An overlength static pressure pipe pile hole drilling construction equipment and a construction process thereof

By using the ultra-long static pressure pipe pile pre-hole construction equipment, combined with the base, hoisting mechanism, pile driving mechanism and pre-hole mechanism, the problem of narrow application range and noise pollution of static pressure pipe pile construction in ultra-long pipe pile driving operations has been solved, and the construction cycle has been shortened and resistance reduced.

CN116289928BActive Publication Date: 2026-11-24CHINA BASE DEV & CONSTR ENG CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202310252574.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-03-15
Publication Date
2026-11-24
Estimated Expiration
2043-03-15

AI Technical Summary

Technical Problem

Existing static pressure pipe pile construction methods are mainly applied to short and medium-sized precast piles, which cannot meet the needs of ultra-long pipe pile driving operations, and there are problems of noise pollution and increased resistance during construction.

Method used

The equipment for drilling ultra-long static pressure pipe piles includes a base, hoisting mechanism, pile driving mechanism and drilling mechanism. Through the cooperation of hydraulic cylinder and limit cylinder, the mortar is diverted and limited during the static pressure pile driving process, which supports the segmented connection of ultra-long pipe piles and reduces construction resistance and noise pollution.

Benefits of technology

It has expanded the application scope of static pressure pipe pile construction, shortened the construction cycle of ultra-long pipe pile driving operations, and reduced noise pollution and construction resistance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116289928B_ABST
    Figure CN116289928B_ABST
Patent Text Reader

Abstract

This application relates to a pre-hole drilling equipment and construction technology for ultra-long static pressure pipe piles, belonging to the technical field of static pressure pipe pile construction equipment. An ultra-long static pressure pipe pile pre-hole drilling equipment includes a base fixed on the ground, a hoisting mechanism mounted on the base, a pile driving mechanism mounted on the base, and a pre-hole drilling mechanism mounted on the base. The pile driving mechanism includes a hydraulic assembly mounted on the base, multiple hydraulic cylinders vertically mounted on the base and connected to the hydraulic assembly, pile driving plates fixed to the telescopic ends of the multiple hydraulic cylinders, and a limiting cylinder fixed to the sidewall of the outer surface of the pipe pile. The limiting cylinder is engaged with the pile driving plate, and the hydraulic cylinders are connected to the hydraulic assembly. This application can ensure the overall integrity of the static pressure pipe pile, is suitable for static pressure construction of ultra-long pipe piles, and can significantly improve the bearing capacity of the static pressure pipe pile.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the technical field of static pressure pipe pile construction equipment, and in particular to a pre-hole construction equipment for ultra-long static pressure pipe piles and its construction process. Background Technology

[0002] Static pressure piling is a common construction method for engineering pile foundations. Static pressure piling involves using a static pile driver to drive precast piles into the soil layer using the pile driving mechanism of the pile driver itself and the reaction force provided by the counterweight on the frame. This pile foundation construction method avoids the vibration, noise, and pollution generated by hammer pile driving and has higher construction efficiency.

[0003] In static pressure pile driving, the power comes from the pressure of hydraulic equipment. As the overall pile length increases and the pile hole depth deepens, the thickness of the soil layer compressed during pile driving increases, significantly increasing the resistance that the precast pile needs to overcome for settlement. Therefore, the pressure exerted on the precast pile by the hydraulic equipment also increases significantly, negatively impacting the integrity of the precast pile and ensuring its bearing capacity. Furthermore, to prevent seepage and collapse in the pile hole, deeper pile holes require backfilling with mortar after completion, further increasing the resistance experienced by the precast pile during driving. Therefore, static pressure pile driving is mainly used for driving medium-to-short precast piles with an overall pile length not exceeding ten meters.

[0004] In view of the above-mentioned technical background, the inventors believe that the existing static pressure pipe pile construction method can only be applied to the driving of short and medium-sized precast column piles, which has the disadvantage of a narrow application range and difficulty in meeting the requirements of ultra-long pipe pile driving operations. Summary of the Invention

[0005] In order to promote the application of static pressure pipe pile construction in ultra-long pipe pile driving operations, shorten the construction cycle of ultra-long pipe pile driving operations, and reduce noise pollution generated during construction, this application provides an ultra-long static pressure pipe pile pre-hole construction equipment and its construction process.

