A 10kV feeder protection overstep action discrimination method based on setting calculation
By using a setting calculation method, the setting value of the 10kV feeder protection is set. Combined with the protection operation status, the vacuum bubble breakdown of the feeder circuit breaker is quickly identified, which solves the problem of busbar undervoltage caused by 10kV feeder faults in substations, realizes rapid fault isolation and power supply restoration, and improves power supply reliability.
Patent Information
- Application Number
- CN202211529512.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-11-30
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2042-11-30
AI Technical Summary
In substations, when a 10kV feeder fault occurs, the protection over-level operation causes the busbar to lose voltage, making it impossible to quickly locate the fault and affecting the reliability of power supply. Existing technology makes it difficult to quickly identify whether the feeder circuit breaker has vacuum bubble breakdown or delayed separation problems.
The standby protection settings and main transformer low backup protection settings of the 10kV feeder protection are adjusted by setting calculation methods. Combined with the protection operation status, it is determined whether the feeder circuit breaker has vacuum bubble breakdown and the fault is quickly isolated.
It enables rapid identification of 10kV feeder faults, rapid isolation of fault points, and restoration of power supply to non-faulty busbars, thereby improving the reliability of power grid supply.
Smart Images

Figure CN115800215B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of substation technology, and specifically to a method for judging over-level operation of 10kV feeder protection based on setting calculation. Background Technology
[0002] In actual substation operation, cascading fault protection trips frequently occur. These trips lead to 10kV busbar voltage loss, expanding the outage area. Cascading outages of the 10kV feeder increase the average outage time for customers, severely impacting power supply reliability. Therefore, it is necessary to quickly locate the fault and restore power as soon as possible to reduce the impact of unplanned 10kV feeder outages on power supply reliability.
[0003] After a fault occurs on a 10kV feeder, if the 10kV feeder circuit breaker has a delayed tripping issue or its vacuum bulb breaks down, it will be unable to quickly isolate the fault. This will cause the main transformer low-voltage backup protection to trip, resulting in a 10kV busbar voltage loss. After a fault trip, it is necessary to quickly locate the fault point, isolate the fault interval, and restore power to customers as soon as possible. Collecting, organizing, and analyzing fault information is crucial during the rapid fault location process. After a fault, protection and control devices send a large amount of information on various types of changes, protection actions, and faults. Conventional protection action analysis requires collecting and organizing various types of information, which is tedious and time-consuming, hindering rapid power restoration.
[0004] Currently, when a power system fault occurs, the substation sends fault-related information such as protection actions and switch changes of each device in that bay to the SCADA system. First, key information of the same category is filtered out, such as SOE type messages. By comparing the times of the protection action and switch change messages, if the switch change time is significantly later than the protection action time, it is determined that the feeder circuit breaker has a slow-opening problem. This method can quickly determine whether there is a slow-opening problem by comparing action message information. However, its shortcoming is that because protection action information comes from the protection device and switch change information comes from the monitoring and control device, if different devices within the substation have inconsistent time synchronization, the time reference systems of the transmitted information will be inconsistent, making it impossible to compare the transmitted protection action and switch change message times. In this case, this solution cannot determine whether there is a slow-opening problem.
[0005] Another existing solution involves using a waveform recorder within the substation to record fault voltage and current AC quantities, protection actions, and switch position changes. The waveform is then used to examine the intervals in which protection actions occurred. By comparing the protection actions and switch auxiliary contact position information, it's possible to determine if the switch has a slow-opening problem. Furthermore, by comparing the fault current waveform and switch position information, it's possible to determine if the switch has a vacuum bulb breakdown problem. This method determines whether the switch has a slow-opening or vacuum bulb breakdown problem by comparing AC and switching quantities in the waveform recorder. However, a drawback is that if the 10kV feeder information is not connected to the waveform recorder, the above information cannot be directly compared, requiring supplementary judgment based on information transmitted from protection and monitoring systems.
