Space flight information system resource scheduling method and system based on PPO algorithm

By constructing a PPO agent model based on the PPO algorithm and combining it with a reward function, the contradiction between system capacity and fairness in existing resource scheduling algorithms is resolved. This enables dynamic optimization of resource scheduling in the space flight information system, improving resource utilization efficiency and business adaptability.

CN116467069BActive Publication Date: 2026-11-20PERA
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310278188.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-03-21
Publication Date
2026-11-20
Estimated Expiration
2043-03-21

AI Technical Summary

Technical Problem

Existing resource scheduling algorithms often neglect other factors when pursuing system capacity or fairness, resulting in low resource utilization efficiency, inability to adapt to the dynamically changing physical world environment, and failure to achieve comprehensive optimization of system capacity, user fairness, and service quality.

Method used

A reinforcement learning method based on the PPO algorithm is adopted. By constructing a PPO agent model and combining the reward function of system capacity benefit and fairness benefit, the resource scheduling of the space flight information system is modeled and trained to realize dynamic adjustment of resource allocation strategy.

Benefits of technology

It achieves a balance between system capacity and user fairness in a dynamic environment, improves resource utilization efficiency, adapts to changes in business status, and optimizes resource scheduling strategies to meet actual application needs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116467069B_ABST
    Figure CN116467069B_ABST
Patent Text Reader

Abstract

The present application relates to a kind of space flight information system resource scheduling method and system based on PPO algorithm, belong to resource scheduling technical field, the scheduling strategy of the existing resource scheduling mode exists is difficult to adapt to the problem of varied physical world system of business change.It is a kind of space flight information system resource scheduling method based on PPO algorithm, comprising: mapping space flight information system into digital twin system, obtains all user terminals in digital twin system, space node, and the resource block in each space node;Based on digital twin system, the resource scheduling process of digital twin system is modeled using reinforcement learning PPO algorithm, obtain PPO agent model;PPO agent model is trained, and the PPO agent model after training is obtained;When receiving the request of user terminal, based on the PPO agent model after training, the resource scheduling of space flight information system is realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of resource scheduling technology, and in particular to a resource scheduling method and system for a space flight information system based on the PPO algorithm. Background Technology

[0002] Following the mobile internet, the development of the metaverse will build upon digital twins to achieve increasingly deeper interactions between the virtual and physical worlds, including virtual nativeness, virtual-physical symbiosis, and virtual-physical linkage. As this development progresses, the connection and interaction between the virtual and physical worlds will become increasingly intelligent.

[0003] In the metaverse, the available resources in both the physical and virtual worlds are limited. Even with advanced technology, without proper resource scheduling, its advantages may not be fully realized. Resource scheduling involves allocating resources within a limited pool to serve the ever-growing needs of system applications. As a digital twin of the virtual world simulating the physical world, it is crucial to realistically reproduce the real physical system of resource scheduling, optimize scheduling methods, and develop simulation strategies applicable to physical entities. This is key to the rational use of physical world resources, improving system performance, and enhancing the user experience.

[0004] Resource scheduling methods need to determine when, on which resource blocks, and using which technologies to allocate resources to which applications. Ideally, resource scheduling aims to maximize system capacity while ensuring fairness for application users and meeting the service quality requirements of different users.

[0005] The scheduling function needs to adjust parameters and strategies in a timely manner based on changes in the actual physical environment and the service quality assurance requirements of different application business types. Since it is difficult to model the resource demands of the physical world using a unified model, it is necessary to dynamically adjust the scheduling method based on intelligent concepts.

[0006] With the rapid development of artificial intelligence in recent years, machine learning has become a hot topic in the industry. Reinforcement learning is a type of machine learning where an agent can find the action policy that maximizes cumulative rewards through interaction with the environment. Digital twins, which simulate physical world networks, possess real-time perception capabilities, providing real-time environmental interaction for reinforcement learning. Based on this, dynamic management and scheduling of resources can be achieved through reinforcement learning.

[0007] In each decision cycle, resource scheduling algorithms typically allocate resources among multiple users based on information such as the user's resource quality status, available resources, and service priorities. Although the scheduling strategies employed vary across different scenarios due to differing optimization objectives, the factors considered in the design of resource scheduling algorithms are largely consistent. In practical systems, the most widely used resource scheduling schemes fall into three categories: the first prioritizes maximizing system capacity without considering the service quality of marginal users; the second focuses on fairness among users without considering system capacity performance from the perspective of the entire system; and the third represents a trade-off between system capacity and fairness, optimizing system capacity performance while ensuring a certain level of user fairness.

