Construction method of a mobile temporary steel bridge with adjustable length

By installing retractable top supports and pulleys inside the main body of the steel temporary bridge, along with guide rails, the problem of inconvenient movement and placement of the steel temporary bridge in irregularly shaped foundation pits is solved, achieving efficient, smooth installation and applicability.

CN116556169BActive Publication Date: 2026-11-20CHINA RAILWAY GUANGZHOU ENG GRP CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310492306.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-05-04
Publication Date
2026-11-20
Estimated Expiration
2043-05-04

AI Technical Summary

Technical Problem

In irregularly shaped foundation pits, the varying lengths of the temporary steel bridge make it difficult to move and position on the irregularly shaped cap beam, affecting installation efficiency.

Method used

By prefabricating a steel temporary bridge body with a length consistent with the maximum width of the cap beam in the foundation pit, and using top supports and pulleys during movement, the top supports can be extended and retracted to adapt to changes in the width of the cap beam, and the pulleys cooperate with the guide rails to move, thereby removing the restrictions of the foundation pit and realizing the flexible installation of the steel temporary bridge.

Benefits of technology

It improves the installation efficiency of steel temporary bridges in irregular foundation pits. It has a simple structure, high applicability, reduces the repeated installation and disassembly of top supports and pulleys, and improves the smoothness and efficiency of installation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116556169B_ABST
    Figure CN116556169B_ABST
Patent Text Reader

Abstract

The application discloses a construction method of a length-adjustable mobile temporary steel temporary bridge, which comprises the following steps: according to the maximum transverse width of a crown beam of a foundation pit, a plurality of bailey beam units are transversely and side by side spliced into a steel temporary bridge main body; then the steel temporary bridge main body is placed on the surface of the crown beam, and then the connection construction between the steel temporary bridge main body and the surface of the foundation pit is carried out; the steel temporary bridge is moved from the surface of the crown beam of the foundation pit with a large transverse width to the surface of the crown beam of the foundation pit with a small transverse width; when the steel temporary bridge is moved, the connecting structure between the steel temporary bridge main body and the surface of the foundation pit is removed first, then the steel temporary bridge is lifted upwards until the bottom surface height of the steel temporary bridge is higher than the surface of the foundation pit, then guide rails are laid on the surface of the foundation pit, the steel temporary bridge is lowered onto the guide rails, then the bailey beam units at the two ends of the steel temporary bridge main body are removed, then the guide rails are removed, the steel temporary bridge main body is lowered onto the surface of the crown beam, and finally the connection construction between the steel temporary bridge main body and the surface of the foundation pit is completed. The application has the effect of improving the installation efficiency of the steel temporary bridge.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of steel structure assembly, and in particular to a construction method for a movable temporary steel bridge with adjustable length. Background Technology

[0002] Steel temporary bridges, also known as prefabricated Bailey bridges, are characterized by modularity. They are made of high-strength steel and consist of lightweight, standardized truss unit components, crossbeams, longitudinal beams, bridge decks, bridge seats, and connectors. They can be quickly assembled on-site using specialized installation equipment to form truss beam bridges suitable for various spans and loads, and are particularly widely used in foundation pit applications.

[0003] In related technologies, the foundation pit capping beam is the main structure supporting the temporary steel bridge. During the installation of the temporary steel bridge, it is erected on the surface of the foundation pit capping beam. The surface of the temporary steel bridge is higher than the surface of the foundation pit. Then, concrete slabs and asphalt are laid on the bridge deck of the temporary steel bridge, and slope treatment is applied to both ends of the temporary steel bridge to complete the transition between the temporary steel bridge and the foundation pit surface.

[0004] Regarding the aforementioned technologies, the applicant believes there are the following drawbacks: In large-scale foundation pit construction, it is often necessary to assemble and disassemble steel temporary bridges and install them at the construction location. However, in irregularly shaped foundation pits, the width of the foundation pit capping beam changes with the width of the foundation pit, and the length of the steel temporary bridge changes accordingly. Compared to assembling and disassembling on a square capping beam, moving and positioning the steel temporary bridge is more inconvenient on irregularly shaped capping beams. The current installation method of steel temporary bridges makes it difficult to move them to the next construction location directly on irregularly shaped capping beams by lateral movement, which affects the installation efficiency of the steel temporary bridges. Therefore, there is room for improvement. Summary of the Invention

[0005] To improve the efficiency of steel temporary bridge installation, this application provides a construction method for a mobile temporary steel bridge with adjustable length.

