Arch bridge outer package concrete roof form construction method and roof form thereof
By suspending the inner formwork of the top slab with lifting tools and setting up a construction platform, the problem of the support frame easily slipping during the construction of the top slab formwork of the rigid frame arch bridge was solved, realizing efficient and safe formwork assembly and turnover, and ensuring construction quality.
Patent Information
- Application Number
- CN202310669917.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-06-07
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2043-06-07
AI Technical Summary
In the existing construction method of using the internal support frame in the formwork box for the top slab of a rigid frame arch bridge, the support frame is prone to slippage and instability, posing safety hazards, occupying space inside the box, affecting the assembly and turnover of the formwork, and reducing construction efficiency.
Lifting tools are used to suspend the inner formwork of the top slab, and the main body section and chamfer section are assembled separately. A construction platform is set up to form a passageway, which avoids the slippage of the support and the occupation of space, and provides an installation position and turnover passage.
This method enables the installation of the top slab formwork without supports, avoiding the risk of support frame slippage, improving construction efficiency and formwork turnover efficiency, and ensuring construction safety and concrete alignment quality.
Smart Images

Figure CN116556216B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of concrete encasing construction technology for rigid frame arch bridges, and particularly to a method for constructing a concrete encasing top slab formwork for arch bridges and the formwork itself. Background Technology
[0002] For rigid-frame concrete arch bridges, after the internal concrete construction is completed, the steel-concrete composite arch is used as the main load-bearing component, and external formwork is used for external concrete pouring. The steel-concrete composite arch is a truss box structure, and the formwork is divided into two parts: the inner box and the outer box. Concrete is poured between the inner and outer formwork to enclose the rigid frame and form the rigid-frame concrete arch rib. However, the load-bearing capacity of the steel-concrete composite arch structure is limited. For large-span rigid-frame arch bridges, the external concrete has a large proportion of weight, and it is impossible to complete the concrete loading in one go. Generally, it is poured in three rings in the order of bottom slab, web slab, and top slab. The concrete of the first ring is constructed to form a new load-bearing structure together with the rigid frame, which together provides support for the subsequent construction rings.
[0003] The inner formwork of the top slab is influenced by the steel-concrete arch truss structure, and has a main section and a chamfered section on the arch rib section. It is generally constructed using a scaffolding method. This involves setting up support frames on the bottom slab of the box girder, which support the top slab formwork to align with the arch rib line before fixing it in place, thus achieving the purpose of the top slab formwork construction. However, due to the curved shape of the rigid-frame concrete arch bridge, the bottom slab of the box girder is actually inclined. The top slab needs to conform to the inclination angle during and after installation. With the support frames resting on the inclined bottom slab, slippage and instability are likely to occur. The inclined formwork, supported on top of the support frame, is also prone to slippage and instability relative to the support frame, posing a safety hazard. This necessitates additional stabilization measures to secure the support frame and the top slab formwork inside the box, increasing construction difficulty and impacting efficiency. Furthermore, because the support frame occupies limited space within the rigid frame box, there is no space for formwork assembly and turnover. The support frame must be removed after the current segment's top slab formwork is completed before installing the next segment's support frame and top slab formwork, leading to difficult turnover, low formwork turnover efficiency, and affecting the overall construction efficiency of the top slab formwork.
[0004] Therefore, there is an urgent need for a technical solution to address the technical problems of the existing rigid frame arch bridge roof slab formwork box internal support method construction, which is prone to slippage and instability of the support frame, posing safety hazards, occupying limited space inside the box, affecting formwork assembly and turnover, and affecting the overall construction efficiency of the roof slab formwork. Summary of the Invention
[0005] The purpose of this invention is to address the technical problems of existing rigid frame arch bridge roof slab formwork box internal support method construction, which has the problems of support frame easy slippage and instability, posing safety hazards, occupying limited space inside the box, affecting formwork assembly and turnover, and affecting the overall construction efficiency of roof slab formwork. The invention provides a method for constructing arch bridge external concrete roof slab formwork and its roof slab formwork.
