Construction method of offshore deep-buried steel pipe pile with disc plate
By combining the base plate of the support plate with the steel pipe pile in the deep-buried steel pipe pile construction method at sea, and combining the rotary blade conveying mixture and grouting technology, the problems of slow construction speed and high cost of marine engineering foundations have been solved, and rapid and low-cost marine foundation construction has been achieved.
Patent Information
- Application Number
- CN202310354881.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-03-22
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2043-03-22
AI Technical Summary
Existing marine engineering foundation construction is slow and costly, and the commonly used shallow foundations are difficult to apply due to seabed scouring, resulting in high construction difficulty and high cost.
The offshore deep-buried steel pipe pile construction method is adopted. By connecting the support plate and stiffening plate in the middle of the steel pipe pile, the mixture is pressurized and transported to form a pit by rotating blades, and cement grout or concrete is injected. The support plate and steel pipe pile are used in combination to make full use of the bearing capacity of the deep seabed foundation soil and quickly drive into the predetermined depth.
It improves construction speed, reduces material and equipment requirements, significantly saves costs, enhances compressive strength, overturning resistance, and sliding resistance, and adapts to seabed scouring environments.
Smart Images

Figure CN116289924B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to a method for constructing deep-buried steel pipe piles at sea in the field of marine engineering. Background Technology
[0002] Offshore wind power, cross-sea bridges, offshore islands and reefs, and offshore engineering platforms are among the marine engineering projects currently experiencing rapid development. Marine engineering projects are conducted in the vast ocean, making them highly susceptible to weather, tides, and waves, resulting in significantly different construction conditions compared to land-based engineering. Marine engineering construction typically requires vessels as construction platforms; the equipment is large and expensive, and the cost of marine foundation engineering construction largely depends on the construction speed and the operating costs of the equipment. Marine foundation engineering construction involves inserting components into the soil below the seabed. Given the varying depths and diverse seabed geological conditions, construction is challenging and costly. Currently, the main forms of marine engineering foundations include large-diameter steel pipe piles, large-diameter bored piles, floating foundations, and suction cylinder foundations. Steel pipe piles and bored piles have very large diameters and deep penetration depths, typically 3–7 meters in diameter and 50–80 meters in depth. Existing large-diameter steel pipe piles offer advantages such as fast construction speed, but their long lengths require large construction equipment and result in high material and construction costs. Offshore bored piles have long construction cycles, often requiring a month or even longer for a single pile, and also suffer from high costs. Due to seabed erosion, shallow foundations commonly used on land are difficult to apply. Therefore, the development of marine engineering foundations that are fast to construct, low in cost, and safe and reliable is urgently needed. Summary of the Invention
[0003] The purpose of this invention is to provide a construction method for deep-buried steel pipe bearing piles at sea. This method can realize the construction of deep-buried steel pipe bearing piles in the ocean, and can significantly improve the compressive strength, overturning resistance, and sliding resistance of steel pipe piles by utilizing deep-buried bearing plates. It also features fast construction speed and low cost.
[0004] This method for constructing deep-buried steel pipe piles at sea includes the following steps:
[0005] a) Fabricate large-diameter steel pipe piles, connect the support plate to the middle of the steel pipe pile, connect the stiffening plate between the support plate and the steel pipe pile, complete the fabrication of the steel pipe support pile, and determine the shape, size and embedment depth of the steel pipe pile and the support plate.
[0006] b) Determine the pile location, cut the foundation soil at the pile location, and mix the foundation soil with water to form a fluid mixture;
[0007] c) The mixture generated during construction in step b) is pumped into a conveying pipeline. The mixture in the conveying pipeline is pressurized by rotating blades and conveyed to the outside of the impact area of the pile foundation construction.
[0008] d) Repeat steps b) to c) to form a pit in the seabed foundation soil that can hold the support plate made in step a). The depth of the pit must meet the burial depth requirement of the support plate determined in step a).