[0006] The construction method for an adjustable-length mobile temporary steel bridge provided in this application adopts the following technical solution: A construction method for a movable temporary steel bridge with adjustable length includes the following steps: S1: Precast steel temporary bridge: Based on the maximum transverse width of the foundation pit cap beam, several Bailey beam units are spliced ​​side by side in the transverse direction to form the main body of the steel temporary bridge. The length of the main body of the steel temporary bridge is consistent with the maximum transverse width of the foundation pit cap beam. S2: Install the steel temporary bridge: Place the main body of the steel temporary bridge on the surface of the cap beam, and then carry out the connection construction between the main body of the steel temporary bridge and the surface of the foundation pit; S3: Moving the temporary steel bridge: Move the temporary steel bridge from the surface of the foundation pit capping beam with a large transverse width to the surface of the foundation pit capping beam with a small transverse width. When moving the temporary steel bridge, first remove the connection structure between the main body of the temporary steel bridge and the surface of the foundation pit, then lift the temporary steel bridge until the bottom of the temporary steel bridge is higher than the surface of the foundation pit. Next, lay guide rails on the surface of the foundation pit. The rails are located below the main body of the temporary steel bridge. Lower the temporary steel bridge onto the guide rails, and then proceed with the steps of moving the main body of the temporary steel bridge. S4: Positioning of the temporary steel bridge: Next, remove the Bailey beam units at both ends of the main body of the temporary steel bridge so that the length of the main body of the temporary steel bridge is consistent with the width of the capping beam below. Then, remove the guide rails and lower the main body of the temporary steel bridge onto the surface of the capping beam. Finally, complete the connection construction between the main body of the temporary steel bridge and the surface of the foundation pit.

[0007] By adopting the above technical solution, and considering the widening of the foundation pit, the foundation pit construction is carried out in order of decreasing width. The steel temporary bridge is moved from the surface of the capping beam with a larger transverse width to the surface of the capping beam with a smaller width. The Bailey beam units at both ends of the main body of the steel temporary bridge are disassembled to adapt to the width of the capping beam. In addition, the steel temporary bridge is pushed out of the foundation pit to remove the restriction on the movement of the steel temporary bridge. Then, guide rails are installed on the surface of the foundation pit below the steel temporary bridge to move the steel temporary bridge to the next construction position. This helps to improve the installation efficiency of the steel temporary bridge.

[0008] Preferably, in the prefabrication step of the temporary steel bridge in S1, the top support is slidably connected laterally inside the Bailey beam unit, and the top support extends and retracts vertically downward; in the lifting step of the main body of the temporary steel bridge in S3, the top support pushes the surface of the cap beam downward to push the main body of the temporary steel bridge out of the pit surface; when the main body of the temporary steel bridge is moved, the top support retracts into the main body of the temporary steel bridge.

[0009] By adopting the above technical solution, the top support component is installed inside the steel temporary bridge. It extends when in use and is stored when not in use, reducing the need for repeated installation and disassembly of the top support component and improving the efficiency of the steel temporary bridge's assembly and disassembly.

[0010] Preferably, the top support is slidably connected inside the main body of the temporary steel bridge, and the sliding direction of the top support is consistent with the length direction of the main body of the temporary steel bridge. In the S4 temporary steel bridge placement step, the top support is first moved laterally towards the middle of the main body of the temporary steel bridge to move the top support directly above the cap beam, and then the Bailey beam units at both ends of the temporary steel bridge are removed.

[0011] By adopting the above technical solution, it is beneficial to reduce the number of top support components to a greater extent. The top support components can be moved to any point along the length of the main body of the steel temporary bridge, which has greater applicability and helps to improve the installation efficiency of the steel temporary bridge.

[0012] Preferably, in the prefabrication step of the steel temporary bridge in S1, pulleys are installed at the bottom of the Bailey beam unit, and the pulleys are adapted to the guide rails.

