Track large rail member laying operation method

By using a flip-type retractable structure and a three-section folding arm gantry crane device, the problems of complex structure and high cost of high-speed rail track component replacement equipment have been solved, enabling fast and convenient replacement of track components and improving transportation capacity and safety.

CN116005501BActive Publication Date: 2026-11-20ZHUZHOU TIMES ELECTRONICS TECH CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202310007265.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-01-04
Publication Date
2026-11-20
Estimated Expiration
2043-01-04

AI Technical Summary

Technical Problem

Existing high-speed rail track replacement equipment is complex in structure, inconvenient to operate, costly, and space-constrained, making it impossible to quickly and efficiently replace rails approximately 50 meters long.

Method used

The gantry crane device, which adopts a flip-type retraction structure, is placed longitudinally on a transport flatcar, simplifying the flip-over operation. Combined with a three-section folding arm beam and a single-stage lifting outrigger, it enables the rapid deployment and storage of the gantry crane device, simplifying the operation process and improving transportation capacity.

Benefits of technology

The operation process of the gantry crane was simplified, costs were reduced, the transportation capacity of a single flatbed truck was increased, and the replacement of large track components was made quick and convenient, reducing safety risks and time costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116005501B_ABST
    Figure CN116005501B_ABST
Patent Text Reader

Abstract

The application discloses a track large rail piece replacement operation method, and first and second transport flat cars and a rail car are coupled and hung to travel to a specified position of a replacement operation site. A door crane device is clamped and turned over one by one through a folding and unfolding device, and after the door crane device restores an unfolded state, the door crane device is unloaded from the first transport flat car according to position and sequence and placed at the specified position. A group of cranes composed of a plurality of door crane devices is used to unload a new track large rail piece from the second transport flat car and place the new track large rail piece under the door crane device on one side of a line, hoist the disassembled old track large rail piece to the other side, hoist the new track large rail piece to the position of the original old track large rail piece on the line, and complete replacement of the new and old track large rail pieces. After the line is restored, the old track large rail piece and the door crane device are recovered according to the same method, and the first and second transport flat cars and the rail car are coupled and driven away. The application can solve the technical problems of existing track large rail piece replacement equipment, such as complex structure and operation, high cost and limited space utilization.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of railway engineering machinery technology, and in particular to a method for replacing large rail components in high-speed railway tracks. Background Technology

[0002] High-speed rail lines mainly refer to operating lines with speeds exceeding 250 km / h. Due to the rapid passage of vehicles and the impact and crushing effect of their wheels, the rails are prone to wear and tear over long distances, necessitating replacement. The high frequency of vehicle traffic requires rapid repair of worn rails. To save time, major track components, such as switch points and point rails, need to be replaced simultaneously. Major high-speed rail components mainly refer to rails approximately 50 meters long, track components of gauge 18 and above (switches, connecting rails, point rails, stock rails, etc.), and track slabs. These components are characterized by their length and weight, making manual replacement difficult. However, due to the limited working area for major high-speed rail components, existing equipment such as rail-changing vehicles and 25-ton rail cranes are insufficient. Therefore, achieving rapid replacement of major high-speed rail components is a pressing technical problem that needs to be solved.

[0003] Currently, there are several main methods for replacing large rail components on high-speed railway tracks:

[0004] The first method involves using 2 to 3 25T railcars to lift large rail components from adjacent lines. This method is prone to causing damage to the large rail components due to deformation during operation. Furthermore, because the synchronization of multiple railcars is poor, there is a risk of large swings, which could lead to safety hazards.

[0005] The second method involves using large track-changing machinery for long-distance rail replacement. However, due to the characteristics of the equipment, this method is only suitable for long-distance replacements on the order of kilometers, and the preparation work is excessively lengthy. Furthermore, when using this equipment to replace rails of tens or hundreds of meters, the end rail wear will exceed the required replacement length. Therefore, the main disadvantages of this method are: high cost, low efficiency, and unsuitability for replacing rails approximately 50 meters long.

[0006] Among the existing technologies, the following technical solutions are mainly related to this application:

[0007] Prior art 1 is Chinese invention application CN114808567A, filed by the applicant on March 31, 2022, and published on July 29, 2022, entitled "A Gantry Crane Device for Replacing Railway Line Components and Its Operation Method." This application discloses a gantry crane device for replacing railway line components and its operation method. The device includes: a truss; a lateral moving mechanism mounted on the truss and capable of moving laterally along the truss to adjust the lifting position; the lateral moving mechanism includes a lifting mechanism that drives a chain to move vertically up and down to transport railway line components; and left and right support legs movably mounted at the lower left and right ends of the truss, respectively, capable of moving laterally along the truss to adjust the lateral span of the gantry crane device. The left and right support legs can also move vertically up and down to adjust the height of the truss above the working surface. This application can solve the technical problems of existing railway line component replacement methods occupying adjacent track space, posing operational safety risks, being inflexible in operation, and being unable to adapt to the operational needs of railway lines under complex working conditions.

[0008] Prior art 2 is Chinese invention application CN114701954A, filed by the applicant on May 7, 2022, and published on July 5, 2022, entitled "A Turnout Replacement Device and System". This application discloses a turnout replacement device and system. The device includes a gantry crane, which further includes: a crossbeam; sliding frames movably disposed at the left and right ends of the crossbeam, the sliding frames being able to move laterally along the crossbeam to adjust the lateral span of the gantry crane; a lifting mechanism disposed on the crossbeam and located between the two sliding frames, capable of moving laterally along the crossbeam to adjust the lifting position of the turnout; and outriggers disposed below the two sliding frames, capable of extending and retracting vertically to adjust the height of the crossbeam from the roadbed. In operation, several gantry cranes are arranged at intervals along the railway line and span the roadbed on both sides of the rails. This application solves the technical problems of low operational safety and inability to lift large-sized turnout components in existing turnout replacement equipment.

[0009] However, both existing technologies 1 and 2 have the following technical defects:

[0010] 1) The gantry crane's retraction mechanism has a relatively complex structure, and the retraction operation includes steps such as lifting, rotating, and clamping, which is inconvenient and time-consuming.

[0011] 2) The gantry crane has a relatively complex structure. It needs to be rotated to be placed on a flatcar without exceeding the clearance limits for transportation. The gantry crane outriggers include a two-stage lifting structure, which greatly increases the cost.