[0006] Firstly, the technical solution adopted in this application for a pre-hole construction device for ultra-long static pressure pipe piles is as follows: An ultra-long static pressure pipe pile pre-hole construction device includes a base fixed on the ground, a hoisting mechanism on the base, a pile driving mechanism on the base, and a pre-hole drilling mechanism on the base. The pile driving mechanism includes a hydraulic assembly on the base, a plurality of hydraulic cylinders vertically mounted on the base and connected to the hydraulic assembly, pile driving plates fixed on the telescopic ends of the plurality of hydraulic cylinders, and a limiting cylinder fixed on the side wall of the outer surface of the pipe pile. The limiting cylinder is engaged with the pile driving plate, and the hydraulic cylinders are connected to the hydraulic assembly.

[0007] By adopting the above technical solution, the base provides stable support for the other parts of the structure of this application, which facilitates the installation of the pile driving mechanism and the adjustment of the relative position between the pile driving mechanism and the pile hole. The hoisting mechanism installed on the base can hoist the static pressure pipe pile to the designated position of the pile driving mechanism, which facilitates the start of static pressure pile driving. The pre-drilling mechanism can excavate the mortar in the static pressure pipe pile through drilling and digging during the static pressure pile driving process, reducing the resistance encountered by the static pressure pipe pile during the pile driving process. The limiting cylinder plays a role in protecting the integrity of the precast pile and can also be used for the segmented connection of ultra-long pipe piles. Thus, the invention aims to promote the application of static pressure pipe pile construction in ultra-long pipe pile driving operations, shorten the construction cycle of ultra-long pipe pile driving operations, and reduce noise pollution generated during construction.

[0008] Optionally, the pile driving plate includes a plate body connected to the telescopic end of the hydraulic cylinder and a plurality of locking blocks slidably connected to the plate body in a direction parallel to the plate surface; the plate body has a through hole in a direction perpendicular to the surface, the locking block is disposed on the hole wall of the through hole, a compression spring is provided between the locking block and the plate body, and the locking block is engaged with the limiting cylinder.

[0009] By adopting the above technical solution, the plate body in the pile driving plate is connected to the telescopic end of the hydraulic cylinder, so that the pressure of the hydraulic cylinder can be transmitted to the static pressure pipe pile through the plate body. The through hole opened on the plate body allows the pile driving plate to be sleeved on the outer wall of the static pressure pipe pile. The locking block installed on the side wall of the through hole can lock into the limiting cylinder installed on the outer wall of the static pressure pipe pile when the pile driving plate moves downward, thereby transmitting pressure. It can also retract into the plate body when moving upward. The compression spring installed between the locking block and the plate body plays a reset role, so that the locking block can lock into the limiting cylinder again.

[0010] Optionally, a plurality of connecting pieces are vertically provided on the plate body, and the plurality of connecting pieces are vertically connected to the side wall of the extension end of the hydraulic cylinder and are evenly distributed along the circumference of the extension end of the hydraulic cylinder.

[0011] By adopting the above technical solution, multiple connecting pieces vertically connected to the extension and retraction end of the hydraulic cylinder on the plate can enhance the strength of the connection structure between the plate and the hydraulic cylinder, making the pushing and pulling process of the hydraulic cylinder on the plate more stable.

[0012] Optionally, the limiting cylinder includes a hinge shaft, two limiting plates sleeved on the hinge shaft, and a plurality of pins passing through the limiting plates in a direction perpendicular to the axis of the limiting plates; the limiting plate is an arc-shaped plate with a semi-circular cross-section, and the outer surface of the limiting plate is provided with ratchet teeth.

[0013] By adopting the above technical solution, the structural design of the two limiting plates of the limiting cylinder being hinged to each other can facilitate the process of fixing the limiting cylinder to the static pressure pipe pile, reduce the friction generated during the installation of the precast pile and the limiting cylinder, and play a protective role for the precast pile structure. The pin installed on the limiting plate can fix the relative position between the precast pile and the limiting plate.