[0013] By adopting the above technical solutions, the main body of the temporary steel bridge can be moved, which helps to improve the smoothness of the temporary steel bridge's repositioning.

[0014] Preferably, the pulley is slidably connected inside the main body of the steel temporary bridge, and the sliding direction of the pulley is consistent with the length direction of the main body of the steel temporary bridge; in the S3 steel temporary bridge moving step, the pulley is moved laterally to directly above the guide rail, and then the main body of the steel temporary bridge is lowered onto the guide rail. After the pulley and the guide rail are engaged, the steel temporary bridge moving step is carried out.

[0015] By adopting the above technical solution, there is no need to adjust according to the position of the pulley or the guide rail. The alignment and matching steps with the guide rail can be completed directly by moving the position of the pulley, which helps to improve the flexibility of guide rail installation.

[0016] In summary, this application includes at least one of the following beneficial technical effects: 1. The foundation pit construction is carried out in descending order of the width of the capping beam. The steel temporary bridge moves with the construction position. The steel temporary bridge is pushed out of the foundation pit to remove the restriction on its movement. The Bailey beam units at both ends of the main body of the steel temporary bridge are disassembled to adapt to the width of the capping beam. In addition, guide rails are installed on the foundation pit surface below the steel temporary bridge to move the steel temporary bridge to the next construction position, which helps to improve the installation efficiency of the steel temporary bridge. 2. By sliding the top support component inside the main body of the steel temporary bridge and sliding the pulley at the bottom of the main body of the steel temporary bridge, the lifting and moving functions of the main body of the steel temporary bridge are facilitated. It has the characteristics of simple structure and high applicability. Attached Figure Description

[0017] Figure 1 This is a schematic diagram of the main structure of a mobile temporary steel bridge in a construction method for an adjustable-length mobile temporary steel bridge according to an embodiment of this application.

[0018] Figure 2 This is a schematic diagram showing the state of the main body of the steel temporary bridge when it is positioned on the transversely wide cap beam in the construction method of a mobile temporary steel bridge with adjustable length according to an embodiment of this application.

[0019] Figure 3 This is a schematic diagram showing the state in which the top support member lifts up the steel temporary bridge in a construction method of an adjustable-length mobile temporary steel bridge according to an embodiment of this application.

[0020] Figure 4 This is a schematic diagram showing the state of the pulley and guide rail in the construction method of a movable temporary steel bridge with adjustable length according to an embodiment of this application.

[0021] Figure 5 This is a schematic diagram showing the state of the main body of the steel temporary bridge when it is moved above the cap beam with a small transverse width, in a construction method of a movable temporary steel bridge with adjustable length according to an embodiment of this application.

[0022] Figure 6 yes Figure 5 Enlarged diagram of point A in the middle.

[0023] Figure 7 This is a schematic diagram showing the state of the main body of the steel temporary bridge when it is positioned on the capping beam with a small transverse width, in the construction method of a mobile temporary steel bridge with adjustable length according to an embodiment of this application.

[0024] Explanation of reference numerals in the attached drawings: 1. Main body of the temporary steel bridge; 11. Bailey beam unit; 111. Bailey sheet; 12. Connecting rod; 2. Top support; 21. Moving seat; 22. Vertical jack; 3. Pulley; 4. Foundation pit; 5. Crown beam; 6. Guide rail. Detailed Implementation

[0025] The following is in conjunction with the appendix Figure 1-7 This application will be described in further detail.

[0026] This application discloses a construction method for a movable temporary steel bridge with adjustable length, including the following steps: S1: Precast steel temporary bridge: See reference Figure 1 and Figure 2 Based on the maximum transverse width of the 4th cap beam 5 of the foundation pit, several Bailey beam units are spliced ​​side by side in the transverse direction to form the main body 1 of the temporary steel bridge. The length of the main body 1 of the temporary steel bridge is consistent with the maximum transverse width of the 4th cap beam 5 of the foundation pit.