[0006] Therefore, a method is needed to quickly identify cascading trips of 10kV feeder protection, especially when a 10kV feeder fault occurs, to determine whether the 10kV feeder circuit breaker has a vacuum bubble breakdown problem, thereby quickly locating the fault, realizing rapid restoration of 10kV undervoltage busbar, and ensuring the reliability of customer power supply. Summary of the Invention
[0007] To address the technical problems existing in the prior art, this invention provides a method for judging the over-level operation of 10kV feeder protection based on setting calculation. This method solves the problem that when a 10kV feeder fault occurs in a substation, the feeder protection and the main transformer low backup protection operate simultaneously, making it impossible to quickly locate the fault. It can determine whether the 10kV feeder circuit breaker has vacuum bubble breakdown or delayed separation, thus quickly locating the fault and enabling rapid restoration of 10kV undervoltage busbars, ensuring the reliability of customer power supply.
[0008] This invention can be achieved by adopting the following technical solutions:
[0009] A method for judging over-level operation of 10kV feeder protection based on setting calculation, the method comprising:
[0010] Based on the power grid operation mode and setting principles, the settings for the 10kV feeder protection standby section and the main transformer low-level backup protection are set; the settings for feeder overcurrent protection, feeder zero-sequence overcurrent protection, main transformer low-level backup overcurrent protection, and main transformer low-level backup zero-sequence overcurrent protection are set.
[0011] Based on the main transformer's low backup protection settings, the operation of the main transformer's backup protection is used to determine whether there is a protection overstepping action in the power system. When there is a protection overstepping action in the power system, based on the setting of the 10kV feeder protection backup section settings, the operation of the feeder protection is used to determine whether the feeder circuit breaker is vacuum bubble breakdown. When it is determined that the feeder circuit breaker is vacuum bubble breakdown, the faulty feeder circuit breaker is isolated.
[0012] In the preferred technical solution, the setting of the feeder overcurrent protection setting includes: the setting items of the feeder overcurrent protection setting include the feeder overcurrent stage I setting, the feeder overcurrent stage I time, the feeder overcurrent stage II setting, the feeder overcurrent stage II time, the feeder overcurrent stage III setting, and the feeder overcurrent stage III time.
[0013] Preferably, the step of determining whether there is a protection overstepping action in the power system based on the main transformer's low backup protection setting and the operation of the main transformer's backup protection includes:
[0014] When the feeder overcurrent protection operates, if the fault current reaches the main transformer overcurrent protection setting of stage I, the fault is cleared by the main transformer low backup overcurrent protection of stage I, indicating that there is a protection over-level operation; if the fault current does not reach the main transformer overcurrent protection setting of stage I but reaches the main transformer overcurrent protection setting of stage II, the fault is cleared by the main transformer low backup overcurrent protection of stage II, indicating that there is a protection over-level operation.
[0015] When the feeder overcurrent protection stage I operates, if the fault current reaches the set value of the main transformer zero-sequence overcurrent stage I, the fault will be cleared by the main transformer low backup zero-sequence overcurrent stage I, indicating that there is a protection over-level operation.
[0016] Specifically, the method of determining whether the feeder circuit breaker has experienced vacuum bubble breakdown based on the protection operation status, based on the setting of the 10kV feeder protection standby section, includes:
[0017] After a feeder fault occurs, if the fault current reaches the feeder overcurrent stage I setting value, the feeder circuit breaker will be tripped after the feeder overcurrent stage I time. If the fault current value meets the feeder overcurrent stage II setting value, the overcurrent stage II protection will operate after the feeder overcurrent stage II time. In this case, it is determined that the feeder circuit breaker has a vacuum bubble breakdown problem.
[0018] If the fault current does not reach the feeder overcurrent stage I setting value, but reaches the feeder overcurrent stage II setting value, and the overcurrent stage II protection operates after the feeder overcurrent stage II time, and the overcurrent stage III protection operates after the feeder overcurrent stage III time, then it is determined that the feeder circuit breaker has a vacuum bubble breakdown problem.
[0019] When the fault current reaches the feeder zero-sequence overcurrent stage I setting value, after the feeder zero-sequence overcurrent stage I time, the feeder zero-sequence overcurrent stage I protection will operate and disconnect the feeder circuit breaker. If the fault current value meets the feeder zero-sequence overcurrent stage II value, after the feeder zero-sequence overcurrent stage II time, the feeder zero-sequence overcurrent stage II protection will operate. Then it is determined that the feeder circuit breaker has a vacuum bubble breakdown problem.
