A data center energy saving control method and device
By collecting and clustering historical data in the data center, the target historical data with the lowest energy consumption is selected, and the cooling system configuration is optimized in real time. This solves the problem of inaccurate cooling system control and enables low-energy operation of the data center.
Patent Information
- Application Number
- CN202310343049.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-03-29
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2043-03-29
AI Technical Summary
Existing data centers cannot precisely control their cooling systems, leading to resource waste and failing to meet energy consumption reduction requirements.
By periodically collecting historical data from the data center, using clustering algorithms to process the data, selecting target historical data with the lowest energy consumption, and matching it with current operating parameters in real time to optimize the cooling system configuration.
It enables precise cooling control of data centers under different load and environmental conditions, reducing total energy consumption and saving resources.
Smart Images

Figure CN116398998B_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of data center technology, and in particular to a data center energy-saving control method and device. Background Technology
[0002] While ensuring the secure operation of IT services, data center cooling technology is crucial. However, excessive cooling output also leads to significant energy consumption. Energy consumption is a critical issue today, and energy conservation and emission reduction are essential requirements for the future development of data centers. Data center optimization based solely on human experience cannot adequately meet the demands for energy reduction.
[0003] Currently, in traditional data centers, if the equipment is not modified and cannot be automated at the customer's request, most old data centers can only rely on expert experience for equipment control. However, the experience levels of data center experts vary, which cannot achieve high efficiency and energy saving, resulting in serious waste of resources. Summary of the Invention
[0004] This application provides a data center energy-saving control method and device to solve the problem of resource waste caused by the inability to accurately control the cooling system in the prior art.
[0005] Firstly, this application provides a data center energy-saving control method, the method comprising:
[0006] Historical data of the data center is collected periodically. The historical data includes the data center's operating load information, external environment information, cooling system operating configuration parameters, and energy consumption information.
[0007] The lowest energy consumption data for the data center under the same operating load and external environment conditions is selected from historical data and saved to the database.
[0008] Collect the current operating load information and external environment information of the data center, and determine the target historical data that matches the current operating load information and external environment information from the database;
[0009] Use the target historical data as the current operating parameters of the data center.
[0010] Optionally, the data center's operating load information is IT load information; the external environment information is outdoor temperature and / or outdoor humidity.
[0011] Optionally, the operating configuration parameters of the data center's cooling system include the equipment activation mode, the number of activated equipment, the equipment number of activated equipment, the chiller chilled water return temperature, the chilled pump frequency, the cooling pump frequency, and the cooling tower frequency.
[0012] Optionally, the method further includes:
[0013] Using a pre-defined clustering algorithm, the collected historical data, including the data center's operating load information and external environment information, are clustered to obtain multiple clusters, where each cluster includes at least one target historical data point.
[0014] Optionally, the steps of obtaining the current operating load information and external environment information of the data center, and determining the target historical data that matches the current operating load information and external environment information from the database, include:
[0015] It collects real-time data on the current operating load and external environment information of the data center, and determines the target cluster that matches the current operating load information and external environment information through a preset clustering algorithm;
[0016] Identify the historical data of the target with the lowest energy consumption from at least one target data point included in the target cluster.
[0017] Optionally, the step of determining the target historical data with the lowest energy consumption from at least one target historical data set included in the target cluster includes:
[0018] The target data contained in the target cluster is matched with the target data in the database, and the historical data of the target with the lowest energy consumption is selected from the matching results.
[0019] Optionally, the target historical data for lowest energy consumption includes the data center's operating load information and external environmental information, as well as the operating configuration parameters of the data center's cooling system.
[0020] Secondly, this application provides a data center energy-saving control device, the device comprising:
[0021] The collection unit is used to periodically collect historical data from the data center. The historical data includes the data center's operating load information and external environment information, as well as the operating configuration parameters of the data center's cooling system and the data center's energy consumption information.
[0022] The filtering unit is used to filter out the data with the lowest energy consumption of the data center under the same operating load information and external environment information from historical data, and save it to the database as the target historical data;
[0023] The determination unit is used to obtain the current operating load information and external environment information of the data center, and to determine the target historical data that matches the current operating load information and external environment information from the database;
[0024] The configuration unit is used to set the target historical data as the current operating parameters of the data center.
[0025] Optionally, the data center's operating load information is IT load information; the external environment information is outdoor temperature and / or outdoor humidity.
[0026] Optionally, the operating configuration parameters of the data center's cooling system include the equipment activation mode, the number of activated equipment, the equipment number of activated equipment, the chiller chilled water return temperature, the chilled pump frequency, the cooling pump frequency, and the cooling tower frequency.