[0008] The specific scheduling algorithms corresponding to the three schemes are round-robin, maximum capacity, and proportional fairness. The following is a brief introduction to these three commonly used resource scheduling algorithms, providing a comparative reference for the policy optimization-based intelligent resource scheduling algorithm designed in this invention.

[0009] (1) Polling Algorithm

[0010] The round-robin algorithm only pursues system fairness, without considering scheduling priority or differences in user demand. At each scheduling moment, the round-robin algorithm allocates resource blocks equally to users according to their request order. If the number of resource blocks is greater than the number of requesting users, all users can be satisfied in the same scheduling moment; if the number of resource blocks is less than the number of users, not all users can obtain resource blocks in the current scheduling moment. In the next scheduling moment, resource block allocation will start from the first unallocated user from the previous moment.

[0011] Round-robin algorithms can guarantee the minimum transmission volume for each user, achieving an upper bound on resource scheduling fairness. However, their drawback lies in the lack of analysis of factors such as service priority and resource quality. In practice, this can lead to two problems: First, since all users have the same priority, real-time services cannot receive higher-priority service, and service quality cannot be guaranteed. Second, because users with poor transmission conditions can also obtain resources, resource utilization efficiency will decrease in the dynamically changing physical environment, and system capacity will suffer to varying degrees.

[0012] (2) Maximum capacity algorithm

[0013] The maximum capacity algorithm uses the system's transmission volume as the optimization objective. It sorts each requesting user based on their transmission quality, prioritizing resource allocation to users with better transmission conditions. Assume that at time t, N users need to communicate, and for resource block k, the capacity measured by user j is R. jIf (k,t), then the scheduling user priority of resource block k is calculated as follows: if different users have the same capacity, the resource block will be allocated to the user who requested it first.

[0014] i k (t)=argmax j=1,...,N (R j (k,t))

[0015] In real-world scenarios, the distribution of each user is random, and the received signal strength will vary. At any given time, the maximum capacity algorithm only favors users with good transmission quality, while edge users, due to poor transmission conditions, have a relatively lower probability of receiving service. Given the need for high reliability across all application terminals, this greedy algorithm is unreasonable and can only be used in practice to obtain the maximum system capacity.

[0016] The two algorithms above exemplify the two extremes of resource scheduling algorithms: pursuing fairness and maximizing system capacity. These can be used to evaluate other scheduling algorithms.

[0017] (3) Proportional Fairness Algorithm

[0018] The proportional fairness algorithm balances system capacity and user fairness. In the scheduling priority rules, it uses the current status of transmission condition quality and the system capacity performance over a period of time as reference factors, thus achieving a certain degree of compromise between fairness and system capacity.

[0019] Suppose that at time t, N users initiate service requests, and for resource block k, the instantaneous transmission volume of user j is R. j (k,t), where user j's average data transfer volume over the past period is T. j (t), then the user priority of resource block k is calculated as follows.

[0020]

[0021] Among them, T j The update formula for (t) is:

[0022]

[0023] Among them, t C The sliding time window can be used to adjust the proportional fairness algorithm's emphasis on system capacity and fairness. C A larger value for T indicates a greater emphasis on fairness, while a smaller value indicates a greater emphasis on system capacity. It can be seen that if a user is in an environment with poor transmission quality for an extended period, then T... j The value of T will decrease, thus increasing the scheduling priority; if a user continuously obtains resources, then T... j(t) will gradually increase, and the priority will decrease accordingly.

[0024] The proportional fairness algorithm satisfies the demand for high-capacity services from users with good transmission quality, while also considering the transmission capacity of users with poor transmission quality. It is the basis for the design of many resource scheduling algorithms.

[0025] In summary, current resource scheduling algorithms, such as the round-robin algorithm, do not analyze factors like service priority and resource quality. In practice, this may lead to situations where higher-priority services fail to receive priority service, and service quality cannot be guaranteed. Furthermore, users with poor transmission conditions may experience lower transmission efficiency, resulting in reduced resource utilization and a loss of overall system capacity. The maximum capacity algorithm only favors users with good transmission conditions, neglecting other users and leading to poor overall service transmission reliability, thus failing to achieve the maximum system capacity. The proportional fairness algorithm balances system capacity and user fairness, achieving a certain degree of compromise between the two. However, its adaptive adjustment capability is weak for physical world systems with diverse service changes. Summary of the Invention

[0026] In view of the above analysis, the present invention aims to provide a space flight information system resource scheduling method and system based on the PPO algorithm, so as to solve the above-mentioned defects of existing resource scheduling algorithms.