[0012] 3) Gantry cranes need to be rotated and placed longitudinally, and due to their long length, only about 4 can be placed on each vehicle, which limits the gantry crane transportation capacity of a single flatcar. Summary of the Invention

[0013] In view of this, the purpose of this application is to provide a method for replacing large track components, so as to solve the technical problems of existing large track component replacement equipment having complex structure and operation, high cost and limited space utilization.

[0014] To achieve the aforementioned objectives, this application specifically provides a technical implementation scheme for a method of replacing large track components. The method includes the following steps:

[0015] S1) Several gantry crane devices are placed horizontally on the first transport flatcar in a folded state, and the new rail components are placed on the second transport flatcar. The first transport flatcar, the second transport flatcar, and the railcar are coupled together and travel to the designated location at the replacement work site.

[0016] S2) The gantry crane devices are clamped and flipped one by one by the flip-type retraction device. At the same time, after the gantry crane devices are restored to the unfolded state, they are unloaded from the first transport flatcar according to their position and sequence and placed in the designated position.

[0017] S3) The new track components are unloaded from the second transport flatcar and placed on one side of the track below the gantry cranes by a group of cranes consisting of multiple gantry cranes;

[0018] S4) The dismantled old track components are hoisted to the other side of the track below the gantry crane using a group of cranes;

[0019] S5) The new track components are hoisted to the original position of the old track components on the line by a group of cranes to complete the replacement of the old track components with the new ones;

[0020] S6) After the line is restored, the old track components are lifted by a group of cranes, and the second transport flatcar enters and places the old track components on the second transport flatcar.

[0021] S7) The gantry crane devices on the line are clamped and flipped one by one by the retraction device, and then returned to the folded state and recycled to the first transport flatcar.

[0022] S8) The gantry crane device is placed horizontally on the first transport flatcar in a folded state, and the first transport flatcar, the second transport flatcar, and the railcar are assembled and driven away.

[0023] Furthermore, two longitudinal guide rails are arranged parallel to each other along the longitudinal direction on the first transport flatcar, and a power unit is arranged between the two longitudinal guide rails, which can provide operating power for the take-up and take-down device.

[0024] Furthermore, in step S2), during the placement operation, the gantry crane device is transported to the designated position via the longitudinal guide rail set on the first transport flatcar, and is clamped and flipped by the take-up and put-down device. The gantry crane device is then placed on the line after being extended to the normal state.

[0025] Furthermore, the gantry crane device includes: a crossbeam, a transverse sliding frame, a lifting mechanism, a lifting chain, and outriggers; the crossbeam further includes a main beam, with hinged folding arms on both sides of the main beam. Transverse sliding frames are movably installed at both ends of the crossbeam, and these sliding frames can move laterally along the crossbeam to adjust the lateral span of the gantry crane device. A lifting mechanism is installed on the crossbeam located between the two transverse sliding frames, and this lifting mechanism can move laterally along the crossbeam to adjust the lateral lifting position of the large track components. The lifting chain is connected to the lifting mechanism for lifting the large track components. Outriggers are installed below the two transverse sliding frames, and these outriggers can extend and retract vertically to adjust the height of the crossbeam above the horizontal plane of the track, simultaneously achieving leveling of the gantry crane device.

[0026] Furthermore, the lateral sliding frame is fitted over the outside of the crossbeam, and one end of the folding drive mechanism is hinged to the main beam, while the other end is hinged to the folding arm. When the retraction device places the gantry crane, the folding drive mechanism drives the folding arm to unfold relative to the main beam, and the lateral sliding frame moves towards the outside of the crossbeam to increase the lateral span of the gantry crane. When the retraction device retracts the gantry crane, the folding drive mechanism drives the folding arm to retract relative to the main beam, and the lateral sliding frame moves towards the inside of the crossbeam to reduce the overall width of the gantry crane.

[0027] Furthermore, the take-up and drop-off device includes: a base, a tilting frame, a tilting drive mechanism, a clamping mechanism, and a connecting rod; the base is fixed to the body of the first or second transport flatcar. One end of the tilting frame is hinged to the base, and the other end extends upward and is hinged to the clamping mechanism, which can clamp large track components. One end of the tilting drive mechanism is hinged to the base, and the other end is hinged to the tilting frame. One end of the connecting rod is hinged to the clamping mechanism, and the other end is hinged to the base. The tilting frame, base, tilting frame clamping mechanism, and connecting rod form a four-bar linkage, and the tilting frame can tilt relative to the base in the front-to-back direction under the drive of the tilting drive mechanism.

[0028] Furthermore, the support leg includes a main support leg, a bracket, and a leveling support leg. The main support leg is located below the two transverse sliding frames, and the bracket is fixed below the main support leg. Leveling support legs are located on the left and right sides of the bracket. The leveling support leg further includes a sleeve and a telescopic rod. The sleeve is fixed to the left and right sides of the bracket, and the telescopic rod is located inside the sleeve, allowing it to extend and retract relative to the sleeve.

[0029] Furthermore, in the transportation state of steps S1) and S8), the gantry crane device is fixed longitudinally at intervals on the longitudinal guide rail to accommodate vehicle clearance. In the placement state of step S2), after one gantry crane device is placed, the next gantry crane device is transported to the designated position via the longitudinal guide rail and clamped and flipped by the take-up and release device. In the recovery state of step S7), after one gantry crane device is recovered, the longitudinal guide rail moves to make room, and the next gantry crane device is clamped, flipped, and placed in the designated position via the longitudinal guide rail for recovery.

[0030] Furthermore, in the placement operation state of step S2), after the deployment device clamps and flips the first gantry crane device above the placement position, the outriggers of the gantry crane device move to both sides of the crossbeam, the leveling outriggers extend downwards to near the ground, the clamping mechanism of the deployment device releases, and each leveling outrigger extends to level the gantry crane device. The first transport flatcar moves forward, repeating the above gantry crane device placement action until all gantry crane devices are placed in the designated positions and leveled.

[0031] Furthermore, in the recovery operation state of step S7), the old track components are lifted by a swarm of cranes, and the second transport flatcar enters in the opposite direction. After the swarm of cranes places the old track components on the second transport flatcar, the lifting chains of the gantry crane device are released. The train continues to travel in the opposite direction, and the gantry crane devices are retrieved one by one onto the first transport flatcar by the take-up and release device. In step S8), after all gantry crane devices have been retrieved, all equipment is fixed on the first and second transport flatcars, and the train departs, completing the replacement operation.