[0020] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0021] This invention proposes a method for judging cascading operation of 10kV feeder protection based on setting calculations. By setting the backup section of the 10kV feeder protection settings, the method determines whether the feeder circuit breaker has experienced vacuum bubble breakdown based on the protection operation status. This solves the problem of simultaneous operation of feeder protection and main transformer low-level backup protection due to 10kV feeder faults in substations, making it impossible to quickly locate the fault. It can effectively distinguish between 10kV feeder equipment faults and 10kV bus faults, achieve rapid fault isolation, restore power to the non-faulty bus, and realize rapid power supply restoration of the 10kV bus, effectively improving the reliability of power grid supply. Attached Figure Description
[0022] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on the structures shown in these drawings without creative effort.
[0023] Figure 1 This is a schematic diagram of the 10kV feeder protection over-level action judgment method in an embodiment of the present invention;
[0024] Figure 2 This is a schematic diagram of a power system feeder protection application scenario in an embodiment of the present invention;
[0025] Figure 3 This is a flowchart of the main transformer low backup overcurrent protection action judgment method in an embodiment of the present invention;
[0026] Figure 4 This is a flowchart of the main transformer low backup zero-sequence overcurrent protection action judgment method in an embodiment of the present invention;
[0027] Figure 5 This is a flowchart illustrating the logic of the feeder overcurrent stage II protection action judgment method in this embodiment of the invention.
[0028] Figure 6 This is a flowchart of the feeder overcurrent stage III protection action judgment method in an embodiment of the present invention;
[0029] Figure 7 This is a flowchart illustrating the logic of the feeder zero-sequence overcurrent stage II protection action judgment method in this embodiment of the invention. Detailed Implementation
[0030] The technical solution of the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. Obviously, the described embodiments are only some embodiments of the present invention, not all embodiments, and the implementation of the present invention is not limited thereto. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0031] Example 1:
[0032] When a feeder fault occurs, if the feeder circuit breaker's vacuum bulb breaks down, the feeder circuit breaker's position changes normally. Combined with the fault current waveform recorded by the waveform recorder, the fault persists even after the switch is opened, and the fault cannot be cleared. This leads to the main transformer's low-voltage backup protection tripping, causing a 10kV busbar voltage loss. Ultimately, the transformer's backup protection trips to clear the fault. When a fault occurs, each bay and terminal generates a large amount of information. Using common methods for rapid fault location, it takes time to process the key information for fault point determination. This invention utilizes the fault characteristic of a 10kV feeder circuit breaker failing to clear the fault current due to vacuum bulb breakdown. That is, although the switch is open, the fault current persists after the feeder protection trips until the main transformer's low-voltage backup protection trips the low-voltage switch, at which point the fault current disappears. Based on the setting of the backup section of the feeder protection, the problem of vacuum bubble breakdown in the 10kV feeder circuit breaker can be judged by the protection operation. This can effectively distinguish between 10kV feeder equipment faults and 10kV bus faults, realize rapid fault isolation, restore power supply to the non-faulty bus, and achieve rapid power supply restoration of the 10kV bus, thus effectively improving the reliability of power grid supply.
[0033] like Figure 1 As shown, the present invention provides a method for judging over-level operation of 10kV feeder protection based on setting calculation, comprising the following steps:
[0034] S1. Based on the power grid operation mode and setting principles, the settings for the 10kV feeder protection standby section and the main transformer low-sequence overcurrent protection are set. Specifically, setting the 10kV feeder protection standby section settings includes setting the feeder overcurrent protection settings and the feeder zero-sequence overcurrent protection settings; setting the main transformer low-sequence overcurrent protection settings includes setting the main transformer low-sequence overcurrent protection settings and the main transformer low-sequence zero-sequence overcurrent protection settings.