[0027] Optionally, the device further includes:
[0028] Clustering unit is used to perform clustering processing on the collected historical data, including the data center's operating load information and external environment information, using a preset clustering algorithm to obtain multiple clusters, wherein each cluster includes at least one target historical data.
[0029] When acquiring the current operating load information and external environment information of the data center, and determining the target history that matches the current operating load information and external environment information from the database, the determination unit is specifically used for:
[0030] It collects real-time data on the current operating load and external environment information of the data center, and determines the target cluster that matches the current operating load information and external environment information through a preset clustering algorithm;
[0031] Identify the historical data of the target with the lowest energy consumption from at least one target data point included in the target cluster.
[0032] Thirdly, this application provides a data center energy-saving control device, which includes:
[0033] Memory, used to store program instructions;
[0034] A processor is configured to invoke program instructions stored in memory and execute the steps of the method described in any of the first aspects above, according to the obtained program instructions.
[0035] Fourthly, embodiments of this application also provide a computer-readable storage medium storing computer-executable instructions for causing a computer to perform the steps of any of the methods described in the first aspect above.
[0036] In summary, the data center energy-saving control method provided in this application periodically collects historical data from the data center. This historical data includes the data center's operating load information and external environment information, as well as the operating configuration parameters of the data center's cooling system and the data center's energy consumption information. The method then filters out the data from the historical data that, under the same operating load information and external environment information, has the lowest energy consumption as target historical data and saves it to a database. Next, it obtains the current operating load information and external environment information of the data center and determines the target historical data that matches the current operating load information and external environment information from the database. Finally, it uses this target historical data as the current operating configuration parameters of the data center.
[0037] The data center energy-saving control method provided in this application collects IT operating load information, external environmental information, operating configuration parameters of the data center's cooling system, and energy consumption information. This collected data is used as historical data of the data center. During subsequent data center operation, the load information and external environmental information of the data center are collected in real time. Based on the real-time collected load information, external environmental information, and historical data, a clustering algorithm is used to determine the optimal operating configuration parameters. These operating configuration parameters are then used as the current configuration recommendation information for the data center to ensure that the total energy consumption of the data center is minimized and resources are saved. Attached Figure Description
[0038] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the description of the embodiments of this application or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in this application. For those skilled in the art, other drawings can be obtained based on these drawings of the embodiments of this application.
[0039] Figure 1 A detailed flowchart of a data center energy-saving control method provided in this application embodiment;
[0040] Figure 2 This is a schematic diagram of the structure of a data center energy-saving control device provided in an embodiment of this application;
[0041] Figure 3 This is a schematic diagram of the hardware architecture of a data center energy-saving control device provided in an embodiment of this application. Detailed Implementation
[0042] The terminology used in the embodiments of this application is for the purpose of describing particular embodiments only and is not intended to limit the application. The singular forms “a,” “the,” and “the” as used in this application and claims are also intended to include the plural forms unless the context clearly indicates otherwise. It should also be understood that the term “and / or” as used herein refers to any or all possible combinations including one or more of the associated listed items.
[0043] It should be understood that although the terms first, second, third, etc., may be used to describe various information in embodiments of this application, such information should not be limited to these terms. These terms are only used to distinguish information of the same type from one another. For example, without departing from the scope of this application, first information may also be referred to as second information, and similarly, second information may also be referred to as first information. Depending on the context, the word "if" may also be interpreted as "when," "when," or "in response to a determination."
[0044] For example, see Figure 1 The diagram shown is a detailed flowchart of a data center energy-saving control method provided in an embodiment of this application. The method includes the following steps:
[0045] Step 100: Periodically collect historical data from the data center, including the data center's operating load information, external environment information, operating configuration parameters of the data center's cooling system, and energy consumption information.
[0046] In this embodiment, historical data of the data center can be collected periodically based on a preset period (e.g., 1 minute, 5 minutes, etc.). Specifically, this includes the data center's own operating load information and the external environment information of the data center, as well as the operating configuration parameters of the data center's cooling system and the overall energy consumption information of the data center under the operating load information and external environment information. It should be noted that the overall energy consumption information can be only the energy consumption of the data center, or it can be the total energy consumption of the data center and the cooling system.
[0047] Specifically, the data center's operational load information includes IT load information; the external environmental information includes outdoor temperature and / or outdoor humidity. The data center's cooling system's operational configuration parameters include equipment activation mode, number of activated equipment, equipment number of activated equipment, chilled water return temperature, chilled water pump frequency, cooling pump frequency, and cooling tower frequency.