[0032] Furthermore, during the replacement operation in steps S3) to S6), the lifting chain of the gantry crane connects to the new track main component, lifting it, while the second transport flatcar continues to move forward until it leaves the work area. The new track main component is then moved laterally by a group of cranes to a stable position near the outriggers. The old track main component is then lifted, moved laterally, and placed on the other side. Finally, the new track main component is lifted and placed in the original position of the old track main component, thus completing the replacement of the old and new track main components.

[0033] By implementing the technical solution of the track replacement method provided in this application, the following beneficial effects are achieved:

[0034] (1) The track replacement method of this application simplifies the structure of the gantry crane deployment device. The original lifting, rotating and clamping deployment mechanism is changed to a flip-type deployment structure for placing and retrieving the gantry crane device. The gantry crane device does not need to be lifted or rotated when it is deployed. It can be directly flipped for deployment, which shortens the operation time and makes the operation more convenient.

[0035] (2) The track replacement method of this application simplifies the structure of the gantry crane device. The crossbeam adopts a three-section folding arm structure, which can be placed on the flatbed without rotating the gantry crane device, thus ensuring that the transportation process does not exceed the limit. At the same time, the outriggers of the gantry crane device only need to adopt a single-stage lifting structure for leveling, which further simplifies the operation process and greatly reduces the cost.

[0036] (3) The track replacement method of this application adopts a three-section folding arm beam structure for the gantry crane device and a flip-type loading and unloading structure for the loading and unloading device, which greatly improves the transport capacity of the gantry crane device of a single flatbed truck. Because the original structure of the gantry crane device is placed longitudinally after rotation and because of its long length, a single truck can only hold about 4 gantry crane devices. However, this application adopts a transverse placement of the gantry crane device, which allows a single truck to hold more than 6 gantry crane devices. Attached Figure Description

[0037] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the accompanying drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of this application. For those skilled in the art, other embodiments can be obtained based on these drawings without creative effort.

[0038] Figure 1 This is a front structural diagram of the gantry crane device in a specific embodiment of the track large rail component replacement operation system on which the method of this application is based;

[0039] Figure 2 This is a schematic top view of the gantry crane device in a specific embodiment of the track large component replacement operation system on which the method of this application is based;

[0040] Figure 3 This is a side view of the gantry crane device in a specific embodiment of the track large rail component replacement operation system on which the method of this application is based;

[0041] Figure 4 This is a front structural diagram of the gantry crane device in a folded state in a specific embodiment of the track large rail component replacement operation system on which the method of this application is based;

[0042] Figure 5This is a schematic top view of the gantry crane device in a folded state in a specific embodiment of the track large component replacement operation system on which the method of this application is based;

[0043] Figure 6 This is a side view of the gantry crane device in a folded state in a specific embodiment of the track large component replacement operation system on which the method of this application is based;

[0044] Figure 7 This is a three-dimensional structural diagram of the gantry crane device in a specific embodiment of the track large rail component replacement operation system on which the method of this application is based;

[0045] Figure 8 This is a schematic side view of the installation structure of the take-up and put-down device in a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0046] Figure 9 This is a schematic top view of the installation structure of the take-up and put-down device of a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0047] Figure 10 This is a schematic front view of the installation structure of the take-up and put-down device in a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0048] Figure 11 This is a side view of the take-up and put-down device in a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0049] Figure 12 This is a side view of the take-up and take-up device in operation state in a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0050] Figure 13 This is a schematic top view of the structure of the take-up and take-up device in operation state in a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0051] Figure 14 This is a schematic front view of the structure of the take-up and take-up device in operation state in a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0052] Figure 15 This is a three-dimensional schematic diagram of the take-up and take-up device in operation state in a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0053] Figure 16 This is a three-dimensional schematic diagram of the working state of the take-up and put-down device from another perspective in a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0054] Figure 17 This is a three-dimensional schematic diagram of the working state of the take-up and put-down device from a third perspective in a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0055] Figure 18 This is a side view of the working principle of the take-up and drop device of a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0056] Figure 19 This is a top view of the working principle of the take-up and put-down device of a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0057] Figure 20 This is a schematic diagram of the working principle of the take-up and put-down device in the A-view direction, representing a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0058] Figure 21 This is a schematic diagram of the working principle of the take-up and put-down device in the B-view direction, representing a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0059] Figure 22 This is a schematic diagram of the working principle of the take-up and put-down device in the C-view direction, representing a specific embodiment of the track large rail component laying and replacement operation system on which the method of this application is based;

[0060] Figure 23 This is a schematic front view of the structure in the transportation state of a specific embodiment of the track component replacement operation method based on this application;

[0061] Figure 24 This is a schematic top view of the structure in the transportation state of a specific embodiment of the track component replacement operation method based on this application;

[0062] Figure 25 This is a schematic front view of the structure of a specific embodiment of the track component replacement method based on this application, in the operation state of the take-up and deployment device;

[0063] Figure 26 This is a schematic top view of the structure of a specific embodiment of the track component replacement method based on this application, in the operating state of the take-up and deployment device;

[0064] Figure 27 This is a schematic diagram of the operation status of the take-up and release device in a specific embodiment of the track large component laying and replacement operation method based on this application;

[0065] Figure 28 This is a schematic diagram of the operation state of the take-up and release device from another perspective, based on a specific embodiment of the track large component replacement operation method of this application.

[0066] Figure 29 This is a schematic diagram of the operation status of the take-up and release device from a third perspective, based on a specific embodiment of the track large component replacement operation method of this application.

[0067] Figure 30 This is a schematic front view of the gantry crane device in the placement state, based on a specific embodiment of the track component replacement operation method of this application.

[0068] Figure 31 This is a schematic top view of the gantry crane device in the placement state of a specific embodiment of the track component replacement operation method based on this application;

[0069] Figure 32 This is a schematic front view of the structure of a specific embodiment of the track large component replacement operation method based on this application, under the condition of unloading new track large components;

[0070] Figure 33 This is a schematic top view of the structure of a specific embodiment of the track large component replacement operation method based on this application, under the condition of unloading new track large components;

[0071] Figure 34 This is a schematic top view of the structure of a specific embodiment of the track large component replacement operation method based on this application, under the condition of replacing new track large components;

[0072] Figure 35 This is a schematic diagram of the gantry crane device recovery operation status according to a specific embodiment of the track large component replacement operation method based on this application;

[0073] Figure 36 This is a schematic diagram of the gantry crane recovery operation status from another perspective, based on a specific embodiment of the track component replacement operation method of this application.

[0074] Figure 37 This is a schematic diagram of the gantry crane recovery operation status from a third perspective, based on a specific embodiment of the track component replacement method of this application.