[0006] To achieve the above objectives, the technical solution adopted by the present invention is as follows: A method for constructing an outer concrete roof slab formwork for an arch bridge includes: setting up lifting tools above the roof slab; assembling the main body section of the inner formwork of the roof slab on the bottom slab and lifting it once using the lifting tools; suspending and assembling the chamfered section of the inner formwork of the roof slab and lifting it a second time; setting up a construction platform at the bottom of the main body section and lifting it to the elevation of the roof slab; fixing the inner formwork of the roof slab within the construction platform, and forming a passageway below the construction platform.
[0007] This invention discloses a construction method for the outer concrete top slab formwork of an arch bridge. The method utilizes lifting equipment to suspend the inner formwork of the top slab, enabling the separate assembly of the main body and chamfered sections of the inner formwork. This allows for support-free installation of the inner formwork, avoiding the risk of support frame slippage and the problem of occupying limited space within the arch box. It also provides space for the assembly of the top slab formwork within the arch box. Furthermore, by setting a construction platform at the bottom of the main body of the inner formwork, an installation position is provided for fixing the inner formwork, facilitating its installation. A passageway is also formed below the main body of the top inner formwork, facilitating the construction of other structures within the arch box and providing a channel for the reuse of the top slab formwork. This allows the next segment of the top slab formwork to be installed without waiting for the current top slab construction to be completed, effectively improving construction efficiency.
[0008] As a preferred embodiment of the present invention, the main body section of the assembled top slab inner formwork includes: laying sleepers on the base plate, laying and connecting formwork components on the sleepers, and leaving hoisting connection areas on both sides of the top of the main body section. The formwork components include longitudinal beams, transverse distribution beams, longitudinal distribution beams, and building formwork arranged sequentially from bottom to top. This allows the main body section of the top slab inner formwork to be assembled on the base plate and reserves positions for connecting lifting tools.
[0009] As a preferred embodiment of the present invention, the chamfered section of the inner formwork of the assembled top slab includes: hinged chamfered section distribution beams at the ends of the transverse distribution beams of the main body section, loosening the hinges to keep the chamfered section distribution beams suspended, and then installing the chamfered section formwork. This ensures that the chamfered section is in a vertical state during formwork assembly, occupies less transverse space within the arch box, and leaves sufficient construction space for formwork installation.
[0010] As a preferred embodiment of the present invention, the installation of the chamfered section template includes: providing a suspension part on the outside of the chamfered section distribution beam, assembling the chamfered section template on the base plate, and suspending and fixing the chamfered section template through the suspension part. The suspension part restricts the relative position of the chamfered section template and the chamfered section distribution beam in the vertical direction, enabling rapid connection between the chamfered section distribution beam and the chamfered section template in a vertical state.
[0011] As a preferred embodiment of the present invention, the limiting and fixing includes: vertically connecting an extension member to the chamfered section template, the extension member passing through the chamfered section distribution beam and then fixedly connecting a limiting member, the limiting member abutting against the chamfered section distribution beam, and / or binding the chamfered section template and the chamfered section distribution beam with iron wire. Through the cooperation of the extension member and the limiting member, the relative position of the chamfered section template and the chamfered section distribution beam in the lateral direction is limited, achieving a stable connection between the chamfered section distribution beam and the chamfered section template.
[0012] As a preferred embodiment of the present invention, the fixing of the inner mold of the top plate includes: fixing the main body section to the rigid frame horizontal bracing via tie rods / steel members, and fixing the chamfered section against the inner wall of the arch box to the upper chord tube and the outer mold of the top plate via tie rods. This improves the stability of the inner mold of the top plate and prevents the inner mold of the top plate from slipping along the arch rib line direction.
[0013] As a preferred embodiment of the present invention, the method further includes the step of setting a patch template on the outside of the hinge joint between the main body section and the chamfer section after the inner mold of the top slab is fixed. This ensures the integrity of the inner mold of the top slab and provides a complete pouring space for the pouring of the top slab concrete.
[0014] As a preferred embodiment of the present invention, during the first lifting, a transverse support rod is provided at the bottom of the main body section; during the second lifting, the two oppositely arranged chamfered sections are connected by a connector. This ensures the structural stability of the top plate inner mold during the lifting process, avoiding uncontrollable shaking or displacement, and improving construction safety.
[0015] As a preferred embodiment of the present invention, several inner formworks of the roof slab are rotated and used in the form of segmental units through a passageway along the arch rib alignment. This enables rapid turnover of the inner formworks of the roof slab and improves the overall construction efficiency of the roof slab.
