thereby allowing a corresponding number of balance blocks 4a matched with the current load torque to fall off the boom 2, so as to relatively accurately suppress the upward movement of the boom.

[0061] The preferred embodiments of the present invention have been described in detail above with reference to the accompanying drawings; however, the present invention is not limited thereto. Within the scope of the inventive concept, various simple modifications can be made to the technical solutions of the present invention, including combinations of various specific technical features in any suitable manner. To avoid unnecessary repetition, the present invention will not describe the various possible combinations separately. However, these simple modifications and combinations should also be considered as the content disclosed in the present invention and are all within the protection scope of the present invention.

Claims

1. A tower crane, characterized in that, include: Tower body (1); A boom (2) is hinged to the top of the tower body (1) via a hinge shaft (22a) and includes a counterweight (21) extending from the hinge position toward one side of the tower body (1) and a lifting boom (23) extending toward the opposite side. The counterweight (21) is equipped with a self-unloading counterweight (4) fixed in place by a self-unloading locking mechanism (3) and a graded locking mechanism (9). The self-unloading counterweight (4) includes a plurality of counterweights (4a). The graded locking mechanism (9) is configured to release the locking of the corresponding counterweights (4a) according to the load torque of the lifting boom (23). A triggering device, connected to the tower body (1), allows the boom (2) to rotate relative to the tower body (1) around the hinge axis (22a) when the lifting torque of the boom (23) suddenly decreases, causing the boom (23) to rise relative to the tower body (1). This triggers the self-unloading locking mechanism (3) to release the self-unloading counterweight (4) and causes the corresponding counterweight (4a) released by the graded locking mechanism (9) to detach from the installation position. The graded locking mechanism (9) includes an electrically controlled pin or a hydraulic pin (13) installed on the balance arm (21) and extending to prevent the balance block (4a) from falling off the installation position. The electrically controlled pin or the hydraulic pin (13) retracts sequentially according to the change of the load torque of the lifting arm (23) to release the locking of the corresponding balance block (4a).

2. The tower crane according to claim 1, characterized in that, The self-unloading locking mechanism (3) includes a load-bearing beam (31) and a support mechanism (32) respectively hinged to the balance arm (21). The load-bearing beam (31) is supported by the support mechanism (32) to keep the self-unloading counterweight (4) in the installation position.

3. The tower crane according to claim 2, characterized in that, The triggering device includes a traction mechanism, which includes a pivot plate (6) hinged to the boom (2) and having a first fulcrum and a second fulcrum, a first tie rod (5) with both ends connected to the first fulcrum and the tower body (1) respectively, and a second tie rod (7) with both ends connected to the second fulcrum and the support mechanism (32) respectively. When the boom (2) rotates relative to the tower body (1) so that the lifting arm (23) rises relative to the tower body (1), the traction mechanism pulls the support mechanism (32) around its hinge axis with the boom (2) relative to the bearing beam (31) to a position where it is disengaged from the bearing beam (31), so that the self-unloading counterweight (4) falls freely from the bearing beam (31).

4. The tower crane according to claim 3, characterized in that, The pivot plate (6) is formed as a sector plate, and the boom (2) is hinged to the central corner of the sector plate, with the first fulcrum and the second fulcrum located at the other two corners respectively; or, the pivot plate (6) is formed as a triangular plate, and the boom (2) is hinged to one corner of the triangular plate, with the first fulcrum and the second fulcrum located at the other two corners respectively.

5. The tower crane according to claim 3, characterized in that, The second tie rod (7) comprises a plurality of tie rod sections connected in sequence, with adjacent tie rod sections being detachably connected to each other and / or connected such that the second tie rod (7) is flexible at the connection position.

6. The tower crane according to claim 3, characterized in that, The boom (2) includes a connecting arm (22) connected between the counterweight boom (21) and the lifting boom (23), the hinge shaft (22a) is located on the lower side of the connecting arm (22), and the pivot plate (6) is hinged to the center of the connecting arm (22).

7. The tower crane according to claim 2, characterized in that, The triggering device includes a pulling mechanism, which includes a fixed support (10) fixed to the top of the tower body (1) and a third pull rod (11) connected between the fixed support (10) and the support mechanism (32), the third pull rod (11) being connected to the fixed support (10) by a flexible rope (12).

8. The tower crane according to claim 2, characterized in that, One of the supporting beam (31) and the support mechanism (32) is formed with a groove, and the other is formed with a spherical surface that mates with the groove, so that the spherical surface is dislodged from the groove and removed from the position supporting the supporting beam (31) by rotating the support mechanism (32).

9. The tower crane according to claim 2, characterized in that, The boom (2) and the load-bearing beam (31) extend horizontally respectively. The support mechanism (32) is hinged to the bottom beam of the boom (2). When supporting the load-bearing beam (31), the angle between the support mechanism (32) and the load-bearing beam (31) toward the side of the self-unloading counterweight (4) is greater than 90°.

10. The tower crane according to claim 1, characterized in that, The tower crane also includes a damping device (8) for slowing down the relative rotation speed of the lifting arm (23) and the tower body (1) or a self-locking device for locking the lifting arm (23) at its extreme upward position, which is hinged to the tower body (1) and the lifting arm (23) at both ends respectively.

Citation Information

Patent Citations

  • Method for improving capacity of flat-head-type tower crane and new-type flat-head-type tower crane

    CN101941653A

  • Movable arm tower crane

    CN103523682A

  • Tower crane adjustable counter-balancing device

    CN112537728A

  • Counter weight self-loading and unloading device and crane

    CN203820335U