[0014] Optionally, a welding ring is provided at one end of the limiting plate; the inner diameter of the welding ring is equal to the outer diameter of the limiting plate.

[0015] By adopting the above technical solution, the welding ring structure at the end of the limiting plate can facilitate the construction personnel to connect the limiting cylinder end by end by welding. The setting of the welding ring can reduce the welding difficulty and improve the welding performance and structural strength of the connection position.

[0016] Optionally, a limiting block is fixedly provided at one end of the pin, and a thread is provided on the surface of the other end of the pin.

[0017] By adopting the above technical solution, the limiting block structure set at one end of the pin shaft plays a role in limiting the position of the pin shaft, which can prevent the pin shaft from disengaging from the limiting cylinder, and the threaded structure set on the surface of the other end of the pin shaft can be used to install nuts for fixing.

[0018] Optionally, the base includes a support rail fixed on the ground and a movable platform slidably connected to the support rail; the movable platform includes a support frame slidably connected to the support rail, a platform plate slidably connected to the support frame in a direction perpendicular to the support rail, and a counterweight box fixedly disposed below the platform plate.

[0019] By adopting the above technical solution, the support rail can support the mobile platform on the one hand, and enable the mobile platform to move along the length of the support rail on the other hand, thereby realizing hole operation. The structural design of the sliding connection between the platform plate and the support frame in the mobile platform enables the platform plate to move along the length of the vertical support rail, thereby realizing hole operation.

[0020] Optionally, the drilling mechanism includes a screw vertically mounted on the base, a power head sleeved on the screw, and a multi-segment drill rod; the multi-segment drill rod is fixedly connected to the power head.

[0021] By adopting the above technical solution, the screw can be used to control the lifting and lowering of the power head, which can provide power for the rotation of the multi-section drill rod and drive the lifting and lowering of the multi-section drill rod. The multi-section drill rod can excavate and divert the mortar inside the static pressure pipe pile to the outside, reducing the resistance encountered by the static pressure pipe pile during the pile driving process.

[0022] Optionally, the drilling mechanism further includes a guide rod; the guide rod is vertically inserted through the power head and slidably connected to the power head.

[0023] By adopting the above technical solution, the guide rod structure in the drilling mechanism can significantly improve the posture stability during the lifting and lowering process of the power head, reduce the collision and friction between the multi-section drill rod and the side wall of the static pressure pipe pile, and help improve the integrity of the overall structure of the static pressure pipe pile and the service life of the multi-section drill rod.

[0024] Secondly, this application provides a pre-hole drilling construction process for ultra-long static pressure pipe piles, which utilizes the pre-hole drilling construction equipment for ultra-long static pressure pipe piles mentioned above, and adopts the following technical solution: A pre-hole construction process for ultra-long static pressure pipe piles includes the following steps: Step 1: Clean and level the construction site, measure and lay out the lines, and mark the positions of the pile holes; Step 2: Use a high-pressure drilling rig to excavate the pile hole to the designed depth, test the soil sample obtained from the drilling, and backfill with mortar after it passes the test. Step 3: Fix the limiting cylinder to the outer wall of the static pressure pipe pile, fix the static pressure pipe pile to the hoisting mechanism and lift it to the pile hole position; Step 4: Vertically introduce the multi-section drill rod into the static pressure pipe pile; Step 5: Simultaneously operate the hydraulic cylinder and power head to perform static pressure and mortar excavation on the static pressure pipe pile until the static pressure pipe pile reaches the specified depth. Step 6: Repeat steps 3 to 4, then weld along the welding ring to fix the static pressure pipe pile. Finally, repeat step 5 until the pile hole at that point is completed.

[0025] By adopting the above technical solution and combining it with the static pressure pipe pile pre-hole construction equipment in this application, the mortar inside the static pressure pipe pile is drained outward while the static pressure pipe pile is driven, thereby reducing the resistance that needs to be overcome when driving the static pressure pipe pile.