[0016] An arch bridge external concrete roof slab formwork includes an inner roof slab formwork and an outer roof slab formwork. The inner roof slab formwork includes several longitudinally spliced segmental units. Adjacent segmental units are bolted together by end node plates. Each segmental unit includes a main body segment and chamfered segments hinged to both sides of the main body segment. Each segmental unit is installed using the arch bridge external concrete roof slab formwork construction method described above.
[0017] The present invention provides an arch bridge external concrete top slab formwork, which achieves structural adjustability and high installation flexibility through the hinged connection of the main body section and the chamfer section. It can be installed separately in conjunction with the above-mentioned construction methods, and is installed and shaped using the above-mentioned construction methods. It has a high degree of matching with the arch rib line and can ensure the linear quality of the formed concrete.
[0018] In summary, due to the adoption of the above technical solutions, the beneficial effects of the present invention's method for constructing an outer concrete roof slab formwork for an arch bridge are: 1. The main body and chamfer sections of the inner mold of the top plate are assembled separately by suspending the inner mold of the top plate with lifting tools, so as to realize the installation of the inner mold of the top plate without support frame, avoiding the risk of support frame slippage and the problem of occupying the limited space inside the box; 2. By creating a passageway below the main section of the top inner mold, the construction of other structures inside the arch box is facilitated, and space is provided for the assembly of the top slab formwork arch box; 3. By setting up a construction platform at the bottom of the main section of the inner formwork of the top slab, an installation position is provided for fixing the inner formwork of the top slab, which facilitates the installation of the top slab formwork; 4. The passageway provides a channel for the reuse of the roof slab formwork, so that the next section of roof slab formwork can be installed without waiting for the current roof slab construction to be completed, which effectively improves construction efficiency; The beneficial effects of the concrete roof slab formwork for an arch bridge according to the present invention are: 1. The main body section and chamfer section are connected by hinges, which makes the structure of the top slab formwork adjustable, and the installation is highly flexible. It can be installed separately in conjunction with the above construction methods. 2. By using the above construction method for installation and shaping, the matching degree with the arch rib line is high, which can ensure the linear quality of the formed concrete. Attached Figure Description
[0019] Figure 1 This is a construction flowchart of a method for constructing an outer concrete roof slab formwork for an arch bridge, as described in Example 1. Figure 2 This is the cross-sectional state of the arch rib before the construction of the top slab formwork; Figure 3 These are the construction status diagrams corresponding to steps one and two in Example 1; Figure 4 yes Figure 3 Enlarged structural diagram at point A; Figure 5 This is the construction status diagram corresponding to step three in Example 1; Figure 6 This corresponds to the construction state in step four of Example 1. Figure 1 ; Figure 7 This corresponds to the construction state in step four of Example 1. Figure 2 ; Figure 8 yes Figure 7 A magnified structural diagram of section B in the middle; Figure 9 This is the construction status diagram corresponding to step six in Example 1; Figure 10 This corresponds to the construction state in step seven of Example 1. Figure 1 ; Figure 11 This corresponds to the construction state in step seven of Example 1. Figure 2 ; Figure 12 This is a structural schematic diagram of a concrete roof slab formwork for an arch bridge according to the present invention; Figure 13 This is a structural schematic diagram of the combination of longitudinal beams and transverse distribution beams in the main section; Figure 14 This is the installation layout diagram of the main section relative to the arch ribs.
[0020] icon: 11-Top slab, 12-Bottom slab, 13-Rigid frame horizontal bracing, 14-Upper chord tube, 15-Passageway, 2-Lifting tools, 21-Vertical steel pipe column, 22-Horizontal bar, 23-Limiting steel column, 24-Suspension rod, 3-Inner formwork of top slab, 31-Main body section, 32-Formwork component, 321-Longitudinal beam, 322-Transverse distribution beam, 323-Longitudinal distribution beam, 324-Building formwork, 325-End node plate, 33-Chamfered section, 331-Chamfered section distribution beam, 332-Chamfered section formwork, 34-Lifting connection area, 35-Insertion formwork, 36-Transverse support rod, 4-Construction platform, 5-Sleeper, 61-Suspension part, 62-Extension piece, 63-Limiting piece, 64-Iron wire, 65-Tie rod, 66-Steel component, 7-Outer formwork of top slab. Detailed Implementation
[0021] The present invention will now be described in detail with reference to the accompanying drawings.