[0075] In the diagram: 1-Gantry crane device, 2-Retracting and extending device, 3-First transport flatcar, 4-Second transport flatcar, 5-Rail car, 6-Power unit, 7-Rail main component, 71-New rail main component, 72-Old rail main component, 8-Longitudinal guide rail, 9-Rail, 101-Main beam, 102-Folding arm, 103-Main support leg, 104-Sleeve, 105-Telescopic rod, 106-Lifting mechanism, 107-Horizontal sliding frame, 108-Lifting chain, 109-Folding drive mechanism, 110-Bracket, 201-Tilting frame, 202-Base, 203-Tilting drive mechanism, 204-Clamping mechanism, 205-Connecting rod. Detailed Implementation

[0076] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of this application, and not all of them. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.

[0077] As attached Figure 1 To be continued Figure 37 As shown, a specific embodiment of the track replacement method of this application is given. The application will be further described below with reference to the accompanying drawings and specific embodiments.

[0078] Example 1

[0079] As attached Figure 1 To be continued Figure 22 As shown, an embodiment of the track large component replacement operation system upon which this application is based specifically includes:

[0080] The railcar 5, the first transport flatcar 3, and the second transport flatcar 4 are coupled together;

[0081] In transport, it is folded horizontally (as shown in the attached image). Figure 9 and attached Figure 13 (In the direction shown by T) placed on the first transport flatcar 3, with no fewer than two gantry crane devices 1;

[0082] A deployment and retrieval device 2, installed on the first transport flatcar 3 or the second transport flatcar 4, enables the placement or retrieval of the gantry crane device 1. For example, in this embodiment, the deployment and retrieval device 2 is specifically installed on the first transport flatcar 3 along its longitudinal direction (as shown in the attached diagram). Figure 8 and attached Figure 9 It is located on one side of the direction shown in the middle L, and is set close to the second transport flatcar 4.

[0083] Two longitudinal guide rails 8 are arranged parallel to each other along the longitudinal direction on the first transport flatcar 3. A power unit 6 is also arranged between the two longitudinal guide rails 8, which provides operating power to the take-up and drop device 2. The power unit 6 can be of different types: battery driven or generator driven, and the actuator can be electric driven or hydraulically driven, etc. Each set of folding gantry crane devices 1 adopts an individual drive or a centralized unified power drive mode. In the gantry crane device placement operation state, the gantry crane device 1 is transported to the designated position by the longitudinal guide rails 8 set on the first transport flatcar 3, and is clamped and flipped by the take-up and drop device 2. The gantry crane device 1 is then placed on the track after being extended to the normal state.

[0084] As attached Figure 1 To be continued Figure 7As shown, the gantry crane device 1 further includes:

[0085] The crossbeam further includes a main beam 101 and folding arms 102 respectively hinged to the left and right sides of the main beam 101.

[0086] The transverse sliding frame 107 is movably installed at both ends of the crossbeam, and the transverse sliding frame 107 can move laterally along the crossbeam (as shown in the attached figure). Figure 7 Move in the direction shown in the middle (W) to adjust the lateral span of the gantry crane 1;

[0087] The lifting mechanism 106, which is installed on the crossbeam and located between the two transverse sliding frames 107, can move laterally along the crossbeam to adjust the transverse lifting position of the large track component 7.

[0088] A lifting chain 108 connected to the lifting mechanism 106 is used for lifting the large rail component 7.

[0089] They are respectively set below the two horizontal sliding frames 107, and can move vertically (as shown in the attached figure). Figure 7 The outriggers (in the direction shown by H) extend and retract to adjust the height of the crossbeam from the horizontal plane of the line, and at the same time achieve the leveling of the gantry crane device 1.

[0090] A transverse sliding frame 107 is fitted onto the outside of the crossbeam, and a folding drive mechanism 109 is hinged between the main beam 101 and the folding arm 102. When the deployment and retraction device 2 places the gantry crane 1, the folding drive mechanism 109 drives the folding arm 102 to unfold relative to the main beam 101, and the transverse sliding frame 107 moves towards the outside of the crossbeam to increase the lateral span of the gantry crane 1 and expand its operational range. When the deployment and retraction device 2 retracts the gantry crane 1, the folding drive mechanism 109 drives the folding arm 102 to retract relative to the main beam 101 to reduce the overall width of the gantry crane 1 and prevent it from exceeding its clearance limits during transportation. (See attached diagram) Figure 1 To be continued Figure 3 The image shows the gantry crane 1 in its extended state, as shown in the attached diagram. Figure 4 To be continued Figure 7 The image shows the gantry crane 1 in its folded state.

[0091] As a typical embodiment of this application, the crossbeam can be further specifically adopted as, for example, an I-shaped structure. The crossbeam and the transverse sliding frame 107 can specifically adopt a structure combining guide rails and sliding sleeves, and the transverse sliding frame 107 is driven along the length direction of the crossbeam by a structure such as a hydraulic cylinder, electric cylinder, or electric lead screw (as shown in the attached figure). Figure 7 (In the direction shown by W) movement. The lifting mechanism 106 can use a hoist or other lifting tools. The outriggers are telescopic and can slide on the crossbeam to adjust the span and height of the folding gantry crane 1 to adapt to different site conditions and the replacement of different sized track components 7.

[0092] The outriggers further include main outriggers 103 disposed below the two transverse sliding frames 106, brackets 110 fixed below the main outriggers 103, and leveling outriggers disposed on the left and right sides of the brackets 110. The leveling outriggers further include sleeves 104 fixed on the left and right sides of the brackets 110, and telescopic rods 105 disposed inside the sleeves 104 and capable of telescopic movement relative to the sleeves 104. Two telescopic leveling outriggers are provided at the lower part of each outrigger to achieve leveling of the gantry crane device 1. Their telescopic movement can be achieved using hydraulic cylinders, electric cylinders, or electric screws.

[0093] The gantry crane device 1 described in Example 1 solves the technical problems of existing operating equipment, such as large size, easy violation of railway clearance limits, high cost, long maintenance window occupancy time, low operating efficiency, and low safety. Its structure is simplified, with a three-section folding arm structure for the crossbeam, allowing it to be placed on the transport flatcar without rotating, thus ensuring that the transport process does not exceed clearance limits. Furthermore, the outriggers of the gantry crane device 1 only require a single-stage lifting structure for leveling, further simplifying the operation process and significantly reducing costs.

