一种对水电站二次调频进行校准调节的方法
By selecting generating units with a large error ratio for calibration and adjustment in the secondary frequency regulation of hydropower stations, the problem of quantitatively measuring the accuracy of secondary frequency regulation of power stations by dispatching in the existing technology has been solved, achieving higher regulation accuracy and error reduction.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- HUANENG LANCANG RIVER HYDROPOWER CO LTD
- Filing Date
- 2023-04-06
- Publication Date
- 2026-07-17
AI Technical Summary
Existing technologies have failed to effectively address the quantitative measurement of the secondary frequency regulation accuracy of power plants by dispatching, resulting in significant randomness in active power regulation errors and failing to meet the dispatching's desired requirement to maximize the accuracy of secondary frequency regulation.
When the secondary frequency regulation of a hydropower station reaches the calibration time threshold and the active power of a single unit has not been completed, the units with an error ratio greater than the calibration accuracy threshold are selected for calibration and regulation. The active power setting value of the units is adjusted to reduce the active power regulation error of the entire plant. The calibration and regulation time and accuracy threshold are set to achieve precise regulation.
It effectively reduces the active power regulation error of hydropower stations, improves the regulation accuracy of secondary frequency regulation, avoids negative impacts on other functions of secondary frequency regulation, and ensures that regulation delay and rate indicators are not affected.
Smart Images

Figure CN116316700B_ABST
Abstract
Citation Information
Patent Citations
Active power output control parameter pre-processing method for hydropower station during automatic power generation
CN105811473A
Hydropower station AGC active allocation method based on unit commitment output model
CN105870979A
Hydropower station automatic generation active output control method
CN105914795A
Hydropower station AGC combined output model and combined operation region calculation method
CN106056236A
A method for active power control of hydropower units in dual-suggestion operating zones
CN111654068B