A parallel computing-based urban rail power supply system operation and maintenance decision method
The parallel computing-based operation and maintenance decision-making method for urban rail power supply systems solves the problem of limited time for subway operation and maintenance, enables rapid and effective operation and maintenance decisions, and improves the quality and efficiency of subway operation and maintenance.
Patent Information
- Application Number
- CN202211742039.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-29
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2042-12-29
AI Technical Summary
Subway operation and maintenance time is limited, and existing technologies are unable to provide effective operation and maintenance decision-making solutions during off-peak hours, affecting the quality and efficiency of operation and maintenance.
A parallel computing-based operation and maintenance decision-making method for urban rail power supply systems is adopted. By constructing a decision model and parallel computing algorithm, operation and maintenance decision-making schemes can be quickly formulated, including maintenance strategies and power restoration schemes under N-2 operating conditions. Thread pool technology is used for parallel solution.
It shortens the calculation time, improves the quality and efficiency of operation and maintenance, ensures that maintenance work during off-peak hours does not affect operation organization, and provides sufficient maintenance time.
Smart Images

Figure CN116402357B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of traction power supply technology for urban rail transit, and more specifically, to a method for operation and maintenance decision-making of urban rail power supply systems based on parallel computing. Background Technology
[0002] As daily passenger volume on the subway continues to rise and subway train operating hours extend, the working time available for operation and maintenance personnel is constantly being compressed. Typically, after deducting time for setting up safety measures and restoring equipment, the effective working time for each power outage maintenance point is only about 1-2 hours, posing significant challenges to maintenance work. If, during off-peak hours, some systems can be switched to other operating modes in advance, routine maintenance work can be carried out, providing ample time for operation and maintenance and improving the quality and efficiency of maintenance. In this case, subway maintenance personnel need to provide timely operation and maintenance decision-making solutions, adopting appropriate operating modes during off-peak hours to ensure that routine maintenance work on substations does not jeopardize operational organization. Summary of the Invention
[0003] To overcome the aforementioned deficiencies of the prior art, embodiments of the present invention provide a parallel computing-based operation and maintenance decision-making method for urban rail power supply systems to solve the problems mentioned in the background art.
[0004] To achieve the above objectives, the present invention provides the following technical solution: a method for operation and maintenance decision-making of urban rail power supply systems based on parallel computing, comprising the following steps:
[0005] Step 1: Based on the N-2 operating conditions under different maintenance circumstances, perform power restoration operations according to the maintenance strategy.
[0006] The specific maintenance strategy is as follows:
[0007] (1) A rectifier unit at a traction substation is under maintenance, and at the same time, a fault occurs on the incoming line of a switch station within the power supply zone.
[0008] like Figure 1 As shown, TSSi is the traction substation with a switchgear numbered i, powered by two external power sources Pi and P'i. TSi,j is the j-th traction substation within the power supply range of the i-th switchgear. QF represents a circuit breaker. Assume that TSi,j is under maintenance, and a fault occurs on one section of the incoming line of the switchgear in the power supply zone. At this time, QF1 and QF2 of the rectifier units in TSi,j should be disconnected, and the section from TSi,j-1 to TSi,j+1 of the traction substations should adopt a large double-sided power supply mode. Disconnect QF1 of TSSi and close QF4, so that the remaining line load is supplied by another external power source P'i.
[0009] (2) Maintenance of the rectifier unit in one traction substation, and fault disconnection of the switching station in the power supply section
[0010] As shown in Figure 2 , RCi and RC’i are the tie switches numbered i. Let Si and S’i be the average apparent powers of Pi and P’i during the simulation period, and Si,C and S’i,C be their contractual capacities. Define the remaining capacity of Pi as Si,m = Si,C - Si. Assume TSi,j is under maintenance, and the switching station in the power supply section is disconnected due to a fault. At this time, if Si-1,m > Si+1,m and S’i-1,m > S’i+1,m, disconnect QF1 and QF2 on TSi,j, close RCi and RC’i, and restore power supply by means of support from adjacent power sources with larger remaining capacity.