[0035] like Figure 2 The diagram shows a power system feeder protection application scenario. The 110kV section uses a line transformer group connection, while the 10kV section uses a single busbar connection. The 110kV main transformer is connected to a section of the 10kV busbar, the 10kV zigzag transformer is connected to the 10kV substation busbar bridge, the 10kV feeder is connected to the 10kV busbar, and the 10kV feeder circuit breaker is located on the 10kV feeder.
[0036] S11. Adjusting the feeder overcurrent protection setting.
[0037] The feeder overcurrent protection settings are configured in three stages. Feeder overcurrent stage III is set to "out of setting," with the current value and delay set to the maximum value within the allowable range. The feeder overcurrent protection settings include the feeder overcurrent stage I setting, feeder overcurrent stage I time, feeder overcurrent stage II setting, feeder overcurrent stage II time, feeder overcurrent stage III setting, and feeder overcurrent stage III time.
[0038] To ensure timely fault clearing when a user's distribution transformer experiences a three-phase short-circuit fault, preferably, the overcurrent I setting of the feeder is greater than the short-circuit current of the user's distribution transformer during a three-phase short-circuit fault. The short-circuit current during a three-phase short-circuit fault is calculated based on the line impedance and the distribution transformer impedance, and the short-circuit impedance of the distribution transformer is obtained based on the transformer capacity, thus possessing a certain degree of sensitivity.
[0039] To ensure timely fault clearing when a short-circuit fault occurs at the end of a 10kV feeder, preferably, the overcurrent II setting of the feeder is greater than the short-circuit current when a short-circuit fault occurs at the end of the 10kV feeder, and the short-circuit current when a short-circuit fault occurs at the end of the 10kV feeder is obtained based on the line impedance.
[0040] The overcurrent protection time for the feeder is set to a fixed time value (Section I). The overcurrent protection time for the feeder is set by an additional time increment compared to Section I. In this example, the time increment is set to 0.3 seconds, and the time setpoint is 0.9 seconds. The specific settings for the feeder overcurrent protection in this case are shown in Table 1.
[0041] For the feeder overcurrent section III (standby section), the setting value of the feeder overcurrent section III is the same as that of the feeder overcurrent section II. The time of the feeder overcurrent section III is one more time increment than that of the feeder overcurrent section II, which is set by 0.3s, i.e., the time setting value of the feeder overcurrent section III is 1.2s.
[0042] Table 1
[0043] Fixed value term First value Feeder overcurrent section I setting 3000A Feeder overcurrent I period 0.3s Feeder overcurrent stage II setting 780A Feeder overcurrent stage II 0.9s Feeder overcurrent stage III setting 780A Feeder overcurrent III stage 1.2s
[0044] S12. Set the zero-sequence overcurrent protection setting for the feeder.
[0045] When a feeder fault occurs, it is necessary to ensure rapid fault clearing while preventing protection malfunctions. To improve the sensitivity and reliability of protection operation, preferably, the feeder zero-sequence overcurrent protection setting is configured in two stages. The feeder zero-sequence overcurrent stage I setting is set to avoid the maximum unbalanced current value during a three-phase short circuit, and the feeder zero-sequence overcurrent stage I time is taken as the maximum value within the allowable range. In this example, the zero-sequence overcurrent protection delay is set to 1 second.
[0046] For the zero-sequence overcurrent protection stage II (standby stage), the setting value of the feeder zero-sequence overcurrent protection stage II is the same as that of the feeder zero-sequence overcurrent protection stage I. The duration of the feeder zero-sequence overcurrent protection stage II is one time increment longer than that of the feeder zero-sequence overcurrent protection stage I, and is set by an increase of 0.3s. The specific setting values for the feeder overcurrent protection are shown in Table 2.
[0047] Table 2
[0048] Fixed value term First value Feeder zero-sequence overcurrent stage I setting 60A Feeder zero-sequence overcurrent I time period 1s Feeder zero-sequence overcurrent stage II setting 60A Feeder zero-sequence overcurrent II stage 1.3s
[0049] S13. Adjust the low backup overcurrent protection setting of the main transformer.
