Construction method of shield tunneling under buildings
By reinforcing the surrounding strata with pre-embedded sleeve valves and grouting before the tunnel boring machine (TBM) arrives, and adjusting the TBM parameters, the TBM can pass through at a uniform speed, thus solving the problems of interrupted piles, ground settlement, and building tilting during TBM construction and ensuring construction safety.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- CHINA RAILWAY 20TH BUREAU GROUP CO LTD
- Filing Date
- 2022-10-25
- Publication Date
- 2026-06-23
AI Technical Summary
During tunnel boring machine (TBM) construction, especially when tunneling under buildings in silty soil, problems such as broken piles, uneven ground settlement, building tilting, and collapse are prone to occur.
Before the tunnel boring machine (TBM) arrives, the surrounding strata are reinforced with pre-embedded sleeve valves and/or grouting. The TBM parameters are adjusted to ensure a uniform speed. During the TBM's passage under the building, the surrounding strata are reinforced with grouting. The pressure of the slurry chamber is controlled. The TBM exits the tail section for lining construction and construction monitoring is conducted to adjust the progress.
It improved the reinforcement effect around the building, reduced pile breakage, controlled ground settlement and building tilt, and ensured construction safety.