[0009] e) Hoist the steel pipe support piles made in step a) to the location of the pit formed in step d), and drive the steel pipe support piles into the predetermined depth.
[0010] f) Cut the foundation soil outside the influence range of the pile foundation and mix the foundation soil with water to form a fluid mixture;
[0011] g) The mixture generated during construction in step f) is pumped into the conveying pipeline. The mixture in the conveying pipeline is pressurized by rotating blades and conveyed to the pit formed during construction in step d). The pit is then backfilled to the predetermined height.
[0012] In the above-mentioned method for constructing deep-buried steel pipe piles at sea, in step e), before the pile driving, one or more combinations of cement grout, mortar, or concrete are injected into the pit formed in step d) to level the bottom of the pit.
[0013] In the above-mentioned construction method of deep-buried steel pipe bearing piles at sea, in step g), grouting is carried out at the bottom of the bearing base plate to fill the gap between the foundation soil and the bearing base plate.
[0014] The offshore deep-buried steel pipe bearing pile construction method of the present invention can meet the requirements for seabed scour depth control. It can utilize the bearing capacity of the deep seabed foundation soil and combine the bearing plate with the steel pipe pile. It has high bearing capacity and fast construction speed. Compared with the existing offshore steel pipe pile construction technology, it can save a lot of steel pipe materials and has low requirements for pile driving equipment. Compared with other offshore foundation construction technology, it can also significantly save costs and shorten the construction period. Attached Figure Description
[0015] Figure 1 This is a schematic cross-sectional view of a deep-buried steel pipe support pile structure used in an embodiment of the present invention.
[0016] Figure 2 A schematic diagram of the cross-section of the pit formed after the fourth step of a method for constructing deep-buried steel pipe piles at sea, as used in an embodiment of the present invention.
[0017] Figure 3 A schematic diagram showing the working condition after the fifth step of a method for constructing deep-buried steel pipe piles at sea, as used in an embodiment of the present invention;
[0018] Figure 4This is a schematic diagram of the cross-section of the deep-buried steel pipe pile support plate formed after the seventh step of the construction method for a deep-buried steel pipe pile in an embodiment of the present invention.
[0019] Figure 5 This is a schematic plan view of the bottom plate structure of a deep-buried steel pipe pile at sea, used in one embodiment of the present invention.
[0020] Explanation of reference numerals in the attached drawings: 1-Steel pipe pile; 2-Support base plate; 3-Stiffening plate; 4-Foundation connection; 5-Circumferential stiffening plate; 6-Leveling filling layer; 7-Stiffening hoop; 8-Sea level; 9-Seabed; 10-Soil pit. Detailed Implementation
[0021] As an embodiment of the present invention, the following is combined with Figures 1-5 This invention introduces a construction method for deep-buried steel pipe bearing piles at sea and the structural structure of the deep-buried steel pipe bearing piles formed after construction. First, combined with... Figure 4 and Figure 5 This section introduces the structural design of deeply buried steel pipe piles. For example... Figure 4 and Figure 5 As shown, the deep-buried steel pipe bearing pile at sea consists of six parts: steel pipe pile, bearing base plate, stiffening plate, foundation connection, circumferential stiffening plate, and leveling filling layer. The steel pipe pile is a type of pile foundation inserted into the foundation soil below the seabed to provide foundation support for marine engineering. The bearing base plate is a plate-shaped component embedded in the foundation soil below the seabed and connected to the outside of the steel pipe pile. The stiffening plate is a plate-shaped component connecting the bearing base plate and the steel pipe pile. The foundation connection is the connecting component between the steel pipe pile and the superstructure of the marine engineering. The circumferential stiffening plate is a plate-shaped component connecting the bearing base plate and the stiffening plate. The leveling filling layer is a component that densely fills the gap between the bearing base plate and the foundation soil and has compressive bearing capacity. In this embodiment, stiffening hoops can be welded to the outer perimeter of the support plate. The stiffening hoops can be ring-shaped components with the same shape as the support plate. The stiffening hoops can improve the bearing capacity of the support plate and strengthen the interaction between the support plate and the foundation soil. The