[0027] The Bailey beam includes several longitudinally distributed Bailey panels 111. The upper and lower parts of adjacent Bailey panels 111 are made of I-beams. Adjacent Bailey panels 111 are connected by several connecting rods 12. The connecting rods 12 are connected to the inner side of the web of two I-beams that are directly opposite each other in adjacent Bailey panels 111. The connecting rods 12 are distributed along the length of the I-beams. At the same time, there are gaps between adjacent Bailey panels 111.

[0028] In this embodiment, a top support 2 is laterally slidably connected inside the Bailey beam unit 11, and the top support 2 extends and retracts vertically downwards. Specifically, the top support 2 includes a movable base 21 and a vertical jack 22. The movable base 21 is slidably connected between two adjacent I-beam flanges at the upper part of the Bailey beam unit 11, so that the top support 2 is housed in the gap between adjacent Bailey beam sections 111. The vertical jack 22 is vertically positioned at the bottom of the movable base 21, and when the vertical jack 22 is in the retracted state, it can be housed inside the Bailey beam unit 11.

[0029] Additionally, pulleys 3 are installed at the bottom of Bailey beam unit 11. The pulleys 3 are slidably connected to the bottom of the steel temporary bridge body 1, and the sliding direction of the pulleys 3 is consistent with the length direction of the steel temporary bridge body 1. In this embodiment, there are four pulleys 3, which are placed at the front and rear ends of the steel temporary bridge body 1 according to the moving direction of the steel temporary bridge body 1.

[0030] S2: Install the temporary steel bridge: Place the main body 1 of the temporary steel bridge on the surface of the cap beam 5, and then carry out the connection construction between the main body 1 of the temporary steel bridge and the surface of the foundation pit 4.

[0031] S3: Mobile steel temporary bridge: (Refer to...) Figure 3 and Figure 4 The temporary steel bridge was moved from the surface of the capping beam 5 of the foundation pit 4 (which has a wider transverse width) to the surface of the capping beam 5 of the foundation pit 4 (which has a narrower transverse width). During the movement, the connecting structure between the main body 1 of the temporary steel bridge and the surface of the foundation pit 4 was first removed, and then the temporary steel bridge was lifted. The lifting process involved vertically advancing and pushing downwards against the surface of the capping beam 5. Once the bottom of the main body 1 of the temporary steel bridge was higher than the surface of the foundation pit 4, guide rails 6 were then laid on the surface of the foundation pit 4, with the rails positioned below the main body 1 of the temporary steel bridge.

[0032] Next, move pulley 3 horizontally to directly above guide rail 6, and then activate vertical jack 22. Vertical jack 22 retracts to lower the main body 1 of the steel temporary bridge onto guide rail 6, with pulley 3 engaging with guide rail 6.

[0033] Reference Figure 5 Then, traction equipment such as winches is used to pull the main body 1 of the temporary steel bridge to move it to a position above the narrower cap beam 5. Before moving the bridge, the vertical jacks 22 need to be retracted into the Bailey beam unit 11 to prevent them from colliding with the sidewalls of the pit 4 and being damaged during the movement of the main body 1.

[0034] S4: Temporary steel bridge placement: Refer to... Figure 6 and Figure 7 First, move the top support 2 towards the middle of the main body 1 of the temporary steel bridge to move the top support 2 directly above the cap beam 5. Then, extend the vertical jack 22 downwards, and the lower end of the vertical jack 22 supports the main body 1 of the temporary steel bridge. Then, remove the Bailey beam units 11 at both ends of the main body 1 of the temporary steel bridge to make the length of the main body 1 of the temporary steel bridge consistent with the width of the cap beam 5 below. Next, remove the guide rail 6, and then move the pulley 3 towards the middle of the main body 1 of the temporary steel bridge to move away from the cap beam 5. Then, lower the main body 1 of the temporary steel bridge to the surface of the cap beam 5 by retracting the vertical jack 22. Finally, complete the connection construction between the main body 1 of the temporary steel bridge and the surface of the foundation pit 4.

[0035] The above are all preferred embodiments of this application, and are not intended to limit the scope of protection of this application. Therefore, all equivalent changes made in accordance with the structure, shape and principle of this application should be covered within the scope of protection of this application.