[0011] (3) Maintenance of the rectifier unit in one traction substation, and fault of the rectifier unit in a non-adjacent traction substation
[0012] As shown in Figure 3 , assume TSi,j is under maintenance, and the non-adjacent TSi,l (l>j+1 or l<j-1) is under fault condition. Disconnect QF1 and QF2 on TSi,j and TSi,l. At this time, the sections from traction mixing substation TSi,j-1 to TSi,j+1 and from TSi,l-1 to TSi,l+1 both adopt large bilateral power supply mode.
[0013] (4) Maintenance of one incoming line of the switching station, and fault of one incoming line of the continuous switching station
[0014] As shown in Figure 4 , assume one feeder line of TSSi is under maintenance, and one incoming line of the adjacent TSSi+1 is under fault condition. At this time, close QF4 on TSSi and TSSi+1, and the remaining line load is supplied by the other external power sources P’i and P’i+1.
[0015] (5) Disconnection and maintenance of the switching station, and fault disconnection of the non-continuous switching station
[0016] As shown in Figure 5As shown, it is assumed that TSSi is in the disconnection maintenance condition, and the adjacent TSSi+1 is in the disconnection fault condition. At this time, if Si-1,m > Si+1,m, S'i-1,m > S'i+1,m, Sj+1,m > Sj-1,m, and S'j+1,m > S'j-1,m, then RCi, RC'i, RCj+1, and RC'j+1 are closed, and power supply is restored by means of supporting power supply from adjacent power sources with larger remaining capacity. For the special case where i+2 = j, Si-1,m < Si+1,m, and Sj+1,m < Sj,m, if min(Si+1,m - Pi, Sj+1,m - Pj) > min(Si-1,m - Pi, Sj-1,m - Pj), then RCi+1 and RCj+1 are closed.
[0017] Step 2: Under the condition of satisfying all N-2 power supply system constraints, a decision model with the minimum departure interval N supported by the power supply system as the goal is constructed as shown in formula (1).
[0018]
[0019]
[0020] Step 3: The decision model is solved in parallel through a brute force search algorithm to obtain the departure interval supported by the system under the current working condition. The method is as follows:
[0021] Initialize conditions, including the original departure interval N0, power supply system parameters, thread pool, task queue, etc.;
[0022] According to different N-2 working conditions, after performing the power supply recovery operation, generate corresponding calculation units for the corresponding working conditions;
[0023] Put the calculation task of each calculation unit into the task queue of the thread pool, and solve each N-2 working condition in parallel to judge whether the constraints are satisfied. If not, update the departure interval according to the set search step size of the departure interval and restart the calculation task; if all are satisfied, output the minimum departure interval supported by the system and end.
[0024] Parallel computing is implemented through thread pool technology, and its principle is as Figure 6 shown.
[0025] An urban rail power supply system operation and maintenance decision-making system includes the following modules:
[0026] A construction module, configured to construct an operation and maintenance decision model with the minimum departure interval N supported by the power supply system as the goal;
[0027] A first processing module, configured to perform a power supply recovery operation through a maintenance strategy when an N-2 fault condition occurs under a certain maintenance condition;
[0028] The second processing module is used to implement the brute-force search algorithm, which solves for the minimum departure interval N by calling the third processing module;
[0029] The third processing module is used in the parallel computing method to decompose the computing task into N-2 parallel computing scenarios.
[0030] The beneficial effects of this invention compared to the prior art are:
[0031] 1. This design improves the decision-making method for urban rail transit operation and maintenance, which can quickly help subway operation and maintenance personnel formulate the best operation and maintenance decision-making plan. This ensures that when staff perform routine maintenance work on substations during off-peak hours, it will not affect the operation organization. It can provide sufficient time for operation and maintenance, and effectively improve the quality and efficiency of operation and maintenance.