[0026] In summary, this application includes at least one of the following beneficial technical effects: 1. The base in this application provides stable support for the other parts of the structure, facilitating the installation of the pile driving mechanism and the adjustment of the relative position between the pile driving mechanism and the pile hole. The hoisting mechanism installed on the base can hoist the static pressure pipe pile to the designated position of the pile driving mechanism, facilitating the start of static pressure pile driving. The pre-drilling mechanism can excavate the mortar in the static pressure pipe pile through drilling and digging during the static pressure pile driving process, reducing the resistance encountered by the static pressure pipe pile during the pile driving process. The limiting cylinder protects the integrity of the precast pile and can also be used for the segmented connection of ultra-long pipe piles, thereby achieving the invention objective of promoting the application of static pressure pipe pile construction in ultra-long pipe pile driving operations, shortening the construction cycle of ultra-long pipe pile driving operations, and reducing noise pollution generated during construction. 2. In this application, the plate body of the pile driving plate is connected to the telescopic end of the hydraulic cylinder, so that the pressure of the hydraulic cylinder can be transmitted to the static pressure pipe pile through the plate body. The through hole opened on the plate body allows the pile driving plate to be sleeved on the outer wall of the static pressure pipe pile. The locking block installed on the side wall of the through hole can be locked into the limiting cylinder installed on the outer wall of the static pressure pipe pile when the pile driving plate moves downward, thereby transmitting pressure. It can also retract into the plate body when moving upward. The compression spring installed between the locking block and the plate body plays a reset role, so that the locking block can be locked into the limiting cylinder again. 3. The limiting cylinder in this application adopts a structure design in which two limiting plates are hinged to each other, which can facilitate the process of fixing the limiting cylinder to the static pressure pipe pile, reduce the friction generated during the installation process of the precast pile and the limiting cylinder, and play a protective role for the precast pile structure. The pin installed on the limiting plate can play a role in fixing the relative position between the precast pile and the limiting plate. Attached Figure Description

[0027] Figure 1 This is a schematic diagram of the structure of a drilling equipment for ultra-long static pressure pipe piles disclosed in the embodiments of this application.

[0028] Figure 2 This is a schematic diagram of the structure of the pile plate in the embodiment of this application.

[0029] Figure 3 This is a schematic diagram of the structure of the limiting cylinder in the embodiments of this application.

[0030] Explanation of reference numerals in the attached drawings: 1. Base; 11. Support rail; 12. Moving platform; 121. Support frame; 122. Platform plate; 123. Counterweight box; 2. Lifting mechanism; 3. Pile driving mechanism; 31. Hydraulic assembly; 32. Hydraulic cylinder; 33. Pile driving plate; 34. Limiting cylinder; 331. Plate; 332. Locking block; 341. Hinge shaft; 342. Limiting plate; 343. Pin shaft; 344. Welding ring; 4. Drill hole mechanism; 41. Screw; 42. Power head; 43. Multi-section drill rod; 44. Guide rod. Detailed Implementation

[0031] The following is in conjunction with the appendix Figure 1 - Appendix Figure 3 This application will be described in further detail.

[0032] Static pressure piling is a common construction method for engineering pile foundations. It involves using a static pile driver to press precast piles into the soil layer using the machine's own weight and the reaction force provided by counterweights on the frame. This method avoids the vibration, noise, and pollution associated with hammer piling and offers higher construction efficiency. The driving force for static pressure piling comes from the pressure of hydraulic equipment. As the pile length and hole depth increase, the thickness of the soil layer compressed during driving increases, significantly increasing the resistance the precast pile needs to overcome. Therefore, the pressure exerted on the precast pile by the hydraulic equipment also increases significantly, negatively impacting the integrity and bearing capacity of the precast pile. Furthermore, to prevent seepage and hole collapse, deeper holes require backfilling with mortar after drilling, further increasing the resistance experienced by the precast pile during driving. Therefore, static pressure piling is primarily used for driving short to medium-sized precast piles with a total length not exceeding ten meters. In order to promote the application of static pressure pipe pile construction in ultra-long pipe pile driving operations, shorten the construction cycle of ultra-long pipe pile driving operations, and reduce noise pollution generated during construction, this application provides an ultra-long static pressure pipe pile pre-hole construction equipment and its construction process.