[0048] For example, data center operation data is collected every minute as historical data. For example, the IT load of the data center is a, the outdoor temperature is b, and the outdoor humidity is c. At this time, the cooling system is in mode 1, the number of devices in operation is d (assuming d = 5), the device numbers of the devices that are in operation are device 1-5, the chiller chilled water return temperature is e, the chilled pump frequency is f1, the cooling pump frequency is f2 and the cooling tower frequency is f3, and the energy consumption of the data center is p.
[0049] Based on the above methods and steps, several data points of data center operation data can be collected as historical data. Among them, the data center's IT load, outdoor ambient temperature, and outdoor ambient humidity can be summarized as external factors.
[0050] Step 110: Filter out the data from historical data that shows the lowest energy consumption of the data center under the same operating load and external environment information, and save it to the database.
[0051] Furthermore, the collected historical data can be preprocessed to select the historical data point with the lowest energy consumption (power) of the data center under the same external factors as the target historical data, and stored therein. Specifically, it can be stored in a designated database. This target historical data corresponds to the time when the data center's energy consumption is at its lowest, including but not limited to the data center's operating load information and external environment information, as well as the data center's cooling system operating configuration parameters and energy consumption information, and this information is saved to the designated database.
[0052] In this embodiment of the application, the above-mentioned data center energy-saving control method may further include the following steps:
[0053] Using a pre-defined clustering algorithm, the collected historical data, including the data center's operating load information and external environment information, are clustered to obtain multiple clusters, where each cluster includes at least one target historical data point.
[0054] That is, clustering algorithms (clustering models) can be used to cluster external factors as feature parameters. In practical applications, external factors can be divided into multiple range clusters based on preset rules, where each range cluster includes at least one target historical data.
[0055] Step 120: Obtain the current operating load information and external environment information of the data center, and determine the target historical data that matches the current operating load information and external environment information from the database.
[0056] In this embodiment of the application, when obtaining the current operating load information and external environment information of the data center, and determining the target historical data that matches the current operating load information and external environment information from the database, a preferred implementation method is as follows:
[0057] Collect real-time data on current operating load and external environment information of the data center, and determine the target cluster that matches the current operating load and external environment information; determine the target historical data with the lowest energy consumption from at least one target historical data included in the target cluster.
[0058] Specifically, during the operation of the data center, the current operating load information and external environmental information of the data center are collected in real time, namely the current external factors (including the current IT load of the data center, the current outdoor temperature and humidity). The current external factors are clustered using a preset clustering algorithm to determine the target clusters that match the current operating load information and external environmental information. The target data contained in the determined target clusters are compared with the target historical data in a specified database. After the matching is completed, the target historical data with the lowest energy consumption is selected. The target historical data with the lowest energy consumption includes the corresponding data center's operating load information and external environmental information, as well as the operating configuration parameters of the data center's cooling system.
[0059] For example, during the operation of a data center, the current external factors of the data center are collected in real time, namely the current operating load and external environment information of the data center. Using the clustering model mentioned above, the target cluster (e.g., cluster 1) that matches the current operating load and external environment information is determined. Then, at least one target data (e.g., target data 1 - target data m) included in the target cluster is compared and matched with the target historical data stored in the specified database. The target historical data with the lowest data center energy consumption in the matching results is selected (e.g., target historical data x, x≤m). The target historical data includes the operating load information and external environment information of the data center, as well as the operating configuration parameter information of the cooling system of the data center.
[0060] In this embodiment of the application, the above-mentioned data center energy-saving control method may further include the following steps: saving the target historical data with the lowest energy consumption selected from the matching results to a designated database.
[0061] Step 130: Use the target historical data as the current operating configuration parameters for this data center.
[0062] Specifically, the target historical data with the lowest energy consumption, determined from at least one target historical data set included in the target cluster, can be displayed on the operation page of the cooling system or the operation page of the data center energy-saving control equipment. This allows administrators to perform operational configuration operations on the data center based on the target historical data, which includes external factors (IT load, outdoor temperature and / or outdoor humidity), equipment operation mode, number of equipment in operation, equipment number of the equipment already in operation, chiller chilled water return temperature, chilled pump frequency, cooling pump frequency, and cooling tower frequency information, so as to achieve real-time operation of the data center at the lowest energy consumption.