[0022] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the invention.
[0023] Example 1 This embodiment uses a currently under-construction, world's largest span rigid-frame arch bridge as an example. The main bridge is a 600m span, upper-bearing, rigid-frame concrete arch bridge. The arch ring consists of two parallel arch ribs and inter-rib bracing. The arch ring is constructed using the steel-concrete composite rigid-frame method, with the rigid frame serving as support for the outer concrete pour. Compared to existing rigid-frame arch bridges, the increased span leads to a longer construction period, increased construction materials, and increased difficulty in high-altitude operations. Figure 2 As shown, after the construction of the base plate 12 and the web plate is completed, the top plate formwork needs to be installed for the pouring of the top plate 11.
[0024] This embodiment of a method for constructing a concrete roof slab formwork for an arch bridge specifically includes: Step 1: Set up lifting tool 2 above the top plate 11, such as... Figure 3 As shown.
[0025] Preferably, the lifting tool 2 includes a hoist tool, which can be an electric hoist or a hand-operated hoist. The hoist tool is small in size and can be easily installed in a space-constrained arched box.
[0026] Preferably, since the arch box is a steel pipe arch rib truss structure with a through surface at the top before the inner mold 3 of the top plate is installed, in this embodiment, the top support is set by welding vertical steel pipe columns 21 to the top of the upper chord tube 14, and by welding limiting steel columns 23 to the bottom of the crossbars 22 whose length is adapted to the width of the arch rib. The top support is set by inserting the limiting steel columns 23 into the vertical steel pipe columns 21. The top support is formed by installing suspension rods 24 along the longitudinal direction of the arch rib on the top support, which is used to suspend and install the lifting tools 2.
[0027] Preferably, in this embodiment, the steel components constituting the frame-type top support are I-beams and / or channel steel to ensure structural strength and thus ensure the stability and safety of the top slab formwork lifting process.
[0028] Preferably, the hoisting tools are positioned above the steel back ribs of the inner mold 3 of the top plate, in a four-point distribution, to achieve stable lifting of the inner mold 3 of the top plate. The hoisting tools can also be used to ensure that the top plate template is installed and fixed in a state consistent with the inclination of the arch rib line, thereby improving the installation accuracy of the top plate template.
[0029] Step 2: Assemble the main body section 31 of the inner mold 3 of the top plate onto the base plate 12, as follows: Figures 3-4 As shown.
[0030] Preferably, the method includes: laying sleepers 5 on the base plate 12, laying and connecting template components 32 on the sleepers 5, and leaving hoisting connection areas 34 on both sides of the top of the main body section 31. The template components 32 include longitudinal beams 321, transverse distribution beams 322, longitudinal distribution beams 323 and building templates 324 arranged sequentially from bottom to top.
[0031] Preferably, in this embodiment, the longitudinal beam 321 adopts three double-channel steel back ribs, and sleepers 5 are set at the bottom of each longitudinal beam 321; the transverse distribution beam 322 adopts several double-channel steels arranged at intervals, and the transverse distribution beam 322 is spot-welded to the longitudinal beam 321; the longitudinal distribution beam 323 adopts square timber, and the square timber is connected to the transverse distribution beam 322 through connecting claws; the building formwork 324 adopts bamboo plywood. During assembly, the square timber and bamboo plywood at the top positions of both ends of the transverse distribution beam 322 are not laid, that is, the square timber and bamboo plywood above the corresponding sides of the longitudinal beam 321 are used to form the hoisting connection area 34, so that the hoisting hoist tool can be connected to the longitudinal beam 321 to achieve lifting, ensuring the stable lifting of the top plate inner mold 3 and the overall stability of the structure during the lifting process.
[0032] Step 3: Lift the object once using lifting tool 2, such as... Figure 5 As shown.
[0033] Preferably, before lifting, prepare a Φ20mm steel wire rope, then lower the hoist tool, wrap the steel wire rope around the longitudinal beam 321, and then connect and fix it to the hoist tool from the other side. Add rubber pads at the position of the longitudinal beam 321 to prevent the steel wire rope from being cut. After the hoist tool is installed, weld angle steel to the bottom of the longitudinal beam 321 as a transverse support rod 36, connect the three double-channel steel back ribs into a whole, and lift synchronously to lift the main body section 31 to about 1.6m above the ground, stop lifting, and then proceed to the next step.