[0033] Firstly, this application discloses a pre-hole drilling equipment for ultra-long static pressure pipe piles. (Refer to...) Figure 1 An ultra-long static pressure pipe pile pre-hole construction device includes a base 1, a hoisting mechanism 2, a pile driving mechanism 3, and a pre-hole drilling mechanism 4. The base 1 is fixedly installed on the ground, and the hoisting mechanism 2, the pile driving mechanism 3, and the pre-hole drilling mechanism 4 are all installed on the base 1.

[0034] Reference Figure 1 The base 1 includes a support rail 11 and a moving platform 12. The support rail 11 consists of two parallel long rails, which are fixed to the pile position by multiple anchor bolts. The moving platform 12 includes a support frame 121, a platform plate 122, and counterweight boxes 123. The support frame 121 consists of several hydraulically driven adjustable support legs and a limiting metal frame. The platform plate 122 is mounted on the limiting metal frame and is slidably connected to the limiting metal frame in a direction perpendicular to the support rail 11. Therefore, the platform plate 122 has two degrees of freedom, enabling the alignment of the pile position. Several counterweight boxes 123 are installed on the lower surface of the platform plate 122. Appropriate weights can be placed in the counterweight boxes 123 according to actual needs.

[0035] Reference Figure 1The hoisting mechanism 2 is fixedly installed on the platform plate 122 of the base 1. The hoisting mechanism 2 includes a cab, a lifting boom, a slewing mechanism, cables, and a lifting hook. The hoisting mechanism 2 is capable of lifting static pressure pipe piles and placing them at the re-pile mechanism 3.

[0036] Reference Figure 1 The pile driving mechanism 3 includes a hydraulic assembly 31, hydraulic cylinders 32, a pile driving plate 33, and a limiting cylinder 34. The hydraulic assembly 31 is mounted on the platform plate 122 of the base 1, and the hydraulic cylinders 32 are connected to the hydraulic assembly 31. There can be four hydraulic cylinders 32. The hydraulic cylinders 32 are vertically positioned to the ground. Two sets of portal beams are welded parallel to each other on the platform plate 122, and two sets of hydraulic cylinders 32 are installed inverted parallel on the top of each set of portal beams. The pile driving plate 33 is fixedly connected to the telescopic ends of the hydraulic cylinders 32 and has multiple connecting plates welded to it. The connecting plates are evenly distributed along the circumference of the cylindrical telescopic ends of the hydraulic cylinders 32. The limiting cylinder 34 is fixedly installed on the outer sidewall of the static pressure pipe pile.

[0037] Reference Figure 1 and Figure 2 The pile driving plate 33 includes a plate body 331 and a locking block 332. The plate body 331 can be a solid rectangular metal plate with a through hole in the middle. A mounting groove is formed on the side wall of the through hole in the plate body 331. The locking block 332 is installed in the mounting groove, and a compression spring is provided between it and the plate body 331. The locking block 332 structure can achieve unidirectional engagement with the rack structure on the outer surface side wall of the limiting cylinder 34, and the compression spring is used for the reset of the locking block 332 structure.

[0038] Reference Figure 1 and Figure 3 The limiting cylinder 34 includes a hinge shaft 341, a limiting plate 342, pins 343, and a welding ring 344. There are two limiting plates 342. Each limiting plate 342 can be an arc-shaped metal plate with a semi-circular cross-section. The hinge shaft 341 passes through one end of each limiting plate 342, and the limiting plates 342 are rotatably connected to the hinge shaft 341. A toothed groove is formed on the outer surface of each limiting plate 342 along its axial direction. Several pins 343 pass through each limiting plate 342. Each pin 343 is perpendicular to the axial direction of the limiting plate 342. One end of each pin 343 has a limiting block to prevent it from falling off, and the other end has threads for installing a nut. A welding ring 344 is provided at the end of each limiting plate 342. The inner diameter of the welding ring 344 is equal to the outer diameter of the limiting cylinder 34.