[0027] On the one hand, this invention provides a resource scheduling method for a space flight information system based on the PPO algorithm, comprising:

[0028] Map the space flight information system into a digital twin system, and obtain all user terminals, space nodes, and resource blocks in each space node within the digital twin system;

[0029] Based on the digital twin system, the resource scheduling process of the digital twin system is modeled using the reinforcement learning PPO algorithm, resulting in the PPO proxy model.

[0030] The PPO agent model is trained to obtain the trained PPO agent model;

[0031] When a request is received from a user terminal, the resource scheduling of the space flight information system is realized based on the trained PPO agent model.

[0032] Based on the above solution, the present invention also makes the following improvements:

[0033] Furthermore, the resulting PPO agent model includes state, action, and reward function; among which,

[0034] state Where λ represents user status information. ω represents resource status information, and ω represents user request information;

[0035] Actions refer to the resource block allocation strategy of spatial nodes;

[0036] The reward function r is set as follows:

[0037]

[0038] Where α represents the weighting factor, R1 n R² represents the system capacity benefit of spatial node n. n Let N represent the fairness benefit of spatial node n, and let N represent the total number of spatial nodes.

[0039] Furthermore, λ = {i1, i2, ..., i} u ,...,i U}, where i u This indicates the request status of user terminal u, where U represents the total number of user terminals; i u ∈{0,1}, i u =1 indicates that user terminal u initiated the request, i u =0 indicates that user terminal u did not initiate a request;

[0040] Where C = {m | m = 1, 2, ..., M}, M represents the total number of resource blocks; B = {n | n = 1, 2, ..., N}; y m,n This indicates the resource usage of resource block m in spatial node n; y m,n ∈{0,1},y m,n =1 indicates that the resource of resource block m in spatial node n is occupied, y m,n =0 indicates that the resources of resource block m in spatial node n are in an idle state;

[0041] ω is used to describe the request information carried by all user terminals that initiate the request.

[0042] Furthermore, assuming user terminal u initiates a request, the request information χ carried by user terminal u... u Represented as:

[0043] χ u =(cell,ID,Range,newArrivedData,nofResourceBlockRequired)

[0044] Where cell represents the service area code to which the user terminal belongs, ID represents the user terminal's identification identifier, Range represents the distance from the user terminal that initiated the request to the destination space node, newArrivedData represents the amount of newly arrived data, and nofResourceBlockRequired represents the number of resource blocks required.

[0045] further,

[0046] R1 n =ε n ×η n (2)

[0047] Where, ε n η represents the transmission efficiency coefficient of spatial node n. n This represents the transmission efficiency of spatial node n.

[0048] further,

[0049]

[0050] Where u1 represents the total number of user terminals requesting at space node n at the current scheduling time, and u2 represents the total number of user terminals that are finally scheduled.

[0051] Furthermore, the PPO agent model is trained, including:

[0052] Initialize the total number of user terminals, the total number of spatial nodes, and the total number of resource blocks in each spatial node; initialize the total number of epochs and the total number of episodes per epoch.

[0053] In each round, perform episode 10 trajectory updates to obtain episode 10 state transition trajectory samples.

[0054] Based on the obtained episode state transition trajectory samples, the Actor network and Critic network are updated in the current round; after the update is completed, the state transition trajectory samples are cleared.

[0055] Furthermore, training the PPO agent model also includes:

[0056] Repeat the trajectory update process for multiple rounds until the states of the Actor network and Critic network converge, or until the total number of epochs is reached, then end the training process and finally obtain the trained PPO agent model.

[0057] Furthermore, the resource scheduling of the space flight information system includes:

[0058] Get the current user terminal's request and generate the current state;

[0059] The current state is input into the trained PPO agent model to obtain the corresponding action, and the resource scheduling of the space flight information system is realized based on the obtained action.

[0060] On the other hand, the present invention also provides a space flight information system resource scheduling system based on the PPO algorithm, comprising:

[0061] The digital twin mapping module is used to map the space flight information system into a digital twin system, and to obtain all user terminals, space nodes, and resource blocks in each space node in the digital twin system.