stiffening hoops can be welded to the lower edge of the support plate. In this embodiment, the steel pipe piles, support plate, stiffening plate, foundation connection, ring stiffening plate, and stiffening hoops can all be steel structures, and adjacent components are connected by welding. In this embodiment, the leveling filling layer can be one or a combination of cement slurry, mortar, and concrete. The following parts of this embodiment mainly combine... Figures 1 to 4 This paper describes the specific implementation steps of the offshore deep-buried steel pipe support pile construction method of the present invention. The first step is to refer to... Figure 1Steel pipe piles are fabricated using large-diameter steel pipes. A support plate is connected to the middle of the steel pipe pile, and a stiffening plate is connected between the support plate and the steel pipe pile to complete the fabrication of the steel pipe support pile body and determine the embedment depth of the support plate. In this step, the steel pipe pile, support plate, stiffening plate, circumferential stiffening plate, and foundation connection can be welded together, meeting the requirements of steel structure design and specifications. The support plate can be circular or polygonal as needed. The diameter, wall thickness, pile length of the steel pipe pile, and the position of the support plate in the steel sheet pile are designed according to the bearing capacity. Generally, a steel pipe pile of a certain length should be designed under the support plate to allow the support plate to act as a pile cap deeply embedded in the soil, working together with the steel pipe pile to provide bearing capacity. In this embodiment, the diameter of the steel pipe pile can be designed to be 3-10m, the wall thickness to be 30-100mm, and the length of the steel pipe pile is closely related to the geological conditions. In this embodiment, the embedment depth of the support plate can be 10-20m, which should be a certain depth below the scour line. The depth of the steel pipe piles below the support plate can be designed to be 10-30m. The size of the support plate is mainly determined based on the foundation design compressive bearing capacity and the bending moment required to resist overturning. The diameter of the support plate can be designed to be 10-30mm, and the thickness of the steel plate can be selected between 30-100mm. The arrangement and size of the stiffening plates and ring stiffening plates can be determined according to the steel structure calculations and construction requirements. After completing the first step, proceed to the second step. According to the design drawings, determine the location of the deeply embedded steel pipe support piles, cut the foundation soil at the pile location, and mix the foundation soil with water to form a mixture. In this step, a rotating drill bit can be used to cut the foundation soil. Alternatively, high-pressure jet grouting piles or MJS (Medium-Screen Jet) systems can be used to cut the soil using high-pressure water jets. A cutterhead can also be installed on a rotating device to cut the soil and rock. Sufficient water is added to the cut soil to form a mixture. When there is enough water and continuous agitation, the cut soil and rock fragments can flow under hydraulic pressure. After completing the second step, proceed to the third step. In this step, the mixture formed in the second step is pumped into a delivery pipeline. Rotating blades pressurize the mixture in the pipeline and transport it to an area outside the impact zone of the pile foundation construction. A suction pump can be installed near the pipeline inlet to draw the soil and rock debris generated in the second step, along with the mixed water, into the pipeline. Rotating blades inside the pipeline then pressurize the mixture and pump it outwards, maintaining a sufficient flow rate to prevent sand and gravel accumulation during pumping. After completing the third step, proceed to the fourth step. This step is a repetition of steps two and three, continuously excavating and transporting the soil and rock at the pile location to an area outside the impact zone of the pile foundation construction, until a pit is formed in the seabed foundation soil. The depth of the pit must meet the burial depth requirements of the support plate, and the shape and size of the pit must meet the requirements for placing the support plate. After completing step four, proceed to step five.In this step, the steel pipe piles fabricated in the first step are hoisted to the location of the pit formed in the fourth step, and then driven into the predetermined depth. In this step, either a vibratory hammer or a hammer-driven method can be used. Because the base plate of the pile supports provides enormous bearing capacity, the required length of the steel pipe pile is much shorter than that of a steel pipe pile