[0039] Reference Figure 1The drilling mechanism 4 includes a screw 41, a power head 42, a multi-segment drill rod 43, and a guide rod 44. The screw 41 is vertically mounted on the platform plate 122 of the base 1 and rotatably connected to the platform plate 122. The power head 42 includes a motor and a plate for supporting the motor, the plate being sleeved on the screw 41. The screw 41 can rotate under the action of another drive motor, driving the power head 42 to rise and fall. The multi-segment drill rod 43 is connected to the motor on the power head 42 via a coupling. The motor can drive the multi-segment drill rod 43 to rotate. The multi-segment drill rod 43 can be composed of multiple drill rod segments, suitable for drilling operations at different depths. The guide rod 44 is vertically welded to the platform plate 122, and multiple guide rods 44 can be provided. In this embodiment, there are two guide rods 44, which are parallel and symmetrically arranged on both sides of the screw 41. The guide rod 44 is a solid smooth rod, passing through the plate of the power head 42 and slidably connected to the plate. Secondly, this application discloses a pre-hole construction process for ultra-long static pressure pipe piles, which utilizes the pre-hole construction equipment for ultra-long static pressure pipe piles described above and adopts the following technical solution: A pre-hole construction process for ultra-long static pressure pipe piles includes the following steps: Step 1: Clean and level the construction site, measure and lay out the lines, and mark the positions of the pile holes; Step 2: Use a high-pressure drilling rig to excavate the pile hole to the designed depth, test the soil sample obtained from the drilling, and backfill with mortar after it passes the test. Step 3: Fix the limiting cylinder 34 to the outer wall of the static pressure pipe pile, fix the static pressure pipe pile to the hoisting mechanism 2 and lift it to the pile hole position; Step 4: Vertically introduce the multi-section drill rod 43 into the static pressure pipe pile; Step 5: Simultaneously operate hydraulic cylinder 32 and power head 42 to perform static pressure and mortar excavation on the static pressure pipe pile until the static pressure pipe pile reaches the specified depth. Step 6: Repeat steps 3 to 4, then weld along welding ring 344 to fix the static pressure pipe pile. Finally, repeat step 5 until the pile hole at this point is completed.

[0040] In the above steps, steps 2 and 3 can be performed simultaneously, thereby shortening the overall construction period. When performing the pilot hole operation in step 4, guide ramps need to be pre-set on both sides of the top of the static pressure pipe pile to prevent the diverted mortar from affecting the operation of the equipment.

[0041] The above are preferred embodiments of this application, and are not intended to limit the scope of protection of this application. Therefore, all equivalent changes made to the structure, shape and principle of this application should be covered within the scope of protection of this application.

Claims

1. A pre-hole construction device for ultra-long static pressure pipe piles, characterized in that: The system includes a base (1) fixed on the ground, a hoisting mechanism (2) mounted on the base (1), a pile driving mechanism (3) mounted on the base (1), and a borehole mechanism (4) mounted on the base (1). The pile driving mechanism (3) includes a hydraulic assembly (31) mounted on the base (1), multiple hydraulic cylinders (32) vertically mounted on the base (1) and connected to the hydraulic assembly (31), pile driving plates (33) fixedly mounted on the telescopic ends of the multiple hydraulic cylinders (32), and a limiting cylinder (34) fixedly mounted on the outer sidewall of the pipe pile. The positioning cylinder (34) is engaged with the pile driving plate (33); the pile driving plate (33) includes a plate body (331) connected to the telescopic end of the hydraulic cylinder (32) and a plurality of locking blocks (332) slidably connected to the plate body (331) in a direction parallel to the plate surface; a through hole is provided on the plate body (331) in a direction perpendicular to the surface, the locking blocks (332) are provided on the hole wall of the through hole, a compression spring is provided between the locking blocks (332) and the plate body (331), and the locking blocks (332) are engaged with the positioning cylinder (34); the positioning cylinder (34) includes a hinge shaft. (341) Two limiting plates (342) sleeved on the hinge shaft (341) and a plurality of pins (343) passing through the limiting plate (342) perpendicular to the axis of the limiting plate (342); the limiting plate (342) is an arc-shaped plate with a semi-circular cross-section, and the outer surface of the limiting plate (342) is provided with ratchet teeth; one end of the limiting plate (342) is provided with a welding ring (344); the inner diameter of the welding ring (344) is equal to the outer diameter of the limiting plate (342); the locking block (332) installed on the side wall of the through hole can be used to drive the pile plate (3 3) When moving downwards, it engages with the limiting cylinder (34) installed on the outer wall of the static pressure pipe pile to transmit pressure, and can retract into the plate (331) when moving upwards. The compression spring installed between the locking block (332) and the plate (331) plays a reset role, so that the locking block (332) can engage with the limiting cylinder (34) again. The pin (343) installed on the limiting plate (342) can fix the relative position between the precast pile and the limiting plate (342). The structure of the locking block (332) can achieve unidirectional engagement with the rack structure on the outer surface side wall of the limiting cylinder (34).