[0062] The PPO agent model construction module, based on the digital twin system, uses the reinforcement learning PPO algorithm to model the resource scheduling process of the digital twin system, and obtains the PPO agent model.

[0063] The PPO agent model training module is used to train the PPO agent model and obtain the trained PPO agent model.

[0064] The resource scheduling module is used to implement resource scheduling of the space flight information system based on the trained PPO agent model when a request is received from a user terminal.

[0065] Compared with the prior art, the present invention can achieve at least one of the following beneficial effects:

[0066] The space flight information system resource scheduling method and system based on the PPO algorithm provided by this invention have the following advantages:

[0067] This invention enables real-time updates of the environment based on the actual application business state of the physical world system, and transmits this information to the intelligent learning end of the scheduling strategy. It not only obtains the strategy for the current resource scheduling request cycle but also updates the learning mechanism and related parameters. Through iterative convergence, it continuously approximates the true state of the environment, ultimately achieving the goal of optimally adapting the scheduling strategy to the actual application business state. The algorithm proposed in this invention can flexibly integrate factors such as system capacity, fairness among users, and service quality into the intelligent learning strategy, achieving the simultaneous optimization of multiple objectives. This results in the optimal resource scheduling strategy, allowing the digital twin system to simulate the scheduling strategy based on the actual business characteristics of the real physical world.

[0068] In this invention, the above-described technical solutions can be combined with each other to achieve more preferred combinations. Other features and advantages of this invention will be set forth in the following description, and some advantages may become apparent from the description or be learned by practicing the invention. The objects and other advantages of this invention can be realized and obtained from what is particularly pointed out in the description and drawings. Attached Figure Description

[0069] The accompanying drawings are for illustrative purposes only and are not intended to limit the invention. Throughout the drawings, the same reference numerals denote the same parts.

[0070] Figure 1 A flowchart of a space flight information system resource scheduling method based on the PPO algorithm provided in Embodiment 1 of the present invention;

[0071] Figure 2 This is a schematic diagram of the overall framework of the PPO proxy model provided in Embodiment 1 of the present invention;

[0072] Figure 3 This is a schematic diagram of the structure of the space flight information system resource scheduling system based on the PPO algorithm provided in Embodiment 2 of the present invention;

[0073] Figure 4 Performance comparison of the system capacity benefits of the algorithm proposed in this invention with commonly used scheduling methods such as round-robin, maximum capacity, and proportional fairness in scenarios where user terminals are evenly distributed;

[0074] Figure 5 The graph shows a performance comparison of the algorithm proposed in this invention with common scheduling methods such as round-robin, maximum capacity, and proportional fairness in a scenario where user terminals are evenly distributed. Detailed Implementation

[0075] Preferred embodiments of the present invention will now be described in detail with reference to the accompanying drawings, which form part of this application and are used together with the embodiments of the present invention to illustrate the principles of the present invention, but are not intended to limit the scope of the present invention.

[0076] Example 1

[0077] A specific embodiment of the present invention discloses a resource scheduling method for a space flight information system based on the PPO algorithm, the flowchart of which is shown below. Figure 1 As shown, the method includes the following steps:

[0078] Step S1: Map the space flight information system into a digital twin system, and obtain all user terminals, space nodes, and resource blocks in each space node in the digital twin system;

[0079] A spaceflight information system is an information system formed by multiple spacecraft distributed in space as space nodes (resource providers) and multiple user terminals distributed on the ground as resource users. Specifically, resource providers are used to supply resource blocks. User terminals are service requesters that access the resource provider through scheduled resource blocks and use the corresponding resource blocks provided by the resource provider.

[0080] In the process of mapping a space flight information system into a digital twin system, the user terminals in the space flight information system are mapped to the user terminals in the digital twin system; the spacecraft in the space flight information system are mapped to the space nodes in the digital twin system; and the resource blocks of the spacecraft in the space flight information system are mapped to the resource blocks of the space nodes in the digital twin system, thereby forming a digital twin system.

[0081] Step S2: Based on the digital twin system, the resource scheduling process of the digital twin system is modeled using the reinforcement learning PPO algorithm to obtain the PPO proxy model;

[0082] Specifically, in this embodiment, when modeling the resource scheduling process of the digital twin system using the reinforcement learning PPO algorithm, the following is executed:

[0083] The resource provider is treated as an intelligent agent, resource usage as the environment, and the scheduling of resource blocks in each spatial node as actions. The intelligent agent observes the environment s... t Decide to perform action a t a t Influence the environment to make it become s t+1 At the same time, the agent receives immediate benefits r from environmental feedback. t .