[0032] 2. The conventional serial computing method requires a lot of time to calculate the N-2 working condition. Parallel computing can significantly shorten the computing time, which is beneficial for subway operation and maintenance personnel to formulate operation and maintenance decision-making plans in a timely manner. Attached Figure Description
[0033] Figure 1 This is a schematic diagram illustrating the restoration of power supply in the case of a fault in the incoming line of a closed substation within the N-2 operating condition.
[0034] Figure 2 This is a schematic diagram illustrating the restoration of power supply during the fault disconnection process of the switchgear within the power supply zone in the N-2 operating condition.
[0035] Figure 3 A schematic diagram for restoring power supply to a non-adjacent traction substation rectifier unit in the N-2 operating condition under fault conditions.
[0036] Figure 4 This is a schematic diagram illustrating the restoration of power supply in the case of a fault in one incoming line of a continuous switching station under the N-2 operating condition.
[0037] Figure 5 This diagram illustrates the restoration of power supply in a discontinuous switching station under N-2 operating conditions after a fault.
[0038] Figure 6 This is a schematic diagram illustrating the principle of parallel computing implemented through a thread pool in this invention. Detailed Implementation
[0039] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0040] Example:
[0041] A parallel computing-based operation and maintenance decision-making method for urban rail transit power supply systems includes the following steps:
[0042] Step SS1: Based on the N-2 operating conditions under different maintenance circumstances, perform power restoration operations according to the maintenance strategy;
[0043] Step SS2: Construct a decision model with the objective of minimizing the departure interval N supported by the power supply system under the power supply system constraints that satisfy all N-2 operating conditions;
[0044] Step SS3: Solve the decision model using a brute-force search algorithm to obtain the departure interval supported by the system under the current operating conditions;
[0045] Step SS4: Implement the computation process of solving the model using parallel computing methods.
[0046] Taking a city's subway as an example, a specific case is shown below:
[0047] Metro maintenance personnel plan to perform maintenance on the rectifier units of TSS8 in the traction substation during off-peak operating hours. To ensure the normal operation of the power supply system under the N-2 fault condition, a decision-making scheme for this scenario is proposed using an operation and maintenance decision model. The system adopts a distributed power supply method, comprising 21 traction substations and 8 step-down substations. The rectifier units in all traction substations have a capacity of 2×2500kW. The contracted capacity of all external power supplies is 12MVA. UTmin is 1000V and UTmax is 1800V. The metro operator's original scheduled departure interval N0 during off-peak operating hours is 2 minutes and 30 seconds.
[0048] During the operation and maintenance decision-making process, the simulation time for each operating condition is set to the current search departure interval Nm, the simulation interval is set to 1s, and NW is set to 30s. When the rectifier unit of TSS8 is in the maintenance operating condition, all N-2 fault operating condition information is shown in Table 1.
[0049] Table 1. Operating Condition Information
[0050]
[0051]
[0052] When the rectifier unit of TSS8 is under maintenance, QF2 and QF3 inside TSS8 should be disconnected. When other fault conditions occur, the operation to restore power supply is shown in Table 2.
[0053] Table 2. Power Restoration Operation
[0054] serial number operate 1 Disconnect QF1 in TSS8 and close QF4. 2 Close RC8, Close RC'9 3~20 Disconnect fault traction units QF2 and QF3
[0055] According to the operation and maintenance decision model, the minimum departure interval is found to be 3 minutes and 30 seconds, and the number of searches is 3.
[0056] In light of the above, when carrying out maintenance work on the TSS8 rectifier unit, the subway operator should select a departure interval of 3 minutes and 30 seconds to ensure the safe operation of the power supply system.