2. The drilling equipment for ultra-long static pressure pipe piles according to claim 1, characterized in that: The plate (331) is provided with a plurality of connecting pieces vertically, and the plurality of connecting pieces are vertically connected to the side wall of the extension end of the hydraulic cylinder (32) and are evenly distributed along the circumference of the extension end of the hydraulic cylinder (32).

3. The ultra-long static pressure pipe pile pre-hole construction equipment according to claim 2, characterized in that: One end of the pin (343) is fixedly provided with a limiting block, and the other end of the pin (343) is provided with a thread.

4. The ultra-long static pressure pipe pile pre-hole construction equipment according to claim 3, characterized in that: The base (1) includes a support rail (11) fixed on the ground and a mobile platform (12) slidably connected to the support rail (11); the mobile platform (12) includes a support frame (121) slidably connected to the support rail (11), a platform plate (122) slidably connected to the support frame (121) in a direction perpendicular to the support rail (11), and a counterweight box (123) fixedly installed below the platform plate (122).

5. The drilling equipment for ultra-long static pressure pipe piles according to claim 4, characterized in that: The drilling mechanism (4) includes a screw (41) vertically mounted on the base (1), a power head (42) sleeved on the screw (41), and a multi-segment drill rod (43); the multi-segment drill rod (43) is fixedly connected to the power head (42).

6. The ultra-long static pressure pipe pile pre-hole construction equipment according to claim 5, characterized in that: The hole-guiding mechanism (4) further includes a guide rod (44); the guide rod (44) is vertically inserted through the power head (42) and slidably connected to the power head (42).

7. A pre-hole construction process for ultra-long static pressure pipe piles, employing the pre-hole construction equipment for ultra-long static pressure pipe piles as described in claim 6, characterized in that, Includes the following steps: Step 1: Clean and level the construction site, measure and mark the location of the pile hole; Step 2: Use a high-pressure drilling rig to excavate the pile hole to the design depth, test the soil sample, and backfill with mortar after it passes the test; Step 3: Fix the limiting cylinder (34) on the outer wall of the static pressure pipe pile, fix the static pressure pipe pile to the hoisting mechanism (2) and lift it to the pile hole location; Step 4: Vertically introduce the multi-section drill rod (43) into the static pressure pipe pile; Step 5: Simultaneously operate the hydraulic cylinder (32) and the power head (42) to perform static pressure and mortar excavation on the static pressure pipe pile until the static pressure pipe pile reaches the specified depth; Step 6: Repeat steps 3 to 4, then weld along the welding ring (344) to fix the static pressure pipe pile, and finally repeat step 5 until the pile hole at this point is completed.

Citation Information

Patent Citations

  • Static pressure construction method for prestressed concrete pipe piles through borehole wall protection method

    CN102767181A

  • Static pile press machine for guiding hole and excavating in middle and construction method thereof

    CN113026746A

  • Static pile driver

    CN214738052U