[0084] Specifically, the main contents of the modeling process are described below:

[0085] (1) State

[0086] A state is a formalized abstraction of the environment and also serves as the basis for determining the actions to be taken. State information represents the environmental information perceived by the agent, as well as the changes brought about by its own actions, and is the basis for the agent to make decisions and evaluate long-term benefits.

[0087] In this embodiment, the aim is to transform the raw state information through layers of nonlinear relationships in a deep neural network into a form highly correlated with long-term gains, and further guide the generation of action decisions. Therefore, the state space should consist entirely of information related to the task objective.

[0088] The state in this embodiment Where λ represents user status information. This represents resource status information, and ω represents user request information.

[0089] User state information λ is used to reflect whether all user terminals have initiated requests. λ = {i1, i2, ..., i...} u ,...,i U}, where i u This indicates the request status of user terminal u, where U represents the total number of user terminals; i u ∈{0,1}, i u =1 indicates that user terminal u initiated the request, i u =0 indicates that user terminal u did not initiate a request. In this embodiment, the collection of user status information is to ensure that no user without a request is considered during the scheduling process of any resource block. This ensures the effectiveness of the scheduling action strategy and reduces the action space.

[0090] Resource status information Used to describe the available information for each spatial node and its various resource blocks. Where C = {m | m = 1, 2, ..., M}, M represents the total number of resource blocks; B = {n | n = 1, 2, ..., N}, N represents the total number of spatial nodes; y m,n This indicates the resource usage of resource block m in spatial node n; y m,n ∈{0,1}, where y m,n =1 indicates that the resource of resource block m in spatial node n is occupied, y m,n =0 indicates that the resource block m in spatial node n is in an idle state. This information is extracted mainly to obtain the status information of each resource block and to prevent unoccupied resource blocks from being used incorrectly.

[0091] User request information ω describes the request information carried by all user terminals that initiate requests. Assuming user terminal u initiates a request, user terminal u carries request information χ. u It can be represented as a high-dimensional vector.

[0092] χ u =(cell,ID,Range,newArrivedData,nofResourceBlockRequired)

[0093] The parameters contained in the high-dimensional vector and their physical meanings are shown in Table 1.

[0094] Table 1. Parameters and their physical meanings in the request information from the user terminal.

[0095]

[0096] (2) Action space

[0097] Actions are the outputs of an intelligent agent to its environment, specifically referring to the allocation strategy of resource blocks in spatial nodes, that is, allocating resource blocks of spatial nodes to user terminals that initiate requests. Valid actions in a given environment are called the action space. The action space must first be complete to provide the possibility of achieving the expected goal; furthermore, the action space should also be legitimate, and actions that are not allowed in a specific state or that cause serious consequences should be directly blocked. The number of user terminals requesting service varies at each moment (service arrival model, such as Poisson distribution), and the resource requirements of each user terminal vary (different service types). Resource allocation is required for all requesting user terminals; therefore, the action space is defined as a resource allocation scheme. Due to resource constraints, if there are many user terminals requesting resources, it may result in some user terminals not being allocated resources (i.e., the selection of which user terminals to allocate resources can be based on their service priority or random selection).

[0098] (3) Reward function

[0099] Different machine learning problems require different reward function settings, i.e., the model's benefit function, and different reward functions will have different optimization effects on the same problem. In reinforcement learning algorithms, the setting of the reward function is crucial. The quality of the reward function design directly determines whether the algorithm can converge, the speed of convergence, and whether it can learn a good policy.

[0100] In this embodiment, the reward function is set considering two performance indicators for measuring system benefits: system capacity and fairness. System capacity benefit describes system capacity performance, and fairness benefit describes fairness performance.

[0101] 1) System capacity benefits

[0102] In resource scheduling algorithms, system capacity is an important indicator for quantifying the system's transmission capability. For a spatial node n, its transmission capability is defined as follows:

[0103] c n =min(w n ,p×g) (1)

[0104] Among them, w n Let g represent the capacity to be transmitted of spatial node n. g and p are constants. g represents the total number of resource blocks of the spatial node, and p represents the upper limit of the capacity that each resource block can transmit. Then p × g represents the total capacity that the spatial node can transmit.

[0105] The transmission efficiency η of spatial node n n for:

[0106]

[0107] Among them, a n This represents the error-free transmission capacity of spatial node n at the current scheduling time.