[0094] As attached Figure 8 To be continued Figure 11 As shown, the take-up and take-down device 2 further includes:

[0095] Base 202 fixed to the body of the first transport flatcar 3 or the second transport flatcar 4;

[0096] A flip frame 201 that is hinged to the base 202 at one end and extends upward at the other end;

[0097] A flipping drive mechanism 203 is hinged between the base 202 and the flipping frame 201;

[0098] A clamping mechanism 204 is hinged to the top of the tilting frame 201 and performs clamping operations on the large track component 7.

[0099] and the connecting rod 205 hinged between the clamping mechanism 204 and the base 202.

[0100] The tilting frame 201, base 202, tilting frame clamping mechanism 204, and connecting rod 205 further form a four-bar linkage. The tilting frame 201, driven by the tilting drive mechanism 203, can move relative to the base 202 in the front-rear direction (as shown in the attached diagram). Figure 8 and attached Figure 11 The direction shown in F is used for the flipping motion.

[0101] The deployment and retraction device 2 is used to unload the gantry crane device 1 from the first transport flatcar 3 onto the track, and to retrieve it from the track back onto the first transport flatcar 3. The deployment and retraction device 2 enables the foldable gantry crane device 1 to be quickly placed onto the track and quickly retrieved from the track onto the transport flatcar. The gantry crane device 1, in its transport state, moves longitudinally (as shown in the attached diagram). Figure 12 and attached Figure 13 The intervals (as shown in the L direction) are fixed on the first transport flatcar 3 to accommodate vehicle clearance.

[0102] As a typical specific embodiment of this application, the operating system includes one or more second transport flatcars 4, on which large rail components 7 are placed. Railcars 5, first transport flatcars 3, and second transport flatcars 4 are sequentially coupled. Six to eight gantry crane devices 1 are placed on the first transport flatcar 3. The transport of the large rail component replacement system employs a coupled operation of railcars 5, first transport flatcars 3 carrying gantry crane devices 1, and second transport flatcars 4 transporting large rail components 7. One modified transport flatcar transports multiple folding gantry crane devices 1, while two ordinary transport flatcars transport both new and old large rail components.

[0103] The track replacement system employs multiple (typically 6-8) folding gantry cranes 1 arranged in a group for lifting. The outriggers are telescopic and can slide on the crossbeam, allowing adjustment of the span and height of the folding gantry cranes 1 to adapt to different site conditions and the replacement of track components 7 of varying sizes. Four telescopic leveling outriggers are installed at the lower part of each outrigger to achieve leveling of the gantry crane 1; their extension and retraction are achieved using hydraulic cylinders or electric screws. The lifting mechanism 106 can further utilize a hoist or other lifting devices.

[0104] As attached Figure 12 To be continued Figure 14 As shown, the gantry crane 1 is fixed longitudinally at intervals on the longitudinal guide rail 8 in the transport state to accommodate vehicle clearance. The operation states of the deployment and retrieval device 2 include the placement operation state and the retrieval operation state of the gantry crane 1. (See attached diagram) Figure 15 To be continued Figure 17 As shown, in the gantry crane placement operation state, after one gantry crane 1 is placed, the next gantry crane 1 is transported to the designated position via the longitudinal guide rail 8 and clamped and flipped by the take-up and retraction device 2. In the gantry crane retrieval operation state, after one gantry crane 1 is retrieved, the longitudinal guide rail 8 moves to make room, and the next gantry crane 1 is clamped, flipped, and placed at the designated position via the take-up and retraction device 2 and retrieved via the longitudinal guide rail 8. It should be noted that, as shown in the attached... Figure 18 To be continued Figure 20 The diagram shown is merely a schematic representation of the working principle of the take-up and take-down device 2 and does not imply that the take-up and take-down device 2 is installed on both sides of the first transport flatcar 3 along the longitudinal direction.

[0105] The second transport flatcar 4 holds the main track components 7. New main track components 71 are transported to the work site via the second transport flatcar 4. The take-up and drop device 2 unloads the gantry cranes 1 one by one from the first transport flatcar 3 according to their positions and sequence, and places them in designated locations. Then, a group of cranes consisting of multiple gantry cranes 1 unloads the new main track components 71 from the second transport flatcar 4 and places them on one side of the track below the gantry cranes 1. The group of cranes then lifts the disassembled old main track components 72 to the other side of the track below the gantry cranes 1. The group of cranes then lifts the new main track components 71 back to the original position of the old main track components 72 on the track, completing the replacement of the old and new main track components. After the track is restored, the group of cranes lifts the old main track components 72, the second transport flatcar 4 enters, places the old main track components 72 on the second transport flatcar 4, and the take-up and drop device 2 retracts the gantry cranes 1 on the track one by one back onto the first transport flatcar 3, which then departs as a group.

[0106] As attached Figure 21 As shown, in the gantry crane placement operation state, after the deployment and retraction device 2 clamps and flips the first gantry crane 1 above the placement position, the outriggers of the gantry crane 1 move to both sides of the crossbeam, the leveling outriggers extend downwards to near the ground, the clamping mechanism 204 of the deployment and retraction device 2 releases, and each leveling outrigger extends to level the gantry crane 1. The first transport flatcar 3 moves forward, repeating the above-mentioned placement action of the gantry crane 1 until all the gantry crane 1s are placed in the designated positions and leveled.

[0107] During the gantry crane's recovery operation, the old track component 72 is lifted by a group of cranes, and the second transport flatcar 4 moves in the opposite direction (i.e., with the attached...). Figure 23 , 24 The train enters in the opposite direction (as shown by L in 25, 26, 30, and 31). After the gantry crane places the old track section 72 onto the second transport flatcar 4, the lifting chain 108 of the gantry crane device 1 is released. The train continues to travel in the opposite direction, and the gantry crane devices 1 are retrieved one by one onto the first transport flatcar 3 via the retraction device 2, as shown in the attached diagram. Figure 22 As shown. After all gantry crane devices 1 have been retrieved, all equipment is secured to the first transport flatcar 3 and the second transport flatcar 4, and then the equipment is assembled and driven away to complete the replacement operation.

[0108] During the track replacement operation, the lifting chain 108 of the gantry crane 1 connects to the new track component 71, lifting the new track component 71. The second transport flatcar 4 continues to move forward until it leaves the work area. The new track component 71 is moved laterally by a group of cranes and placed stably near the outriggers. The old track component 72 is then lifted, moved laterally, and placed on the other side. Finally, the new track component 71 is lifted and placed in the position of the old track component 72 to complete the replacement of the old and new track components.