[0034] Preferably, when the wire rope needs to pass through the template, a Φ30mm channel is set at the corresponding position on the template of the main body section 31 for the Φ20mm wire rope to pass through. The wire rope is passed through the channel, around the longitudinal beam 321, and then out through the channel on the other side to be connected and fixed to the hoist tool. After the channel is used, it is sealed with foam glue.
[0035] Step 4: Suspend and assemble the inner formwork 3 of the top slab, including the installation of the chamfered section distribution beam 331 and the chamfered section template 332, as follows. Figures 6-8 As shown.
[0036] Preferably, the installation of the chamfered section distribution beam 331 specifically includes: connecting the chamfered section distribution beam 331 one by one to the transverse distribution beam 322 of the main body section 31 with bolts, loosening the bolt hinges, keeping the chamfered section distribution beam 331 suspended, so that each chamfered section distribution beam 331 is in a vertically lowered state.
[0037] Preferably, the two chamfered segments 33, which are arranged opposite to each other and in a vertically downward state, are connected by a connector.
[0038] Specifically, the connector can be a steel bar or a steel plate, which is welded and fixed to the chamfered section distribution beam 331 to fix the chamfered section distribution beam 331, so that the inner formwork 3 of the top plate is structurally stable during the lifting process, avoiding uncontrollable shaking, displacement, etc., and improving construction safety.
[0039] Preferably, the chamfered section template 332 has the same structure as the template component 32 of the main section 31, including square timber and bamboo plywood. The installation of the chamfered section template 332 specifically includes: setting a suspension part 61 on the outside of the chamfered section distribution beam 331, assembling the chamfered section template 332 on the base plate 12, and suspending and fixing the chamfered section template 332 through the suspension part 61.
[0040] Specifically, since the chamfered section distribution beam 331 includes a first section and a second section set at an angle, the first section is in a vertical state in step four. The corresponding chamfered section template 332 is obtained by measuring the template installation position in advance and obtaining the position of the top square timber of the template on the chamfered section distribution beam 331. Steel components such as angle steel, channel steel, and steel plate are welded below the corresponding position as a suspension part 61. The suspension part 61 supports the square timber in the template component 32 and bears the weight of the template, thereby achieving the limiting and fixing of the first chamfered section template 332 in the height direction. The second section is in an inclined state in step four and is temporarily fixed by binding at least two iron wires 64.
[0041] Specifically, such as Figure 8 As shown, to prevent the chamfered section template 332 from tilting outward, at least two limiting components are provided on the chamfered section template 332. The limiting components include an extension 62 that is vertically connected to the chamfered section template 332. The extension 62 passes through the chamfered section distribution beam 331 and is fixedly connected to the limiting component 63. The limiting component 63 abuts against the chamfered section distribution beam 331. In this embodiment, the extension 62 is made of wood strips, and the limiting component 63 is made of wood strips or blocks and connected by nails. The extension 62 is connected to the template square timber by nails and is connected to the limiting component 63 after passing through the chamfered section distribution beam 331. The limiting component 63 is located below the extension 62 in the height direction to achieve the limiting and fixing of the chamfered section template 332 in the lateral direction.
[0042] Step 5: Use lifting tool 2 for a second lifting operation.
[0043] Specifically, using a hoist, the top slab template 3 is further lifted to a position where the main body section 311 is at least 2m away from the bottom slab, providing construction space for the installation of the construction platform 4.
[0044] Step 6: Set up construction platform 4 at the bottom of main section 31, such as... Figure 9 As shown.
[0045] Preferably, the construction platform 4 is formed by connecting a steel frame to the bottom of the main body section 31 and laying platform components.
[0046] Specifically, in this embodiment, the construction platform 4 is made of angle steel, and the angle steel is connected by bolts. During installation, the upper angle steel is welded to the transverse distribution beam 322 of the main body section 31, and then the hangers, longitudinal bars, and transverse bars are installed in sequence. After the installation is completed, the construction platform 4 is formed by laying steel planks and binding triangular wood and other platform components, which facilitates the movement of workers. The width of the construction platform 4 is adaptively adjusted according to the width inside the arch box.