[0108] Considering the resource block utilization rate ε as a transmission efficiency coefficient, assume that at the current scheduling moment, the total number of resource blocks allocated to user terminals by space node n is d. n Then we can obtain the transmission efficiency coefficient ε of spatial node n. n As shown in the following formula:

[0109]

[0110] Thus, the system capacity benefit R1 of spatial node n n As shown in the following formula:

[0111] R1 n =ε n ×η n (4)

[0112] 2) Fairness benefits

[0113] If only system capacity is considered without considering fairness, it will lead to serious resource imbalance. Therefore, fairness among all users should also be considered.

[0114] The fairness benefit is set from the perspective of scheduling users. If the total number of user terminals requesting at space node n at the current scheduling time is u1, and the total number of user terminals that are finally scheduled is u2, then the fairness benefit R2 of space node n is... n :

[0115]

[0116] Furthermore, considering the conflicting relationship between system capacity benefits and fairness benefits, a reasonable resource scheduling strategy should strike a balance between system capacity and fairness based on specific application scenarios and business needs. This aims to optimize fairness among users while ensuring system capacity performance. Moreover, different reward function forms will result in different performance at each scheduling moment. Therefore, this embodiment also adds a weighting factor α∈[0,1] to adjust the emphasis on system capacity and fairness in the reward function according to different needs.

[0117] In summary, the reward function is set as follows:

[0118]

[0119] Step S3: Train the PPO agent model to obtain the trained PPO agent model;

[0120] The overall framework of the PPO agency model is as follows: Figure 2 As shown in the diagram, the intelligent agent observes the environment, senses the requests from all user terminals at each spatial node, generates resource scheduling results based on a strategy, and transmits them to the scheduler to form an effective scheduling scheme. After executing the scheduling scheme, it enters the next state and simultaneously obtains a reward value based on a set benefit function. Through continuous interaction, several trajectories are formed, and these sequence data are then input into the neural network to update parameters and adjust the strategy to maximize cumulative benefits.

[0121] In this embodiment, each round of the PPO agent model interacts with the environment to form several trajectory sequences. After each round, the data of the trajectory combinations is sampled, and the Actor network and Critic network are iteratively updated multiple times. The training process of the PPO agent model is described as follows:

[0122] The PPO surrogate model consists of an Actor network and a Critic network, which correspond to the policy and value function for optimizing reinforcement learning, respectively.

[0123] Step S31: Initialize the total number of user terminals, the total number of spatial nodes, and the total number of resource blocks in each spatial node; initialize the total number of epochs and the total number of episodes per epoch.

[0124] Step S32: In each round, perform episode 10 trajectory updates to obtain episode 10 state transition trajectory samples;

[0125] During each trajectory update, the following is executed:

[0126] State s t The input is fed into the Actor network; the Actor network forms a policy probability distribution based on the output dimension, and then randomly samples the policy probability distribution to obtain action a. t And the likelihood function value log_prob of the action t ;

[0127] Action a t The input environment, the scheduler formulates a scheduling policy, executes it, and receives a reward r. t and the next state s t+1 ;

[0128] Stored state transition trajectory samples (s) t ,a t ,log_prob t ,r t );

[0129] Based on the next state s t+1Repeat the process of obtaining the next trajectory update and store the corresponding state transition trajectory samples.

[0130] Therefore, after performing episodeotrajectory trajectory updates, episodeotrajectory state transition trajectory samples can be obtained.

[0131] Step S33: Based on the obtained episode state transition trajectory samples, update the Actor network and Critic network for the current round (i.e., train the PPO proxy model); after the update is complete, clear the state transition trajectory samples; specifically,

[0132] In this embodiment, the Actor network and Critic network are updated using existing methods, and the specific process will not be described in detail.

[0133] Repeatedly execute trajectory updates for multiple rounds (i.e., repeatedly execute steps S32 and S33), execute the trajectory update for the next round, until the states of the Actor network and Critic network converge, or until the total number of rounds (epochs) is reached, the training process ends, and finally the trained PPO agent model is obtained.

[0134] Step S4: When a request is received from a user terminal, resource scheduling of the space flight information system is implemented based on the trained PPO agent model.

[0135] Step S41: Obtain the current user terminal's request and generate the current state;

[0136] Step S42: Input the current state into the trained PPO agent model to obtain the corresponding action, and realize the resource scheduling of the space flight information system based on the obtained action.