without a base plate. For deeply buried steel pipe piles, the base plate only needs to be driven to the bottom of the pit, not into the soil. The length of deeply buried steel pipe piles is much shorter than that of steel pipe piles with the same bearing capacity. Consequently, the driving resistance is significantly reduced, the requirements for driving equipment are greatly reduced, driving efficiency is improved, and construction costs are significantly reduced. In this step, the support plate cannot be driven into the soil. Considering that the flatness of the pit bottom formed in the fourth step is often difficult to ensure full-area close contact with the support plate, the separation problem between the support plate and the soil can be solved by one of the following two methods: The first method is to inject one or more combinations of cement grout, mortar, or concrete into the pit formed in the fourth step before pile driving to level the bottom of the pit. Before these materials solidify, drive the steel pipe piles into the soil, ensuring close contact between the bottom of the support plate and the injected material. A flat surface can be formed before the injected material solidifies, and the support plate can be supported after the injected material solidifies. The second method is to drive the deeply buried steel pipe support piles into the soil in this step. After the support plate contacts the bottom of the pit, a grouting pipe is reserved between the support plate and the bottom of the pit. After the pit is backfilled, grouting is carried out at the bottom of the support plate to fill the gap between the foundation soil and the support plate. After completing step five, proceed to step six. In this step, the foundation soil is cut outside the influence range of the pile foundation, and mixed with water to form a mixture. The construction process in this step is similar to that of step two, except that the construction location is different. After completing step six, proceed to step seven. In this step, the mixture formed in step six is pumped into a delivery pipeline. The mixture in the pipeline is pressurized by rotating blades and transported to the pit formed in step four. The pit is then backfilled to the predetermined height. This step is similar to the construction process of step three, except that the purpose is to backfill the pit. This completes the construction of the deep-buried steel pipe pile foundation at sea according to the present invention.
[0022] This patent includes, but is not limited to, other construction methods or processes that can be used by professionals in the field.
Claims
1. A method for constructing deep-buried steel pipe piles at sea, characterized by: Includes the following steps: a) Fabricate a large-diameter steel pipe pile (1), connect a support plate (2) in the middle of the steel pipe pile (1), connect a stiffening plate (3) between the support plate (2) and the steel pipe pile (1), complete the fabrication of the steel pipe support pile, and determine the shape, size and embedment depth of the steel pipe pile (1) and the support plate (2). b) Determine the pile location, cut the foundation soil at the pile location, and mix the foundation soil with water to form a fluid mixture; c) The mixture generated during construction in step b) is pumped into a conveying pipeline. The mixture in the conveying pipeline is pressurized by rotating blades and conveyed to the outside of the impact area of the pile foundation construction. d) Repeat steps b) to c) to form a pit in the seabed foundation soil that can hold the support plate (2) made in step a), and make the depth of the pit meet the burial depth requirement of the support plate determined in step a). e) Hoist the steel pipe support piles made in step a) to the location of the pit formed in step d), and drive the steel pipe support piles into the predetermined depth. f) Cut the foundation soil outside the influence range of the pile foundation and mix the foundation soil with water to form a fluid mixture; g) The mixture generated during construction in step f) is pumped into the conveying pipeline. The mixture in the conveying pipeline is pressurized by rotating blades and conveyed to the pit formed during construction in step d). The pit is then backfilled to the predetermined height.
2. The construction method for deep-buried steel pipe piles at sea according to claim 1, characterized in that... In step e) above, before the piling construction, one or more combinations of cement grout, mortar or concrete are injected into the pit formed in step d) to level the bottom of the pit formed in step d).
3. The construction method for deep-buried steel pipe piles at sea according to claim 1, characterized in that... In step g) above, grouting is carried out at the bottom of the support plate (2) to fill the gap between the foundation soil and the support plate (2).