[0057] Traditional algorithms employ serial programming, which is abbreviated as serial algorithm. The parallel algorithm proposed in this paper, under a multi-layer parallel computing architecture, uses a multi-core CPU to compute multiple decomposed tasks, and is denoted as PA. The improved brute-force search algorithm narrows the search range by skipping unnecessary traversal conditions, and is denoted as VA. In this example, the simulation time of each algorithm is shown in Table 3. As can be seen from Table 3, SA+VA improves the computation speed by 2.37 times compared to SA. PA+VA achieves an even greater speedup of 12.7 times. PA+VA has highly efficient computational capabilities when performing operation and maintenance decision-making. Through the operation and maintenance decision-making model and parallel computing, subway management personnel can make quick decisions based on maintenance needs in a short time. This has significant engineering implications for the operation and maintenance work and emergency management of subway staff.
[0058] Table 3. Algorithm Simulation Time
[0059]
[0060] Parallel computing can significantly shorten computation time, enabling subway maintenance personnel to formulate maintenance decisions in a timely manner and effectively improving the quality and efficiency of operation and maintenance.
[0061] The accompanying drawings of the embodiments disclosed in this invention only involve the structures involved in the embodiments of this disclosure. Other structures can refer to the general design. In the absence of conflict, the same embodiment and different embodiments of this invention can be combined with each other.
[0062] In conclusion, the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A parallel computing-based urban rail power supply system operation and maintenance decision method, characterized in that: The operation and maintenance decision-making method for the urban rail power supply system includes the following steps: step SS1: Perform power restoration operations according to the maintenance strategy under N-2 operating conditions under different maintenance circumstances; Step SS2: Construct a decision model with the objective of minimizing the departure interval N supported by the power supply system under the power supply system constraints that satisfy all N-2 operating conditions; Step SS3: Solve the decision model using a brute-force search algorithm to obtain the departure interval supported by the system under the current operating conditions; Step SS4: Implement the model solution process using parallel computing methods; The brute-force search algorithm improves efficiency by skipping unnecessary conditions when traversing the N-2 operating conditions. Its steps are as follows: Initialize the conditions, including the original departure interval N0 and power supply system parameters; traverse the N-2 operating conditions in sequence; perform power supply calculation and statistical analysis after power restoration operation; determine whether the constraints are met; if not, jump to the next step; if all conditions are met, output the minimum departure interval that the system can support and end the process; update the departure interval according to the set departure interval search step size and jump to the previous step. The parallel computing method is based on thread pool technology to reuse threads and solve the decision model in parallel. The steps are as follows: initialize the thread pool, clear the task queue, generate corresponding computing units according to different N-2 working conditions, put the computing tasks of each computing unit into the task queue of the thread pool, and solve the N-2 working conditions in parallel.
2. The urban rail power supply system operation and maintenance decision method based on parallel computing according to claim 1, characterized in that: The maintenance strategy specifically involves dividing the system into DC system maintenance conditions and AC system maintenance conditions based on different maintenance conditions, and providing corresponding power restoration operations for each condition.
3. The operation and maintenance decision-making method for urban rail power supply systems based on parallel computing according to claim 1, characterized in that: The decision model described above specifically involves solving for the minimum departure interval N supported by the power supply system under the constraints of all N-2 operating conditions. The steps are as follows: Iterate through the N-2 operating conditions under the current maintenance situation to simulate the power supply system load process during time period T; Given the power supply system constraints that satisfy all N-2 operating conditions, solve for the minimum departure interval N supported by the power supply system. 。 4. A parallel computing-based operation and maintenance decision-making system for urban rail transit power supply systems, wherein the system is used to execute the operation and maintenance decision-making method for urban rail transit power supply systems as described in any one of claims 1-3, characterized in that: Includes the following modules: The module is used to build an operation and maintenance decision model with the goal of minimizing the departure interval N supported by the power supply system. The first processing module is used to restore power supply through maintenance strategies when an N-2 fault occurs during a certain maintenance operation. The second processing module is used to implement the operation and maintenance decision model based on the brute-force search algorithm, and solves the minimum solution of departure interval N in parallel by calling the third processing module; The third processing module is used to implement the parallel computing method, which decomposes the computing task into N-2 parallel computing scenarios.
Citation Information
Patent Citations
Electric transmission line maintenance plan optimization method and system based on manifold learning
CN106780141A