[0137] It is important to emphasize that, because there is a mapping relationship between the digital twin system and the corresponding space flight information system, actions that respond to user terminal requests can directly affect the space flight information system mapped by the digital twin system, thereby enabling resource scheduling of the space flight information system.

[0138] Example 2

[0139] Embodiment 2 of the present invention discloses a space flight information system resource scheduling system based on the PPO algorithm, the structural schematic diagram of which is shown below. Figure 3 As shown, it includes:

[0140] The digital twin mapping module is used to map the space flight information system into a digital twin system, and to obtain all user terminals, space nodes, and resource blocks in each space node in the digital twin system.

[0141] The PPO agent model construction module, based on the digital twin system, uses the reinforcement learning PPO algorithm to model the resource scheduling process of the digital twin system, and obtains the PPO agent model.

[0142] The PPO agent model training module is used to train the PPO agent model and obtain the trained PPO agent model.

[0143] The resource scheduling module is used to implement resource scheduling of the space flight information system based on the trained PPO agent model when a request is received from a user terminal.

[0144] The specific implementation process of Embodiment 2 of the present invention can be found in the above method embodiments, and will not be repeated here.

[0145] Since this embodiment is based on the same principle as the above method embodiments, this system also has the corresponding technical effects of the above method embodiments.

[0146] Example 3

[0147] Embodiment 3 of the present invention provides an example of a space flight information system to verify the effects of Embodiments 1 and 2.

[0148] In the space flight information system illustrated in this embodiment, the total number of user terminals is set to 60, the number of space nodes is set to 3, and each space node includes 5 resource blocks. Requests from each user terminal are generated randomly. Specific simulation parameter settings are shown in the table below.

[0149] Table 2 Simulation Parameters

[0150]

[0151]

[0152] Performance comparison analysis of common methods under different business intensities.

[0153] Figure 4 and Figure 5 The diagrams show a performance comparison of the proposed algorithm with commonly used scheduling methods such as round-robin, maximum capacity, and proportional fairness in a scenario where user terminals are evenly distributed. Overall, the proposed method ensures system capacity performance while also maintaining fairness, avoiding the sacrifice of fairness in the pursuit of capacity.

[0154] Specifically, such as Figure 4As shown, when the business intensity is low, such as before 0.5, the performance of the four methods is not significantly different. The system capacity efficiency performance of the algorithm proposed in this invention is not outstanding, slightly higher than the maximum capacity method. This is because under low business intensity, the available resources in the system can meet the current user requests, and the number of users that the four scheduling methods can serve is not significantly different, resulting in small differences in their system capacity performance. As the business intensity increases, the resource utilization efficiency of the four algorithms gradually improves. This is because the increase in business intensity leads to an increase in the number of users initiating business requests at each scheduling moment, thereby increasing the system capacity performance. Figure 4 It can be further seen that the algorithm proposed in this invention achieves the fastest performance improvement in system capacity efficiency, while the improvement rates of other algorithms slow down to varying degrees in the later stages. At a business intensity of 0.9, the system capacity efficiency of the method proposed in this invention is 12.4% higher than the maximum capacity algorithm and 17.9% higher than the proportional fairness algorithm.

[0155] exist Figure 5 In the context of varying workloads, the round-robin algorithm exhibits stable fairness performance, while the maximum capacity method, which disregards fairness in user service, experiences a sharp decline in fairness performance as workload increases. The method proposed in this invention, while showing some decrease in fairness with increasing workload, demonstrates a significantly smaller decline compared to the maximum capacity and proportional fairness methods. For instance, compared to a workload of 0.1, the maximum capacity method shows a 54% decrease in fairness at workload 0.9, the proportional fairness method a 33% decrease, and the method proposed in this invention a 13% decrease.

[0156] Those skilled in the art will understand that all or part of the processes of the methods described in the above embodiments can be implemented by a computer program instructing related hardware, and the program can be stored in a computer-readable storage medium. The computer-readable storage medium may be a disk, optical disk, read-only memory, or random access memory, etc.

[0157] The above description is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any changes or substitutions that can be easily conceived by those skilled in the art within the scope of the technology disclosed in the present invention should be included within the scope of protection of the present invention.