[0109] Example 2

[0110] In this embodiment, other auxiliary processes such as confirming the support point of the gantry crane, leveling the support point, disassembling the rail fasteners, cutting, welding and grinding the rails, and leveling are omitted. The following describes the main process of the rail replacement method of this application by taking the replacement of the turnout (a typical rail component 7) as an example.

[0111] Appendix Figure 23 To be continued Figure 37 As shown, an embodiment of the track large component replacement operation method of this application based on the system described in Embodiment 1 specifically includes the following steps:

[0112] S1) As attached Figure 23 and attached Figure 24 As shown, several (e.g., 6 to 8) gantry crane devices 1 are placed horizontally in a folded state on the longitudinal guide rail 8 of the first transport flatcar 3 (using a modified flatcar) (to adapt to vehicle clearance). The new track large rail component 71 is placed on two second transport flatcars 4 (using ordinary flatcars). The first transport flatcar 3, the second transport flatcar 4 and the railcar 5 are grouped and coupled together and traveled to the designated position at the replacement work site.

[0113] S2) As attached Figure 25 To be continued Figure 29 As shown, the vehicle formation travels in the direction indicated by L, and the gantry crane 1 is clamped and flipped one by one by the flipping structure of the deployment and retraction device 2. At the same time, after the gantry crane 1 is restored to the unfolded state, it is unloaded from the first transport flatcar 3 according to its position and sequence, and placed in the designated location, as shown in the attached figure. Figure 30 and attached Figure 31 As shown;

[0114] S3) As attached Figure 32 and attached Figure 33 As shown, the new track rail component 71 is unloaded from the second transport flatcar 4 and placed on one side of the track below the gantry crane 1 by a group of cranes consisting of multiple gantry cranes 1.

[0115] S4) As attached Figure 34 As shown, the dismantled old track rail component 72 is hoisted to the other side of the track below the gantry crane device 1 by a group of cranes;

[0116] S5) The new track main rail component 71 is hoisted to the position of the original old track main rail component 72 on the line by a group of cranes to complete the replacement of the old and new track main rail components;

[0117] S6) After the line is restored, the old track rail component 72 will be lifted by a group of cranes, and the second transport flatcar 4 will be oriented towards the attached... Figure 23 , 24Enter in the opposite direction shown by L in 25, 26, 30 and 31, and after placing the old track large rail component 72 on the second transport flatcar 4 by the group crane, release the chain clamp of the gantry crane device 1;

[0118] S7) The vehicle formation continues to travel in the opposite direction to L, using the retraction device 2 to clamp and flip the gantry cranes 1 on the line one by one, and then return them to their folded state before retrieving them onto the first transport flatcar 3, as shown in the attached diagram. Figure 35 To be continued Figure 37 As shown;

[0119] S8) After the gantry crane device 1 is recovered, it is placed horizontally on the first transport flatcar 3 in a folded state. All equipment is fixed on the transport flatcar. The first transport flatcar 3, the second transport flatcar 4 and the railcar 5 are grouped together and driven away in the direction shown by L to complete the replacement operation.

[0120] Two longitudinal guide rails 8 are arranged parallel to each other along the longitudinal direction on the first transport flatcar 3, and a power unit 6 is arranged between the two longitudinal guide rails 8. The power unit 6 can provide operating power for the take-up and take-down device 2.

[0121] In step S2), when the gantry crane is in the placement operation state, the gantry crane 1 is transported to the designated position by the longitudinal guide rail 8 set on the first transport flatcar 3, and is clamped and flipped by the take-up and take-down device 2. The gantry crane 1 is then placed on the line after being extended to the normal state.

[0122] The gantry crane device 1 further includes: a crossbeam, a transverse sliding frame 107, a lifting mechanism 106, a lifting chain 108, and support legs. The crossbeam further includes a main beam 101, with hinged folding arms 102 connected to the left and right sides of the main beam 101. Transverse sliding frames 107 are movably installed at both ends of the crossbeam 101, and can move laterally along the crossbeam to adjust the lateral span of the gantry crane device 1. A lifting mechanism 106 is installed on the crossbeam located between the two transverse sliding frames 107, and can move laterally along the crossbeam to adjust the lateral lifting position of the track main component 7. The lifting chain 108 is connected to the lifting mechanism 106 for lifting the track main component 7. Support legs are installed below the two transverse sliding frames 107, and can extend and retract vertically to adjust the height of the crossbeam above the horizontal plane of the track, thereby achieving leveling of the gantry crane device 1.

[0123] A transverse sliding frame 107 is fitted onto the outside of the crossbeam. One end of the folding drive mechanism 109 is hinged to the main beam 101, and the other end is hinged to the folding arm 102. When the retraction device 2 places the gantry crane device 1, the folding drive mechanism 109 drives the folding arm 102 to unfold relative to the main beam 101, and the transverse sliding frame 107 moves towards the outside of the crossbeam to increase the lateral span of the gantry crane device 1. When the retraction device 2 retracts the gantry crane device 1, the folding drive mechanism 109 drives the folding arm 102 to retract relative to the main beam 101, and the transverse sliding frame 107 moves towards the inside of the crossbeam to reduce the overall width of the gantry crane device 1.

[0124] The take-up and take-down device 2 further includes: a tilting frame 201, a base 202, a tilting drive mechanism 203, a clamping mechanism 204, and a connecting rod 205. The base 202 is fixed to the body of the first transport flatcar 3 or the second transport flatcar 4. One end of the tilting frame 201 is hinged to the base 202, and the other end extends upward and is hinged to the clamping mechanism 204, which can clamp the large track component 7. One end of the tilting drive mechanism 203 is hinged to the base 202, and the other end is hinged to the tilting frame 201. One end of the connecting rod 205 is hinged to the clamping mechanism 204, and the other end is hinged to the base 202. The tilting frame 201, base 202, clamping mechanism 204, and connecting rod 205 form a four-bar linkage, allowing the tilting frame 201 to tilt relative to the base 202 in the front-to-back direction under the drive of the tilting drive mechanism 203.

[0125] The outriggers further include main outriggers 103, brackets 110, and leveling outriggers. The main outriggers 103 are positioned below the two transverse sliding frames 107, and the brackets 110 are fixed below the main outriggers 103. Leveling outriggers are positioned on the left and right sides of the brackets 110. Each leveling outrigger further includes a sleeve 104 and a telescopic rod 105. The sleeve 104 is fixed to the left and right sides of the brackets 110, and the telescopic rod 105 is positioned inside the sleeve 104, allowing it to extend and retract relative to the sleeve 104.