[0050] To ensure timely fault clearing in the event of a 10kV busbar fault, the low-level backup overcurrent stage I setting of the main transformer is configured to guarantee a certain sensitivity to the short-circuit current during a phase-to-phase fault on the 10kV busbar. The low-level backup overcurrent stage I setting of the main transformer is as follows:
[0051]
[0052] Among them I zd The primary transformer's low backup overcurrent stage I setting is... K represents the short-circuit current when a phase-to-phase fault is detected on a 10kV busbar. lm Sensitivity.
[0053] The overcurrent stage II setting is set to avoid the maximum load current. The overcurrent stage II time of the main transformer low backup overcurrent protection is the same as the overcurrent stage I time of the main transformer low backup overcurrent protection plus a time increment. In this example, the time increment is 0.3s. The specific settings for the main transformer low backup overcurrent protection are shown in Table 3.
[0054] Table 3
[0055]
[0056]
[0057] S14. Set the low-sequence zero-sequence overcurrent protection setting of the main transformer.
[0058] The setting value for the first stage of the low-sequence overcurrent protection of the main transformer is designed to avoid the zero-sequence current flowing through the neutral point resistance caused by the zero-sequence voltage generated at the neutral point of the grounding transformer due to the asymmetry of the three-phase voltage in the system during normal operation. In this example, the duration of the first stage of the low-sequence overcurrent protection of the main transformer is set to 2.7s. The specific setting values for the low-sequence overcurrent protection of the main transformer are shown in Table 4.
[0059] Table 4
[0060] Fixed value term First value Main transformer low backup zero-sequence overcurrent stage I setting 75A Main transformer low backup zero-sequence overcurrent I period 2.7s
[0061] S2. Based on the main transformer low backup protection setting, determine whether there is a protection overstepping action in the power system by checking the operation of the main transformer backup protection. If it is determined that there is a protection overstepping action in the power system, based on the setting of the 10kV feeder protection backup section, determine whether the feeder circuit breaker is vacuum bubble broken by checking the operation of the feeder protection. If it is determined that the feeder circuit breaker is vacuum bubble broken, isolate the faulty feeder circuit breaker.
[0062] Based on the low backup protection settings of the main transformer, the operation of the main transformer backup protection is used to determine whether there is a protection overstepping action in the power system. Specifically, this includes:
[0063] When the feeder overcurrent protection (Stage I) operates, if the fault current reaches the main transformer overcurrent stage I setting, the main transformer low-backup overcurrent stage I will clear the fault, indicating a protection over-level operation. If the fault current does not reach the main transformer overcurrent stage I setting, but reaches the main transformer overcurrent stage II setting and the main transformer low-backup overcurrent stage II clears the fault, it is also considered a protection over-level operation. The logic flowchart for the main transformer low-backup overcurrent protection operation judgment method is as follows: Figure 3 As shown.
[0064] Specifically, when a feeder fault occurs, if the fault current reaches the feeder overcurrent stage I setting of 3000A, the overcurrent stage I protection will trip after 0.3 seconds, disconnecting the feeder circuit breaker. If the vacuum bulb of the feeder circuit breaker breaks down, although the switch changes position (the feeder circuit breaker tripping time is approximately tens of milliseconds), the fault cannot be cleared, and the fault current still exists. Since the fault current value meets the overcurrent stage II setting of 780A, the overcurrent stage II protection will trip after approximately 0.6 seconds. At this point, the fault is still not cleared. When the fault current reaches the main transformer undercurrent stage I setting of 10002A, the main transformer undercurrent protection will trip, disconnecting the main transformer undercurrent switch and clearing the fault. If the fault current does not reach the main transformer undercurrent stage I setting, but reaches the main transformer undercurrent stage II setting of 4290A, and the fault lasts for 1.2 seconds, the main transformer undercurrent stage II protection will trip, disconnecting the main transformer undercurrent switch and clearing the fault.
[0065] When the feeder overcurrent protection (Stage I) operates, if the fault current reaches the main transformer's zero-sequence overcurrent protection (Stage I) setting, the main transformer's low-backup zero-sequence overcurrent protection (Stage I) will clear the fault, indicating a protection over-level operation. The logic flowchart for the main transformer's low-backup zero-sequence overcurrent protection operation judgment method is as follows: Figure 4 As shown.