Claims

1. A resource scheduling method for a space flight information system based on the PPO algorithm, characterized in that, include: The space flight information system is mapped into a digital twin system, acquiring all user terminals, space nodes, and resource blocks in each space node within the digital twin system. The space flight information system is an information system formed by multiple spacecraft distributed in space as space nodes and multiple user terminals distributed on the ground as resource users. Among them, space nodes act as resource providers, providing resource blocks; user terminals are service requesters that access the resource provider through scheduled resource blocks and use the corresponding resource blocks provided by the resource provider. Based on the digital twin system, the resource scheduling process of the digital twin system is modeled using the reinforcement learning PPO algorithm, resulting in the PPO proxy model. Train the PPO agent model to obtain the trained PPO agent model; When a request is received from a user terminal, the resource scheduling of the space flight information system is realized based on the trained PPO agent model. The resulting PPO agent model includes states, actions, and a reward function; among which, state ;in, Indicates user status information, Indicates resource status information. This indicates the user's request information; Actions refer to the resource block allocation strategy of spatial nodes; reward function The settings are as follows: (1) in, Indicates the weighting factor. Representing spatial nodes The system capacity benefits Representing spatial nodes Fairness benefits Indicates the total number of nodes in the space; ,in, Indicates user terminal The request status, Indicates the total number of user terminals; , Indicates user terminal Initiate a request, Indicates user terminal No request was made; ,in, , Indicates the total number of resource blocks; ; Representing spatial nodes medium resource block Resource usage status; , Representing spatial nodes medium resource block Resources are being occupied. Representing spatial nodes medium resource block The resources are idle; Used to describe the request information carried by all user terminals that initiate requests; Assuming the user terminal Initiating a request, user terminal Carrying request information Represented as: in, cell Indicates the service area code to which the user terminal belongs. ID This represents the user terminal's identification identifier. Range This represents the distance from the user terminal that initiated the request to the destination spatial node. newArrivedData Indicates the amount of newly arrived data. nofResourceBlockRequired Indicates the number of resource blocks required.

2. The resource scheduling method for a space flight information system based on the PPO algorithm according to claim 1, characterized in that, (2) in, Representing spatial nodes The transmission efficiency coefficient, Representing spatial nodes Transmission efficiency.

3. The resource scheduling method for a space flight information system based on the PPO algorithm according to claim 1, characterized in that, (3) in, Indicates the spatial node at the current scheduling time. The total number of user terminals making the requests. This represents the total number of user terminals that were finally scheduled.

4. The resource scheduling method for a space flight information system based on the PPO algorithm according to any one of claims 1-3, characterized in that, Training the PPO agent model includes: Initialize the total number of user terminals, the total number of spatial nodes, and the total number of resource blocks in each spatial node; initialize the total number of epochs and the total number of episodes per epoch. In each round, perform episode 10 trajectory updates to obtain episode 10 state transition trajectory samples. Based on the obtained episode state transition trajectory samples, the Actor network and Critic network are updated in the current round; after the update is completed, the state transition trajectory samples are cleared.

5. The space flight information system resource scheduling method based on the PPO algorithm according to claim 4, characterized in that, Training the PPO agent model also includes: Repeat the trajectory update process for multiple rounds until the states of the Actor network and Critic network converge, or until the total number of epochs is reached, then end the training process and finally obtain the trained PPO agent model.

6. The resource scheduling method for a space flight information system based on the PPO algorithm according to claim 5, characterized in that, The resource scheduling for the space flight information system includes: Get the current user terminal's request and generate the current state; The current state is input into the trained PPO agent model to obtain the corresponding action, and the resource scheduling of the space flight information system is realized based on the obtained action.

7. A space flight information system resource scheduling system based on the PPO algorithm, characterized in that, The system is implemented based on the space flight information system resource scheduling method based on the PPO algorithm as described in any one of claims 1-6, and the system includes: The digital twin mapping module is used to map the space flight information system into a digital twin system, and to obtain all user terminals, space nodes, and resource blocks in each space node in the digital twin system. The PPO agent model construction module, based on the digital twin system, uses the reinforcement learning PPO algorithm to model the resource scheduling process of the digital twin system, and obtains the PPO agent model. The PPO agent model training module is used to train the PPO agent model and obtain the trained PPO agent model. The resource scheduling module is used to implement resource scheduling of the space flight information system based on the trained PPO agent model when a request is received from a user terminal.

Citation Information

Patent Citations

  • Multi-beam satellite beam resource adaptation method based on service demand prediction

    CN114071528A

  • Hybrid power system energy management method based on PPO algorithm

    CN115310858A