[0126] In the transport state of steps S1) and S8), the gantry crane 1 is fixed longitudinally at intervals on the longitudinal guide rail 8 to accommodate vehicle clearance. In the gantry crane placement state of step S2), after one gantry crane 1 is placed, the next gantry crane 1 is transported to the designated position via the longitudinal guide rail 8 and clamped and flipped by the take-up and release device 2. In the gantry crane retrieval state of step S7), after one gantry crane 1 is retrieved, the longitudinal guide rail 8 moves to make room, and the next gantry crane 1 is clamped, flipped, and placed in the designated position via the longitudinal guide rail 8.

[0127] In the gantry crane placement operation state of step S2), after the deployment and retraction device 2 clamps and flips the first gantry crane 1 above the placement position, the outriggers of the gantry crane 1 move to both sides of the crossbeam, the leveling outriggers extend downwards to near the ground, the clamping mechanism 204 of the deployment and retraction device 2 releases, and each leveling outrigger extends to level the gantry crane 1. The first transport flatcar 3 moves forward, repeating the above gantry crane 1 placement operation until all gantry crane 1s are placed in the designated positions and leveled.

[0128] In step S7), during the gantry crane recovery operation, the old track main component 72 is lifted by a group of cranes, and the second transport flatcar 4 moves in the opposite direction (i.e., attached). Figure 23 , 24 The gantry cranes (in the opposite direction to L) enter the road. After placing the old track components 72 onto the second transport flatcar 4, the lifting chains 108 of the gantry crane 1 are released. The vehicle convoy continues to travel in the opposite direction, and the gantry crane 1s are retrieved one by one onto the first transport flatcar 3 by the retraction device 2.

[0129] During the track replacement operation in steps S3) to S6), the lifting chain 108 of the gantry crane 1 connects the new track component 71, lifts the new track component 71, and the second transport flatcar 4 continues to move forward until it leaves the work area. The new track component 71 is then moved laterally by a group of cranes to a stable position near the outriggers. The old track component 72 is then lifted, moved laterally, and placed on the other side. Finally, the new track component 71 is lifted and placed in the original position of the old track component 72, thus completing the replacement of the old and new track components.

[0130] The track replacement method described in Example 2 can solve the technical problems of large deformation, large swing, low operation efficiency, and long time occupied during the on-site hoisting and replacement of track components. By using multiple folding gantry crane devices 1 to lift and replace track components simultaneously, the system is not only simple in structure, space-saving, and easy to operate, but also has low overall system cost, requires fewer operators, and significantly reduces the time occupied during the skylight.

[0131] In the description of this application, it should be noted that when an element is referred to as being "fixed to" or "set on" another element, it may be directly or indirectly set on another element; when an element is referred to as being "connected to" another element, it may be directly or indirectly connected to another element.

[0132] It should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", and "outer" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are used only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this application.

[0133] Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of this application, "multiple" or "several" means two or more, unless otherwise explicitly specified.

[0134] It should be noted that the structures, proportions, sizes, etc., shown in the accompanying drawings of this specification are only used to complement the content disclosed in the specification for those skilled in the art to understand and read, and are not intended to limit the conditions under which this application can be implemented. Therefore, they have no substantial technical significance. Any modifications to the structure, changes in the proportions, or adjustments to the size, without affecting the effects and purposes that this application can produce, should still fall within the scope of the technical content disclosed in this application.

[0135] By implementing the technical solution of the track replacement method described in the specific embodiments of this application, the following technical effects can be achieved:

[0136] (1) The track large rail component replacement operation method described in the specific embodiments of this application has a simplified structure of the gantry crane take-up and put-down device. The original lifting, rotating, clamping take-up and put-down mechanism has been changed to a flip-type take-up and put-down structure for placing and retrieving the gantry crane device. The gantry crane device does not need to be lifted or rotated when it is taken up and put down. It can be directly flipped up and put down. By using multiple folding gantry cranes to lift and replace the track large rail components, fewer operators are needed, the operation time is shorter, and the process is simpler, clearer and more convenient.

[0137] (2) The track replacement method described in the specific embodiments of this application has a simplified gantry crane structure. The folding beam adopts a three-section folding arm structure and is installed horizontally on the flatcar during transportation. It can be placed on the flatcar without rotating the gantry crane, thus ensuring that the transportation process does not exceed the limit. At the same time, the outriggers of the gantry crane only need to adopt a single-stage lifting structure for leveling, which further simplifies the operation process and greatly reduces the cost. The group lifting operation composed of multiple gantry cranes makes the positioning of the track large components more accurate and the replacement operation safer and more reliable.

[0138] (3) The track replacement method described in the specific embodiments of this application has greatly improved the transport capacity of a single flatbed truck by adopting a three-section folding arm beam structure for the gantry crane device and a flip-type retraction and deployment structure for the deployment and deployment device. Since the original structure of the gantry crane device is placed longitudinally after rotation and because of its long length, a single truck can only hold about 4 gantry crane devices. However, since this application adopts the lateral placement of the gantry crane device, a single truck can hold more than 6 gantry crane devices.

[0139] The various embodiments in this specification are described in a progressive manner, with each embodiment focusing on the differences from other embodiments. The same or similar parts between the various embodiments can be referred to each other.

[0140] The above description is merely a preferred embodiment of this application and is not intended to limit this application in any way. Although this application has been disclosed above with reference to preferred embodiments, it is not intended to limit this application. Any person skilled in the art can make many possible variations and modifications to the technical solutions of this application using the methods and techniques disclosed above, or modify them into equivalent embodiments with equivalent changes, without departing from the spirit and technical essence of this application. Therefore, any simple modifications, equivalent substitutions, equivalent changes, and modifications made to the above embodiments based on the technical essence of this application without departing from the content of the technical solutions of this application shall still fall within the protection scope of the technical solutions of this application.