[0066] When a feeder fault occurs, and the zero-sequence current reaches the zero-sequence overcurrent stage I setting of 60A, the zero-sequence overcurrent stage I protection will trip after 1 second, disconnecting the feeder circuit breaker. If the vacuum bulb of the feeder circuit breaker breaks down, although the switch changes position (the feeder circuit breaker tripping time is approximately tens of milliseconds), the fault cannot be cleared, and the fault current still exists. Since the zero-sequence overcurrent stage I and stage II current settings are the same, the fault zero-sequence current value also meets the zero-sequence overcurrent stage II value of 60A. After approximately 0.3 seconds, the zero-sequence overcurrent stage II protection will trip. When the fault current reaches the main transformer low-voltage zero-sequence overcurrent stage I setting of 75A, the main transformer low-voltage zero-sequence overcurrent stage I protection will trip, disconnecting the main transformer low-voltage switch and clearing the fault.
[0067] When it is determined that there is a protection over-level operation in the power system, based on the setting of the 10kV feeder protection spare section, the operation of the feeder protection is used to determine whether the feeder circuit breaker has a vacuum bubble breakdown, specifically including:
[0068] After a feeder fault occurs, if the fault current reaches the feeder overcurrent stage I setting, and the feeder circuit breaker is tripped after the feeder overcurrent stage I time, and the fault current value meets the feeder overcurrent stage II setting, and the overcurrent stage II protection trips after the feeder overcurrent stage II time, then it is determined that the feeder circuit breaker has a vacuum bubble breakdown problem. The logic flowchart for the feeder overcurrent stage II protection tripping judgment method is as follows: Figure 5 As shown.
[0069] Specifically, when a feeder fault occurs and the fault current reaches the overcurrent stage I setting of 3000A, the overcurrent stage I protection will activate after 0.3 seconds, disconnecting the feeder circuit breaker. If the vacuum bulb of the feeder circuit breaker breaks down, although the switch changes position (the feeder circuit breaker's opening time is approximately tens of milliseconds), the fault cannot be disconnected, and the fault current remains. Since the fault current value meets the overcurrent stage II value of 780A, the overcurrent stage II protection will activate after approximately 0.6 seconds. If the feeder circuit breaker changes position and both of the above current protection stages activate, it indicates that the feeder circuit breaker has a vacuum bulb breakdown problem. In this embodiment, the overcurrent stage I activation time is 0.3 seconds, the overcurrent stage II activation time is 0.9 seconds, and the timing of stage II activation starts simultaneously with stage I. Stage I activation has already occurred for 0.3 seconds, and stage II activation will occur after approximately 0.6 seconds.
[0070] If the fault current does not reach the feeder overcurrent stage I setting, but reaches the feeder overcurrent stage II setting, and the overcurrent stage II protection operates after the feeder overcurrent stage II time period, and the overcurrent stage III protection operates after the feeder overcurrent stage III time period, then it is determined that the feeder circuit breaker has a vacuum bubble breakdown problem. The logic flowchart for the feeder overcurrent stage III protection operation judgment method is as follows: Figure 6 As shown.
[0071] Specifically, when a feeder fault occurs, if the fault current does not reach the overcurrent stage I setting of 3000A but reaches the overcurrent stage II setting of 780A, the overcurrent stage II protection will activate after 0.9 seconds. If the vacuum bulb of the feeder circuit breaker breaks down, the fault cannot be cleared, and the fault current remains. The overcurrent stage III setting of 780A is the same as that of overcurrent stage II, and the overcurrent stage III protection will activate after another 0.3 seconds. If the feeder circuit breaker changes position and both of the above current protection stages activate, it indicates that the feeder circuit breaker has a vacuum bulb breakdown problem. The activation time of overcurrent stage I is 0.9 seconds, and the activation time of overcurrent stage II is 1.2 seconds. The timing of stage III activation starts simultaneously with stage II. Stage II has already activated for 0.9 seconds, and stage II will activate after approximately 0.3 seconds.