[0047] Step 7: Raise the formwork to the top slab elevation 11, fix the inner formwork 3 of the top slab within the construction platform 4, and form a passageway 15 below the construction platform 4. Figures 10-12 As shown.
[0048] Preferably, step seven specifically includes: welding and fixing the main body section 31 to the rigid frame horizontal bracing 13 via tie rod 65 to fix the main body section 31; after welding and fixing, releasing the hoist tool and the limiting measures of the chamfer section 33 to complete the lifting operation of the inner mold 3 of the top plate; then manually pushing and pulling the chamfer section distribution beam 331 towards the web to make it fit with the already poured web and temporarily fixing it; then fixing it to the upper chord tube 14 and the outer mold 7 of the top plate via tie rod 65 to realize the installation of the inner mold 3 of the top plate.
[0049] Preferred, such as Figure 14 As shown, in order to further improve the installation stability of the main body section 31, the main body section 31 is fixed to the stiffening frame flat bracing 13 by welding steel components 66 on the basis of fixing the tie rod 65.
[0050] Step 8: After the inner formwork 3 of the top slab is fixed, a patch template 35 is installed on the outside of the hinge joint between the main body section 31 and the chamfered section 33. The patch template 35 is made of wood templates measured on site and installed in the hoisting connection area 34 of the original hoisting tool. It is fixed with nails and the gaps are filled with foam glue to ensure the integrity of the inner formwork 3 of the top slab and provide a complete pouring space for the concrete pouring of the top slab.
[0051] This embodiment describes a construction method for the outer concrete roof slab formwork of an arch bridge. The inner roof slab formwork 3 is suspended by a lifting tool 2, allowing for the separate assembly of the main body section 31 and the chamfered section 33 of the inner roof slab formwork 3. This enables the inner roof slab formwork 3 to be installed without supports, avoiding the risk of support frame slippage and the problem of occupying limited space within the box girder. It provides space for the assembly of the roof slab formwork within the arch box. Simultaneously, a construction platform 4 is set at the bottom of the main body section 31 of the inner roof slab formwork 3, providing a fixed installation position and facilitating the installation of the roof slab formwork. Furthermore, a passageway 15 is formed below the main body section 31 of the inner roof slab formwork 3, facilitating the construction of other structures within the arch box and providing a channel for the reuse of the roof slab formwork 3. This allows the next segment of the roof slab formwork to be installed without waiting for the current roof slab 11 to be completed, effectively improving construction efficiency.
[0052] Example 2 like Figures 1-12 As shown in this embodiment, a method for constructing an outer concrete top slab formwork for an arch bridge is based on embodiment 1. Several inner top slab formwork 3 are used in a segmental unit formwork via a passageway 15 along the direction of the arch rib.
[0053] This embodiment describes a method for constructing an outer concrete top slab formwork for an arch bridge. At least two sets of top slab formwork are prepared along the axis of the arch rib. During the curing period after the completion of the current segment's top slab 11, materials can be transferred through the passageway 15 to install the top slab formwork for the next segment to be poured, thereby achieving rapid turnover of the inner formwork 3 of the top slab and improving the overall construction efficiency of the top slab.
[0054] Example 3 like Figures 1-14 As shown, a formwork for the outer concrete slab of an arch bridge includes an inner formwork 3 and an outer formwork 7. The inner formwork 3 includes several longitudinally spliced segmental units, and adjacent segmental units are bolted together by end node plates 325. Each segmental unit includes a main body segment 31 and chamfered segments 33 hinged to both sides of the main body segment 31. Each segmental unit is installed using the construction method for the outer concrete slab of an arch bridge as described above.
[0055] This embodiment of an arch bridge external concrete top slab formwork achieves structural adjustability and high installation flexibility through the hinged connection between the main body section 31 and the chamfered section 33. It can be installed separately in conjunction with the above construction method and formed by the above construction method. It has a high degree of matching with the arch rib line and can ensure the linear quality of the formed concrete.