Claims

1. A construction method for a movable temporary steel bridge with adjustable length, characterized in that: Includes the following steps: S1: Precast steel temporary bridge: Based on the maximum transverse width of the foundation pit (4) capping beam (5), several Bailey beam units (11) are spliced ​​side by side in the transverse direction to form the main body of the steel temporary bridge (1). The length of the main body of the steel temporary bridge (1) is consistent with the maximum transverse width of the foundation pit (4) capping beam (5). S2: Install the steel temporary bridge: Place the main body (1) of the steel temporary bridge on the surface of the cap beam (5), and then carry out the connection construction between the main body (1) of the steel temporary bridge and the surface of the foundation pit (4); S3: Moving the temporary steel bridge: Move the temporary steel bridge from the surface of the capping beam (5) of the pit (4) with a large transverse width to the surface of the capping beam (5) of the pit (4) with a small transverse width. When moving the temporary steel bridge, first remove the connection structure between the main body (1) of the temporary steel bridge and the surface of the pit (4), then lift the temporary steel bridge until the bottom of the main body (1) of the temporary steel bridge is higher than the surface of the pit (4). Then lay the guide rail (6) on the surface of the pit (4). The rail is located below the main body (1) of the temporary steel bridge. Lower the temporary steel bridge onto the guide rail (6), and then carry out the moving step of the main body (1) of the temporary steel bridge. S4: Positioning of the temporary steel bridge: Next, remove the Bailey beam units (11) at both ends of the main body (1) of the temporary steel bridge so that the length of the main body (1) of the temporary steel bridge is consistent with the width of the lower cap beam (5). Then remove the guide rail (6) and lower the main body (1) of the temporary steel bridge to the surface of the cap beam (5). Finally, complete the connection construction between the main body (1) of the temporary steel bridge and the surface of the foundation pit (4).

2. The construction method of a length-adjustable mobile temporary steel bridge according to claim 1, characterized in that: In the prefabrication step of the temporary steel bridge in S1, the top support (2) is laterally slidably connected inside the Bailey beam unit (11), and the top support (2) extends and retracts vertically downward; in the lifting step of the main body of the temporary steel bridge (1) in S3, the top support (2) pushes the surface of the cap beam (5) downward to push the main body of the temporary steel bridge (1) out of the surface of the pit (4); When the main body (1) of the moving steel temporary bridge is moved, the top support (2) retracts into the main body (1) of the steel temporary bridge.

3. The construction method of a length-adjustable mobile temporary steel bridge according to claim 2, characterized in that: The top support (2) is slidably connected to the main body (1) of the steel temporary bridge, and the sliding direction of the top support (2) is consistent with the length direction of the main body (1) of the steel temporary bridge. In the S4 steel temporary bridge placement step, the top support (2) is first moved laterally to the middle of the main body (1) of the steel temporary bridge to move the top support (2) directly above the cap beam (5), and then the Bailey beam units (11) at both ends of the steel temporary bridge are removed.

4. The construction method of a length-adjustable mobile temporary steel bridge according to claim 1, characterized in that: In the prefabrication step of the steel temporary bridge in S1, a pulley (3) is installed at the bottom of the Bailey beam unit (11), and the pulley (3) is adapted to the guide rail (6).

5. The construction method of a length-adjustable mobile temporary steel bridge according to claim 4, characterized in that: The pulley (3) is slidably connected to the bottom of the steel temporary bridge body (1), and the sliding direction of the pulley (3) is consistent with the length direction of the steel temporary bridge body (1). In the S3 steel temporary bridge moving step, the pulley (3) is moved horizontally to the top of the guide rail (6), and then the steel temporary bridge body (1) is lowered onto the guide rail (6). The steel temporary bridge moving step is carried out after the pulley (3) and the guide rail (6) are engaged.

6. The construction method of a length-adjustable mobile temporary steel bridge according to claim 2, characterized in that: The Bailey beam comprises several longitudinally distributed Bailey panels (111), and the top support (2) is accommodated in the gap between adjacent Bailey panels (111).

7. The construction method of a length-adjustable mobile temporary steel bridge according to claim 2, characterized in that: The top support (2) includes a movable seat (21) and a vertical jack (22). The movable seat (21) is slidably connected to the Bailey beam unit (11), and the vertical jack (22) is vertically downward at the bottom of the movable seat (21).