[0072] When the fault current reaches the feeder zero-sequence overcurrent stage I setting, after the feeder zero-sequence overcurrent stage I time, the feeder zero-sequence overcurrent stage I protection operates, disconnecting the feeder circuit breaker. If the fault current value meets the feeder zero-sequence overcurrent stage II value, and after the feeder zero-sequence overcurrent stage II time, the feeder zero-sequence overcurrent stage II protection operates, then it is determined that the feeder circuit breaker has a vacuum bubble breakdown problem. The logic flowchart of the feeder zero-sequence overcurrent stage II protection judgment method is as follows: Figure 7 As shown.
[0073] Specifically, when a feeder fault occurs, and the zero-sequence current reaches the zero-sequence overcurrent stage I setting of 60A, the zero-sequence overcurrent stage I protection will trip after 1 second, disconnecting the feeder circuit breaker. If the feeder circuit breaker experiences vacuum bubble breakdown, although the switch changes position (the feeder circuit breaker's opening time is approximately tens of milliseconds), the fault cannot be cleared, and the fault current remains. Since the zero-sequence overcurrent stage I and stage II current settings are the same, the fault zero-sequence current value also meets the zero-sequence overcurrent stage II value of 60A. After approximately 0.3 seconds, the zero-sequence overcurrent stage II protection will trip. If the feeder circuit breaker changes position and both of the above zero-sequence current protection stages trip, it is determined that the feeder circuit breaker has a vacuum bubble breakdown problem.
[0074] This invention is based on setting the backup section value of the 10kV feeder protection. Through the above judgment method, when the main transformer backup protection is activated, that is, when it is determined that there is a protection over-level operation in the power system, if the fault still exists after the feeder circuit breaker is opened, and two consecutive protection elements of the same type of feeder protection are activated, it can be quickly determined that the vacuum bulb of the feeder circuit breaker is broken down, the bus fault can be quickly eliminated, and the power supply to the under-voltage bus can be quickly restored by isolating the faulty feeder interval.
[0075] The above embodiments are preferred embodiments of the present invention, but the embodiments of the present invention are not limited to the above embodiments. Any changes, modifications, substitutions, combinations, or simplifications made without departing from the spirit and principle of the present invention shall be considered equivalent substitutions and shall be included within the protection scope of the present invention.
Claims
1. A method for judging over-level operation of 10kV feeder protection based on setting calculation, characterized in that, Including the following steps: Based on the power grid operation mode and setting principles, the settings for the 10kV feeder protection standby section and the main transformer low-level backup protection are set; the settings for feeder overcurrent protection, feeder zero-sequence overcurrent protection, main transformer low-level backup overcurrent protection, and main transformer low-level backup zero-sequence overcurrent protection are set. Based on the main transformer low backup protection setting, the operation of the main transformer backup protection is used to determine whether there is a protection overstepping operation in the power system; when there is a protection overstepping operation in the power system, based on the setting of the 10kV feeder protection backup section setting, the operation of the feeder protection is used to determine whether the feeder circuit breaker has vacuum bubble breakdown. When it is determined that the feeder circuit breaker is a vacuum bubble breakdown, the feeder circuit breaker that isolates the fault is used. The setting of the feeder overcurrent protection setting includes: the setting items of the feeder overcurrent protection setting include the feeder overcurrent stage I setting, the feeder overcurrent stage I time, the feeder overcurrent stage II setting, the feeder overcurrent stage II time, the feeder overcurrent stage III setting, and the feeder overcurrent stage III time; The setting of the zero-sequence overcurrent protection setting for the feeder includes: setting the feeder zero-sequence overcurrent stage I setting to avoid the maximum unbalanced current value during a three-phase short circuit; setting the feeder zero-sequence overcurrent stage II setting to be the same as the feeder zero-sequence overcurrent stage I setting; taking the maximum value within the allowable range for the feeder zero-sequence overcurrent stage I time; and setting the feeder zero-sequence overcurrent stage II time to be one time stage longer than the feeder zero-sequence overcurrent stage I time. The setting of the low backup overcurrent protection setting of the main transformer includes: setting the sensitivity to ensure the short-circuit current when a phase-to-phase fault occurs on the 10kV busbar; setting