[0056] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A method for constructing a concrete roof slab formwork for an arch bridge, characterized in that, include: Lifting tools (2) are installed above the top plate (11); Assemble the main body section (31) of the inner mold (3) of the top plate on the base plate (12) and lift it once using a lifting tool (2); The inner formwork of the suspended top plate (3) is chamfered (33) and then lifted a second time. A construction platform (4) is set at the bottom of the main section (31) and raised to the elevation of the top slab (11); The inner formwork (3) of the top plate is fixed inside the construction platform (4), and a passageway (15) is formed below the construction platform (4). The top support is set up by welding a vertical steel pipe column (21) to the top of the upper chord (14) and welding a limiting steel column (23) to the bottom of a crossbar (22) whose length is adapted to the width of the arch rib. The limiting steel column (23) is inserted into the vertical steel pipe column (21). A frame-type top support is formed by installing a suspension rod (24) along the longitudinal direction of the arch rib on the top support, which is used to suspend and install lifting tools (2). The construction platform (4) is formed by connecting a steel frame to the bottom of the main body section (31) and laying platform components; Several top plate inner molds (3) are used in the form of segmental units through the passageway (15) along the arch rib line direction.
2. The construction method for the external concrete roof slab formwork of an arch bridge as described in claim 1, characterized in that, The main body section (31) of the assembled top plate inner formwork (3) includes: sleepers (5) laid on the bottom plate (12), template components (32) laid on the sleepers (5) and connected, and hoisting connection areas (34) left on both sides of the top of the main body section (31). The template components (32) include longitudinal beams (321), transverse distribution beams (322), longitudinal distribution beams (323) and building templates (324) arranged sequentially from bottom to top.
3. The construction method for the formwork of the outer concrete roof slab of an arch bridge as described in claim 2, characterized in that, The chamfered section (33) of the assembled top plate inner formwork (3) includes: hinged chamfered section distribution beam (331) at the end of the transverse distribution beam (322) of the main body section (31), loosening the hinged part to keep the chamfered section distribution beam (331) suspended, and then installing the chamfered section template (332).
4. The construction method for the formwork of the outer concrete roof slab of an arch bridge as described in claim 3, characterized in that, The installation of the chamfer section template (332) includes: setting a suspension part (61) on the outside of the chamfer section distribution beam (331), assembling the chamfer section template (332) on the base plate (12), and suspending the chamfer section template (332) through the suspension part (61) and fixing it in a limited position.
5. A method for constructing a concrete roof slab formwork for an arch bridge as described in claim 4, characterized in that, The limiting and fixing includes: vertically connecting an extension (62) to the chamfered section template (332), the extension (62) passing through the chamfered section distribution beam (331) and then fixing a limiting member (63) thereto, the limiting member (63) abutting against the chamfered section distribution beam (331), and / or binding the chamfered section template (332) and the chamfered section distribution beam (331) with iron wire (64).
6. The construction method for the formwork of the outer concrete top slab of an arch bridge as described in claim 1, characterized in that, The fixing of the inner mold (3) of the top plate includes: fixing the main body section (31) to the stiffening frame flat bracing (13) by means of tie rod (65) / steel component (66), and fixing the chamfered section (33) against the inner wall of the arch box to the upper chord tube (14) and the outer mold (7) of the top plate by means of tie rod (65).
7. A method for constructing a concrete roof slab formwork for an arch bridge as described in claim 1, characterized in that, It also includes the step of setting a patch template (35) on the outside of the hinge of the main body section (31) and the chamfer section (33) after the inner mold (3) of the top plate is fixed.
8. A method for constructing a concrete roof slab formwork for an arch bridge as described in claim 1, characterized in that, During the first lifting, a horizontal support rod (36) is provided at the bottom of the main body section (31). During the second lifting, the two chamfered sections (33) that are set opposite to each other are connected by a connector.
9. A formwork for the outer concrete roof slab of an arch bridge, characterized in that, The system includes an inner formwork and an outer formwork. The inner formwork (3) comprises several longitudinally spliced segmental units. Adjacent segmental units are bolted together by end node plates (325). Each segmental unit includes a main body segment (31) and chamfered segments (33) hinged to the transverse sides of the main body segment (31). Each segmental unit is installed using a construction method for an arch bridge outer concrete top slab formwork as described in any one of claims 1-8.
Citation Information
Patent Citations
Novel SCC construction-method moving hanging basket for corrugated steel webs and construction method of hanging basket
CN105625195A
Construction method for reinforced concrete box-type arch bridge
CN108589535A