Claims

1. A method for replacing large track components, characterized in that, Includes the following steps: S1) Several gantry crane devices are placed horizontally on the first transport flatcar in a folded state, and the new rail components are placed on the second transport flatcar. The first transport flatcar, the second transport flatcar, and the railcar are coupled together and travel to the designated location at the replacement work site. S2) The gantry crane devices are clamped and flipped one by one by the flipping structure of the take-up and take-down device. At the same time, after the gantry crane devices are restored to the unfolded state, they are unloaded from the first transport flatcar according to their position and sequence and placed in the designated position. S3) The new track components are unloaded from the second transport flatcar and placed on one side of the track below the gantry cranes by a group of cranes consisting of multiple gantry cranes; S4) The dismantled old track components are hoisted to the other side of the track below the gantry crane using a group of cranes; S5) The new track components are hoisted to the original position of the old track components on the line by a group of cranes to complete the replacement of the old track components with the new ones; S6) After the line is restored, the old track components are lifted by a group of cranes, and the second transport flatcar enters and places the old track components on the second transport flatcar. S7) The gantry crane devices on the line are clamped and flipped one by one by the retraction device, and then returned to the folded state and recycled to the first transport flatcar. S8) The gantry crane device is placed horizontally on the first transport flatcar in a folded state, and the first transport flatcar, the second transport flatcar, and the railcar are assembled and driven away. The take-up and take-down device includes: a base, a tilting frame, a tilting drive mechanism, a clamping mechanism, and a connecting rod; the base is fixed to the body of the first transport flatcar or the second transport flatcar; One end of the flipping frame is hinged to the base, and the other end extends upward and is hinged to the clamping mechanism, which can clamp the large track components; one end of the flipping drive mechanism is hinged to the base, and the other end is hinged to the flipping frame; one end of the connecting rod is hinged to the clamping mechanism, and the other end is hinged to the base; the flipping frame, the base, the flipping frame clamping mechanism, and the connecting rod form a four-bar linkage, and the flipping frame can flip relative to the base in the front-back direction under the drive of the flipping drive mechanism.

2. The method for replacing large track components according to claim 1, characterized in that: Two longitudinal guide rails are arranged parallel to each other along the longitudinal direction on the first transport flatcar, and a power unit is arranged between the two longitudinal guide rails. The power unit can provide operating power for the take-up and take-down device.

3. The method for replacing large track components according to claim 2, characterized in that: In step S2), during the placement operation, the gantry crane is transported to the designated position via the longitudinal guide rail set on the first transport flatcar, and is clamped and flipped by the take-up and take-down device. The gantry crane is then placed on the line after being extended to the normal state.

4. The method for replacing large track components according to claim 2 or 3, characterized in that, The gantry crane device includes: a crossbeam, a transverse sliding frame, a lifting mechanism, a lifting chain, and outriggers; the crossbeam further includes a main beam, with hinged folding arms on the left and right sides of the main beam; transverse sliding frames are movably installed at the left and right ends of the crossbeam, and the transverse sliding frames can move laterally along the crossbeam to adjust the lateral span of the gantry crane device; a lifting mechanism is installed on the crossbeam located between the two transverse sliding frames, and the lifting mechanism can move laterally along the crossbeam to adjust the lateral lifting position of the large track components; the lifting chain is connected to the lifting mechanism for lifting the large track components; outriggers are installed below the two transverse sliding frames, and the outriggers can extend and retract vertically to adjust the height of the crossbeam from the horizontal plane of the track, while simultaneously achieving leveling of the gantry crane device.

5. The method for replacing large track components according to claim 4, characterized in that: The lateral sliding frame is fitted onto the outside of the crossbeam. One end of the folding drive mechanism is hinged to the main beam, and the other end is hinged to the folding arm. When the retraction device places the gantry crane, the folding drive mechanism drives the folding arm to unfold relative to the main beam, and the lateral sliding frame moves toward the outside of the crossbeam to increase the lateral span of the gantry crane. When the retraction device retracts the gantry crane, the folding drive mechanism drives the folding arm to retract relative to the main beam, and the lateral sliding frame moves toward the inside of the crossbeam to reduce the overall width of the gantry crane.

6. The method for replacing large track components according to claim 5, characterized in that: The support leg includes a main support leg, a bracket, and a leveling support leg. The main support leg is located below the two transverse sliding frames, and the bracket is fixed below the main support leg. Leveling support legs are located on the left and right sides of the bracket. The leveling support leg further includes a sleeve and a telescopic rod. The sleeve is fixed on the left and right sides of the bracket, and the telescopic rod is located inside the sleeve. The telescopic rod can extend and retract relative to the sleeve.

7. The method for replacing large track components according to any one of claims 1, 2, 3, 5, and 6, characterized in that: In the transportation state of steps S1) and S8), the gantry crane device is fixed longitudinally at intervals on the longitudinal guide rail to adapt to the vehicle clearance. In the placement state of step S2), after the previous gantry crane device is placed, the next gantry crane device is transported to the designated position through the longitudinal guide rail and is clamped and flipped by the take-up and release device. In the recovery state of step S7), after the previous gantry crane device is recovered, the longitudinal guide rail moves to make room, and the next gantry crane device is clamped, flipped and placed in the designated position by the take-up and release device and recovered through the longitudinal guide rail.

8. The method for replacing large track components according to claim 7, characterized in that: In the placement operation state of step S2), after the take-up and drop device clamps the first gantry crane device and flips it above the placement position, the outriggers of the gantry crane device move to both sides of the crossbeam, the leveling outriggers extend downwards to near the ground, the clamping mechanism of the take-up and drop device is released, and each leveling outrigger extends to level the gantry crane device; the first transport flatcar moves forward and repeats the above gantry crane device placement action until all gantry crane devices are placed in the designated position and leveled.

9. The method for replacing large track components according to any one of claims 1, 2, 3, 5, 6, and 8, characterized in that: In the recovery operation state of step S7), the old track large rail component is lifted by a group of cranes, the second transport flatcar enters in the opposite direction, the group of cranes places the old track large rail component on the second transport flatcar, and the lifting chain of the gantry crane device is released; the group continues to travel in the opposite direction, and the gantry crane devices are retrieved one by one onto the first transport flatcar by the take-up and release device; in step S8), when all gantry crane devices have been retrieved, all equipment is fixed on the first transport flatcar and the second transport flatcar, the group departs, and the replacement operation is completed.

10. The method for replacing large track components according to claim 9, characterized in that: During the replacement operation in steps S3) to S6), the lifting chain of the gantry crane connects the new track main component and lifts it. The second transport flatcar continues to move forward until it leaves the work area. The new track main component is moved laterally by a group of cranes and placed stably on one side near the outrigger. The old track main component is lifted, moved laterally, and placed on the other side. Then, the new track main component is lifted and placed in the original position of the old track main component to complete the replacement of the old and new track main components.

Citation Information

Patent Citations

  • Turnout replacement device and system

    CN114701954A

  • Railway line component laying and replacing gantry crane device and operation method thereof

    CN114808567A

  • Hoisting vehicle and method for replacing of long and heavy parts of high-speed railway turnout

    CN107476146A

  • Railway line component laying and replacing operation method

    CN114775344A