A method for butt welding of a group of air separation unit tower type equipment
By employing lifting and jack support methods in the assembly and welding of tower-type equipment in air separation units, and by welding in sections and adjusting verticality, the problems of high welding difficulty and difficulty in controlling misalignment were solved, achieving efficient and low-cost welding results.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- CHINA THIRD METALLURGICAL GRP
- Filing Date
- 2023-06-29
- Publication Date
- 2026-06-26
AI Technical Summary
The welding of the tower equipment inside the air separation cold box is difficult, the weld is prone to deformation, and it is difficult to guarantee the amount of welding misalignment and the verticality of the equipment, resulting in time-consuming, labor-intensive and costly construction.
Lifting and hoisting equipment was used to assemble the upper and lower tower bodies, and the welds were evenly distributed and welded in sections. Jacks were used to support and adjust the verticality. A symmetrical and segmented welding sequence was adopted, combined with double-person double-sided argon arc welding technology, to monitor and adjust the misalignment and verticality.
It improved welding efficiency, saved construction costs, ensured weld quality and equipment verticality, and provided a safe and stable construction guarantee.