[0063] In this way, the data center's operating system can be precisely controlled based on real-time load and environmental information. By continuously selecting the lowest energy consumption target historical data as the current operating configuration parameters through clustering algorithms, the best low-energy consumption target historical data can be optimized. This allows the data center to operate normally while rationally controlling the cooling effect of the cooling system, minimizing the total energy consumption of the data center and preventing resource waste.
[0064] Based on the same inventive concept as the above-described method embodiments, see, for example, the following: Figure 2 The diagram shown is a structural schematic of a data center energy-saving control device provided in an embodiment of this application. The device includes:
[0065] The collection unit 20 is used to periodically collect historical data of the data center. Each piece of historical data includes the data center's operating load information and external environment information, the operating configuration parameters of the data center's cooling system under the operating load information and external environment information, and the data center's energy consumption information.
[0066] The filtering unit 21 is used to filter out historical data that has the same operating load information and external environment information, and has the lowest energy consumption of the data center, as target historical data and save it to the database.
[0067] The determining unit 22 is used to obtain the current operating load information and external environment information of the data center, and to determine the target historical data that matches the current operating load information and external environment information from the database;
[0068] Configuration unit 23 is used to use the operating configuration parameter information of the cooling system included in the target historical data as the current operating configuration parameter of the cooling system of the data center.
[0069] Optionally, the data center's operating load information is IT load information; the external environment information is outdoor temperature and / or outdoor humidity.
[0070] Optionally, the operating configuration parameters of the data center's cooling system include the equipment activation mode, the number of activated equipment, the equipment number of activated equipment, the chiller chilled water return temperature, the chilled pump frequency, the cooling pump frequency, and the cooling tower frequency.
[0071] Optionally, the device further includes:
[0072] Clustering unit is used to perform clustering processing on the collected historical data, including the data center's operating load information and external environment information, using a preset clustering algorithm to obtain multiple clusters, wherein each cluster includes at least one target historical data.
[0073] When obtaining the current operating load information and external environment information of the data center, and determining the target history that matches the current operating load information and external environment information from the database, the determining unit 22 is specifically used for:
[0074] Collect real-time data on the current operating load and external environment information of the data center, and determine the target cluster that matches the current operating load information and external environment information;
[0075] Identify the target historical data with the lowest energy consumption from at least one target historical data point included in the target cluster.
[0076] These units can be one or more integrated circuits configured to implement the above methods, such as one or more Application Specific Integrated Circuits (ASICs), one or more digital signal processors (DSPs), or one or more Field Programmable Gate Arrays (FPGAs). Alternatively, when one of these units is implemented using processing element scheduler code, the processing element can be a general-purpose processor, such as a Central Processing Unit (CPU) or other processor capable of calling program code. Furthermore, these units can be integrated together to form a system-on-a-chip (SOC).
[0077] Furthermore, regarding the data center energy-saving control device provided in this application embodiment, from a hardware perspective, a schematic diagram of the hardware architecture of the data center energy-saving control device can be found in [reference needed]. Figure 3 As shown, the data center energy-saving control device may include: a memory 30 and a processor 31.
[0078] The memory 30 is used to store program instructions; the processor 31 calls the program instructions stored in the memory 30 and executes the above method embodiment according to the obtained program instructions. The specific implementation method and technical effect are similar, and will not be described again here.
[0079] Optionally, this application also provides a data center energy-saving control device, including at least one processing element (or chip) for performing the above method embodiments.
[0080] Optionally, this application also provides a program product, such as a computer-readable storage medium storing computer-executable instructions for causing the computer to perform the above-described method embodiments.
[0081] Here, a machine-readable storage medium can be any electronic, magnetic, optical, or other physical storage device that can contain or store information, such as executable instructions, data, etc. For example, a machine-readable storage medium can be: RAM (Random Access Memory), volatile memory, non-volatile memory, flash memory, storage drives (such as hard disk drives), solid-state drives, any type of storage disk (such as optical discs, DVDs, etc.), or similar storage media, or combinations thereof.
[0082] The systems, devices, modules, or units described in the above embodiments can be implemented by computer chips or entities, or by products with certain functions. A typical implementation device is a computer, which can take the form of a personal computer, laptop computer, cellular phone, camera phone, smartphone, personal digital assistant, media player, navigation device, email sending and receiving device, game console, tablet computer, wearable device, or any combination of these devices.
[0083] For ease of description, the above devices are described separately by function as various units. Of course, in implementing this application, the functions of each unit can be implemented in one or more software and / or hardware.