the first stage of the low backup overcurrent protection of the main transformer: ; in The primary transformer's low backup overcurrent stage I setting is... This refers to the short-circuit current when a phase-to-phase fault is detected on a 10kV busbar. Sensitivity; The overcurrent stage II setting is set according to the maximum load current. The overcurrent stage II time of the main transformer low backup is the overcurrent stage I time of the main transformer low backup plus a time difference. The overcurrent stage I time of the main transformer low backup is 0.9 seconds and the time difference is 0.3 seconds. The setting of the low-backup zero-sequence overcurrent protection setting of the main transformer includes: the setting of the first stage of the low-backup zero-sequence overcurrent protection of the main transformer is set to avoid the zero-sequence current passing through the neutral point resistance caused by the zero-sequence voltage generated at the neutral point of the grounding transformer due to the asymmetry of the three-phase voltage of the system during normal operation, and the time of the first stage of the low-backup zero-sequence overcurrent protection of the main transformer is 2.7s. The method of determining whether there is a protection overstepping action in the power system based on the main transformer's low backup protection settings and the operation of the main transformer's backup protection includes: When the feeder overcurrent protection operates, if the fault current reaches the main transformer overcurrent protection setting of stage I, the fault is cleared by the main transformer low backup overcurrent protection of stage I, indicating that there is a protection over-level operation; if the fault current does not reach the main transformer overcurrent protection setting of stage I but reaches the main transformer overcurrent protection setting of stage II, the fault is cleared by the main transformer low backup overcurrent protection of stage II, indicating that there is a protection over-level operation. When the feeder overcurrent protection stage I operates, if the fault current reaches the set value of the main transformer zero-sequence overcurrent stage I, the fault will be cleared by the main transformer low backup zero-sequence overcurrent stage I, indicating that there is a protection over-level operation.
2. The method for judging over-level operation of 10kV feeder protection based on setting calculation as described in claim 1, characterized in that, The overcurrent setting of section I of the feeder is greater than the short-circuit current of the three-phase fault of the user's distribution transformer, the overcurrent setting of section II of the feeder is greater than the short-circuit current when a short-circuit fault occurs at the end of the 10kV feeder, and the overcurrent setting of section III of the feeder is the same as that of section II of the feeder. The overcurrent period I of the feeder is set to a fixed time value. The overcurrent period II of the feeder is one time step longer than the overcurrent period I. The overcurrent period III of the feeder is one time step longer than the overcurrent period II.
3. The method for judging over-level operation of 10kV feeder protection based on setting calculation as described in claim 1, characterized in that, The method of determining whether a feeder circuit breaker has experienced vacuum bubble breakdown based on the protection operation status, based on the set value of the 10kV feeder protection standby section, includes: When the fault current reaches the feeder overcurrent stage I setting value, the feeder circuit breaker is tripped after the feeder overcurrent stage I time. If the fault current value meets the feeder overcurrent stage II setting value, the overcurrent stage II protection operates after the feeder overcurrent stage II time. Then it is determined that the feeder circuit breaker has a vacuum bubble breakdown problem. If the fault current does not reach the feeder overcurrent stage I setting value, but reaches the feeder overcurrent stage II setting value, and the overcurrent stage II protection operates after the feeder overcurrent stage II time, and the overcurrent stage III protection operates after the feeder overcurrent stage III time, then it is determined that the feeder circuit breaker has a vacuum bubble breakdown problem. When the fault current reaches the feeder zero-sequence overcurrent stage I setting value, after the feeder zero-sequence overcurrent stage I time, the feeder zero-sequence overcurrent stage I protection will operate and disconnect the feeder circuit breaker. If the fault current value meets the feeder zero-sequence overcurrent stage II value, after the feeder zero-sequence overcurrent stage II time, the feeder zero-sequence overcurrent stage II protection will operate. Then it is determined that the feeder circuit breaker has a vacuum bubble breakdown problem.
Citation Information
Patent Citations
Automatic jump selection method of electrified railway feeder line started by external contacts
CN102005737A
Protection method for multilevel direct current distribution feeder line
CN104934950A