[0084] Those skilled in the art will understand that embodiments of this application can be provided as methods, systems, or computer program products. Therefore, this application can take the form of a completely hardware embodiment, a completely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, embodiments of this application can take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.
[0085] This application is described with reference to flowchart illustrations and / or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of this application. It will be understood that each block of the flowchart illustrations and / or block diagrams, and combinations of blocks in the flowchart illustrations and / or block diagrams, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, special-purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, generate instructions for implementing the flowchart... Figure 1 One or more processes and / or boxes Figure 1 A device that provides the functions specified in one or more boxes.
[0086] Furthermore, these computer program instructions can also be stored in a computer-readable storage medium that can direct a computer or other programmable data processing device to operate in a particular manner, such that the instructions stored in the computer-readable storage medium produce an article of manufacture including instruction means, which are implemented in the process. Figure 1 One or more processes and / or boxes Figure 1 The function specified in one or more boxes.
[0087] These computer program instructions may also be loaded onto a computer or other programmable data processing equipment to cause a series of operational steps to be performed on the computer or other programmable equipment to produce a computer-implemented process, thereby providing instructions that execute on the computer or other programmable equipment for implementing the process. Figure 1 One or more processes and / or boxes Figure 1 The steps of the function specified in one or more boxes.
[0088] The above are merely preferred embodiments of this application and are not intended to limit this application. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the scope of protection of this application.
Claims
1. A method for energy saving control of a data center, characterized by, The methods include: Historical data from the data center is collected periodically. This historical data includes the data center's operating load information and external environmental information, as well as the operating configuration parameters of the data center's cooling system and the data center's energy consumption information. The operating load information of the data center is IT load information, the external environmental information is outdoor temperature and outdoor humidity, and the operating configuration parameters of the cooling system include equipment activation mode, number of activated equipment, equipment number of activated equipment, chilled water return temperature of the chiller, chilled pump frequency, cooling pump frequency, and cooling tower frequency. The lowest energy consumption data for the data center under the same operating load and external environment conditions is selected from historical data and saved to the database. A preset clustering algorithm is used to cluster the collected historical data, including the data center's operating load information and external environment information, using external factors formed by the IT load information, outdoor temperature and outdoor humidity as feature parameters. Based on preset rules, the external factors are divided into multiple range clusters, where each range cluster includes at least one target historical data. During the operation of the data center, the current operating load information and external environment information of the data center are collected in real time. The current IT load information of the data center, the current outdoor temperature and the current outdoor humidity are used as the current external factors. The current external factors are clustered using a preset clustering algorithm to determine the target cluster that matches the current operating load information and the external environment information. The target data contained in the determined target cluster is compared with the target historical data stored in the database. After the matching is completed, the target historical data with the lowest energy consumption in the matching results is selected. The target historical data with the lowest energy consumption includes the corresponding data center's operating load information and external environment information, as well as the operating configuration parameter information of the data center's cooling system. The target historical data is used as the current operating configuration parameter of the data center, and the target historical data is displayed on the operation page of the cooling system or the operation page of the data center energy-saving control equipment, so that the administrator can perform operation configuration operations on the data center based on the external factors, equipment start-up mode, number of equipment started, equipment number of the equipment that has been started, chiller chilled water return temperature, chilled pump frequency, cooling pump frequency and cooling tower frequency information included in the target historical data.
2. A data center energy saving control device applied to the control method of claim 1, characterized in that, The device includes: The collection unit is used to periodically collect historical data from the data center. The historical data includes the data center's operating load information and external environment information, as well as the operating configuration parameters of the data center's cooling system and the data center's energy consumption information. The filtering unit is used to filter out the data with the lowest energy consumption of the data center under the same operating load information and external environment information from historical data, and save it to the database as the target historical data; The determination unit is used to obtain the current operating load information and external environment information of the data center, and to determine the target historical data that matches the current operating load information and external environment information from the database; The configuration unit uses the target historical data as the current operating configuration parameter information for the data center.
3. A data center energy saving control device, characterized by, The device includes: Memory, used to store program instructions; A processor is used to call program instructions stored in memory and execute the steps of the control method as described in claim 1 according to the obtained program instructions.
4. A computer-readable storage medium, characterized in that, The computer-readable storage medium stores computer-executable instructions for causing a computer to perform the steps of the control method as described in claim 1.
Citation Information
Patent Citations
Data center control method, apparatus and system
CN108234553A
Method, device and equipment for air conditioner working mode recommendation
CN111831871A
Energy-saving control method and energy-saving control device of air conditioner and air conditioner control terminal
CN113294902A